• Tidak ada hasil yang ditemukan

Supplemental Bid Bulletin No. 1 - Department of Finance

N/A
N/A
Protected

Academic year: 2024

Membagikan "Supplemental Bid Bulletin No. 1 - Department of Finance"

Copied!
4
0
0

Teks penuh

(1)

Republic of the Philippines

DEPARTMENT OF FINANCE

Roxas Boulevard Corner Pablo Ocampo, Sr. Street Manila 1004

BIDS AND AWARDS COMMITTEE Supplemental Bid Bulletin No. 1

April 11, 2022

Supply, Delivery and Installation of Furniture / Fixtures / Workstations for the DOF 8th Floor Offices, EDPC Building

ITB No. 2022-02-G

This Supplemental Bid Bulletin No. 1 is issued to modify or amend the item in the Bid Documents. This shall form an integral part of the Bid Documents.

REFERENCE AMENDMENT/CHANGE/ CLARIFICATION

Page 40, Technical Specifications

Bidders must state here either “Comply” or “Not Comply” against each of the individual parameters of each Specification stating the corresponding performance parameter of the equipment offered. A statement in the Bidder's statement of compliance that is found to be false either during Bid evaluation, post-qualification or the execution of the Contract may be regarded as fraudulent and render the Bidder or supplier liable for prosecution subject to the applicable laws and issuances.

Bidders must state here either “Comply” or “Not Comply” against each of the individual parameters of each Specification stating the corresponding performance parameter of the equipment offered. Statements of “Comply”

or “Not Comply” must be supported by evidence in a Bidders Bid and cross- referenced to that evidence. Evidence shall be in the form of manufacturer’s un- amended sales literature, unconditional statements of specification and compliance issued by the manufacturer, samples, independent test data etc., as appropriate. A statement that is not supported by evidence or is subsequently found to be contradicted by the evidence presented will render the Bid under evaluation liable for rejection. A statement either in the Bidder's statement of compliance or the supporting evidence that is found to be false either during Bid evaluation, post-qualification or the execution of the Contract may be regarded as fraudulent and render the Bidder or supplier liable for prosecution subject to the applicable laws and issuances.

Page 40, Technical Specifications

Item Specifications Statement of Compliance 3 Manpower

requirements a. One (1)

Licensed Interior Designer, at least 3 years’

Page 40, Technical Specifications

Item Specifications Statement of Compliance 3 Manpower

requirements a. Project

Lead/Coordinator, graduate of

(2)

2

REFERENCE AMENDMENT/CHANGE/ CLARIFICATION

experience, preferably graduate of Interior Design Course (submit CV);

b. Production Supervisor, at least 3 years’

experience, preferably graduate of relevant 4 year course (submit CV)

relevant 4 year course (e.g.

interior designer, architect,

industrial engineer,

etc.)(submit CV);

b. Production Supervisor, minimum 5 years relative

experience (submit CV)

Page 30, Special Conditions of Contract GCC

Clause

4

The inspections and tests that will be conducted are:

All furniture / fixtures / workstations to be

delivered on-site must be compliant with the DOF required specifications.

The winning bidder must provide a mock set-up of the workstation, including samples of the office chairs.

Page 30, Special Conditions of Contract GCC

Clause

4

The inspections and tests that will be conducted are: All furniture / fixtures / workstations to be delivered on-site must be

compliant with the DOF required specifications. The bidder with the Lowest Calculated Bid (LCB) must provide a mock set-up of the workstation, including samples of the office chairs during post-qualification phase.

(3)

3

REFERENCE AMENDMENT/CHANGE/ CLARIFICATION

Page 41, Technical Specifications

Item Specifications Statement of Compliance

5

Inspection

The inspections and tests that will be conducted are: All furniture/fixtures/

workstations to be delivered on-site must be compliant with the DOF required

specifications. The winning bidder must provide a mock set- up of the workstation, including samples of the office chairs.

Page 41, Technical Specifications

Item Specifications Statement of Compliance

5

Inspection

The inspections and tests that will be conducted are: All furniture/fixtures/

workstations to be delivered on-site must be compliant with the DOF required

specifications. The bidder with the Lowest Calculated Bid (LCB) must provide a mock set- up of the

workstation,

including samples of the office chairs during post- qualification phase.

Page 42-61, Technical Specifications Original Specifications:

Item Description

Statement Of Compliance

Desk Grommet

Provide 60mm diameter zinc alloy chrome plated grommet per work desk.

Partition thickness

45mm thk.

Aluminum powder coated framed partitions with 2- 6mm

Page 42-61, Technical Specifications Replace all corresponding specifications with:

Item

Statement Of Compliance

Desk Grommet

Provide 60mm diameter black plastic PU grommet per work desk to eliminate electrical grounding

Partition thickness

45mm-50mm thk. Aluminum powder coated framed partitions with 2-6mm thk.

(4)

4

REFERENCE AMENDMENT/CHANGE/ CLARIFICATION

thk. Fabric tile with

……….

Workstation Partition height

…….total height of partition shall be 1200mm.

Provide 1200mm height aluminum framed fabric partition and provide polished stainless steel + nylon adjustable glider for partitions.

Fabric tile with

……….

Workstation Partition height

…….total height of partition shall be 1.1m.

Provide 1.1m height

aluminum framed fabric partition and provide polished stainless steel + nylon adjustable glider for partitions.

For guidance and information of all concerned.

MARIA EDITA Z. TAN Undersecretary and BAC Chairperson

Name Initial Date

Eden C. Zamora Liceria A. Te J. Establecida

Referensi

Dokumen terkait

Page 35 12.1.a iii Statement identifying the bidder’s single largest completed contract similar to the bid, except under conditions provided for in Section 23.5.1.3 of IRR of R.A.. The

3 September 24, 2021 Procurement of Various Food Items for the Department of Finance ITB No.. 3 is issued to modify or amend the item in the Bid

Technical Specifications Delete Deadline for submission of 1 Storyboard for AVPs and TVCs, 2 Curriculum Vitae of key members, and 3 Previous Works will be on January 25, 2018, 3:00 PM

Technical Specifications Please refer to attached diagram for the detailed specifications None The schedule on the submission of bids is July 31, 2017, 9:45 a.m.. at the BAC

Authority registration ‐ Mayor’s permit ‐ Tax Clearance ‐ Joint Venture Agreement if applicable ‐ Audited Financial Statement stamped received by BIR ‐Latest Income and Business Tax

REFERENCE AMENDMENT/CHANGE/CLARIFICATION Page 3 Request for Quotation The schedule of bidding activities are as follows: ACTIVITIES Schedules Posting of Request for Quotation

REFERENCE AMENDMENT/CHANGE/CLARIFICATION Page 3 Request for Quotation The schedule of bidding activities are as follows: ACTIVITIES Schedules Posting of Request for Quotation

Description Delivery Schedule Bidder's Compliance 1 50 Laptop 30 days 2 60 Computer, work station, set 30 days Page 64 Section VI Schedule of Requirements Item No... BELTRAN