PAGE 1 MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 17 DECEMBER 2019
PRESENT
Cameron McKenzie Group Manager – Development & Compliance (Chair) Paul Osborne Manager – Development Assessment
Benjamin Hawkins Manager – Subdivision & Development Certification Angelo Berios Manager – Environment & Health
Amanda Burke Acting Manager – Regulatory Services Nicholas Carlton Manager – Forward Planning
Kristine McKenzie Principal Executive Planner
APOLOGIES
Craig Woods Manager – Regulatory Services
TIME OF COMMENCEMENT 8:30am
TIME OF COMPLETION 8:49am
ITEM-1 CONFIRMATION OF MINUTES
RESOLUTION
The Minutes of the Development Assessment Unit Meeting of Council held on 26 November 2019 be confirmed.
ITEM-2 DA 818/2017/HC – ALTERATIONS AND ADDITIONS TO AN EXISTING PLACE OF WORSHIP – LOT 2 AND 3 DP 252239, NOS. 167 AND 169 FOXALL ROAD, NORTH KELLYVILLE
PUBLIC NOTIFICATION OF THE DETERMINATION PURSUANT TO ITEM 2(2)(c) AND (d) OF SCHEDULE 1 OF THE ENVIRONMENTAL PLANNING 7 ASSESSMENT ACT, 1979
DECISION:
The development application be approved subject to conditions in the report.
PAGE 2 REASONS FOR THE DECISION:
Sections 4.15 and 4.65-4.70 (EP&A Act) – Satisfactory.
Clauses 39-46 (EP&A Regulations) – Satisfactory.
SEPP Sydney Region Growth Centres 2006 – Satisfactory, permissible with consent under the provisions of existing use rights.
State Environmental Planning Policy No. 55 – Remediation of Land – Satisfactory.
North Kellyville DCP – Variation, see report.
THDCP Part C Section 1 – Parking – Variation, see report.
THDCP Part C Section 3 – Landscaping – Variation, see report.
Section 7.12 Contribution: Stage 2: $6,500.00 and Stage 3: $32,546.86.
HOW COMMUNITY VIEWS WERE TAKEN INTO ACCOUNT IN MAKING THE DECISION:
The development application was notified and three (3) submissions including a petition were received. The issues raised were discussed in the report.
ITEM-3 DA 1697/2016/ZD - A SUBDIVISION CREATING 12 COMMUNITY TITLE RURAL RESIDENTIAL LOT AND ONE ASSOCIATION LOT – LOT 103 DP 752047, 85
GIBBS ROAD, KENTHURST PUBLIC NOTIFICATION OF THE DETERMINATION PURSUANT TO ITEM 20(2)(c) AND
(d) OF SCHEDULE 1 OF THE ENVIRONMENTAL PLANNING & ASSESSMENT ACT, 1979
DECISION:
The development application be approved subject to a deferred development commencement condition and conditions of consent.
REASONS FOR THE DECISION:
Section 4.15 (EP&A Act) 1979 – Satisfactory.
The Hills Local Environmental Plan 2019 – Satisfactory.
SEPP 55 – Remediation of Land – Satisfactory.
SREP 20 – Hawkesbury-Nepean River – Satisfactory.
The Hills Development Control Plan 2012 – Part B Section 1 – Rural – Variations sought (see report).
Section 7.12 Development Contribution: $15,730.00
HOW COMMUNITY VIEWS WERE TAKEN INTO ACCOUNT IN MAKING THE DECISION:
The development application was notified and four (4) submissions were received.