Pelaksanaan kegiatan pemboran di wilayah tambang IM dilakukan oleh konsultan yang ditunjuk oleh IM dan diawasi oleh Departemen Engineering seksi Geologist IM.
Kemajuan Eksplorasi Exploration Progress
Bulan | Month Deksripsi | Description
Januari | January
Februari | February Kegiatan eksplorasi masih berfokus pada kajian geotek untuk area disposal.Exploration activities still focused on geotech studies for disposal areas.
Maret | March
April | April Kegiatan eksplorasi masih berfokus pada kajian geotek untuk area disposal dan OLC.Exploration activities are still focused on geotech studies for disposal and OLC areas.
Mei | May Kegiatan pemboran dengan total 1.082,6 meter (1 Mei 2016 – 1 Juni 2016).
Drilling activities in total of 1,082.6 meters (May 1, 2016 - June 1, 2016).
Juni | June Total pemboran sejumlah 1.082,6 meter | Total drilling of 1,082.6 meters.
Juli | July Tidak ada kegiatan eksplorasi | No exploration activities.
Agustus | August Tidak ada kegiatan eksplorasi | No exploration activities.
September | September Tidak ada kegiatan eksplorasi | No exploration activities.
Oktober | October Telah selesai dilakukan 1 titik pemboran geotek dan pemasangan alat inclinometer, sekaligus pengambilan
data geotek dan melakukan pemboran inill di area Pit A sebanyak 9 titik dengan total kedalaman 1039,63
meter.
Geotech drilling and inclinometer installation have been completed, as well as geotech data collection and
inill drilling in the Pit A area of 9 points with a total depth of 1039.63 meters.
November | November Telah selesai dilakukan 3 titik pemboran geotek dan sekaligus
pemasangan alat inclinometer dengan kedalam 30–40 meter. Untuk selanjutnya akan dilakukan pemboran
lanjutan dan pemasangan alat inklinometer sebanyak 1 titik tersisa. Untuk pemboran Inill pada bulan ini
telah selesai 2 titik dari 9 titik yang direncanakan.
Three geotech drilling points have been completed and at the same time,Installation of inclinometer in depth level of 30-40 meters. Further drilling and inclinometer increments will be carried out to the
remaining 1 point. On this month, Inill drilling has completed 2 points from 9 planned points.
Desember | December Telah selesai dilakukan 1 titik pemboran geotek pada titik bor INC PK 23-02 dan sekaligus pemasangan alat
inclinometer dengan kedalam 42 meter, sehingga pada akhir Desember 2016 total keseluruhan pemboran geotek yang telah diselesaikan 4 titik dari yang telah direncanakan yaitu pada titik bor INC PK 23-03, titik bor INC PK 23-04, titik bor INC-PK 23-01, titik bor INC PK 23-02 dengan total kedalaman keseluruhan 146
meter. Selanjutnya, untuk pemboran Inill pada Desember 2016 yang menggunakan 1 unit mesin bor yaitu
Rig Jacro 200 telah menyelesaikan 4 titik bor yaitu pada titik ID-05. ID-02, ID-04 dan ID-09 dari 3 titik yang tersisa, adapun total keseluruhan titik bor yang telah diselesaikan sampai dengan akhir bulan Desember 2016 berjumlah 6 titik dengan total kedalaman keseluruhan 758,98 meter yaitu pada titik bor ID-03, titik bor ID-06, titik bor ID-05, titik bor ID-02, titik bor ID-04, titik bor ID-09 dari 9 titik bor yang direncanakan.
Geotech drilling has been done at the point of drilling INC PK 23-02 and at the same time installation of inclinometer in depth level of 42 meters has been completed, so at the end of December 2016, the total geotech drilling has completed 4 points from the planned drill point INC PK 23 -03, drill point INC PK 23-04, drill point INC-PK 23-01, drill point INC PK 23-02 with total depth overall 146 meters. Furthermore,
on December 2016, Inill drilling which used 1 drilling machine unit i.e Rig Jacro 200 has completed 4 drill
point at point ID-05. ID-02, ID-04 and ID-09 of the remaining 3 points, while the total number of drill points completed by the end of December 2016 was 6 points with a total depth of 758.98 meters at the drill point ID-03, the drill point ID-06, drill point ID-05, drill point ID-02, drill point ID-04, drill point ID-09 of 9 planned drill points.
Rencana Pemboran Selanjutnya Subsequent Drilling Plan
Bulan | Month Deskripsi Rencana | Plan Description
Februari 2016
February 2016 Tetap melakukan update terhadap model geologi.Kept updating the geological model.
Maret 2016
March 2016
April 2016
April 2016
Melakukan update plan pemboran pada area pit (inill drilling) serta pemboran geotek pada pit dan OPD2.
Updated drilling plan in pit area (inill drilling) and conducted geotech drilling on pit and OPD2.
Mei 2016
May 2016 Melakukan kegiatan pemboran pada area PIT (inill drillingadalah 1.019,5 meter. ), dengan total kedalaman dari rencana 14 titik bor
Conducted drilling activities in PIT area (inill drilling), with total depth of 14 point drill in 1,019,5 meter.
Juni 2016
June 2016 Melakukan kajian update model berdasarkan data pemboran yang dihasilkan.Conducted model update reviews based on the resulting drilling data.
Juli 2016
July 2016 Mengkaji penggunaan alat inclinometer untuk monitoring disposaldilakukan pemboran di 8 titik berdasarkan rekomendasi dwi eltis. OPD2. Melalui penggunaan alat tersebut, akan
Assessed the use of inclinometer tools for OPD2 disposal monitoring. Using the tool, drilling would be conducted at 8 points based on bi-elastic recommendations.
Agustus 2016
August 2016 Masih melakukan kajian update model berdasarkan data pemboran yang dihasilkan.Still reviewing update model based on the resulting drilling data.
September 2016
September 2016 Melakukan pemboran geotek dan pemasangan alat inclinometer sebanyak 4 titik.Carrying out Geotech drilling and installation of inclinometer tools in 4 points.
Oktober 2016
October 2016 Melakukan update model geologi sesuai dengan data kemajuan penambangan.Updating geological model according to mining progress data.
November 2016
November 2016 Masih melanjutkan sisa 3 titik pemboran untuk pemasangan alat inclinometer dan sekaligus pengambilan data geotek serta akan melakukan pemboran inill di area Pit A IM sebanyak 9 titik dengan total kedalaman 1.039,6
meter.
Still continued drilling in the remaining 3 points of drilling to install inclinometer and simultaneously took
geotech data and would do inill drilling in Pit A IM area 9 points with total depth of 1,039.6 meters.
Desember 2016
December 2016 Masih melanjutkan sisa 1 titik pemboran untuk pemasangan alat inclinometer dan sekaligus pengambilan data geotek serta melanjutkan pemboran inill di area Pit A IM sebanyak 7 titik tersisa.
Still continued drilling in the remaining 1 point of drilling for installing inclinometer tools and simultaneously
taking geotech data as well as continuing Inill drilling in the Pit A IM area of 7 remaining points.
Januari 2017
January 2017 Melanjutkan sisa titik pemboran dengan sisa total kedalaman 280,7 meter.inill di area Pit A IM sebanyak 3 titik tersisa yaitu pada titik ID-08, ID-07, ID-01
Continued the remaining inill drilling points in the Pit A IM area of 3 remaining points at the point ID-08, ID-07,
ID-01 with the remaining total depth of 280.7 meters.