ANALISIS KINERJA WAKTU DAN BIAYA DENGAN METODE EARNED VALUE (NILAI HASIL) PADA PROYEK PEMBANGUNAN GEDUNG DHARMA WANITA TAHAP II TARAKAN

N/A
N/A
Protected

Academic year: 2022

Membagikan "ANALISIS KINERJA WAKTU DAN BIAYA DENGAN METODE EARNED VALUE (NILAI HASIL) PADA PROYEK PEMBANGUNAN GEDUNG DHARMA WANITA TAHAP II TARAKAN"

Copied!
12
0
0

Teks penuh

(1)

ii

ANALISIS KINERJA WAKTU DAN BIAYA DENGAN METODE EARNED VALUE (NILAI HASIL) PADA

PROYEK PEMBANGUNAN GEDUNG DHARMA WANITA TAHAP II TARAKAN

Skripsi

Diajukan Kepada Universitas Muhammadiyah Malang Untuk Memenuhi Salah Satu Persyaratan Akademik

Dalam Menyelesaikan Program Sarjana Teknik

DISUSUN OLEH:

ALFIAN SAIFUL ANAM 201410340311077

JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK

UNIVERSITAS MUHAMMADIYAH MALANG

2021

(2)

iv

(3)

v

(4)

vi

LEMBAR PERSEMBAHAN

Tugas akhir ini saya persembahkan untuk orang tua saya ibu Elmi Suprapti dan bapak Imam Kusaeni serta adik-adik saya yang telah mensupport selama proses penulisan naskah skripsi ini. Selain keluarga tentunya berterima kasih untuk sahabat yang sudah seperti keluarga sendiri yaitu D’BODO. Untuk teman sekelas sipil B untuk dukungannya. Pihak-pihak terkait yang telah direpotkan dalam pengambilan data terutama untuk bapak jalil dan bapak agus.

(5)

v

KATA PENGANTAR

Alhamdulillah, segala puji dan syukur kehadirat Allah SWT, pemberi rahmat dan hidayah kepada seluruh manusia. Dengan ridho , izin dan kekuasan-Mu, akhirnya penulis dapat menyelesaikan tugas akhir dengan judul ‘Analisis Kinerja Waktu dan Biaya dengan Metode Earned Value pada proyek pembangunan Gedung Dharma Wanita Tahap II Tarakan’ dengan lancar.

Penulis menyadari bahwa demi terwujudnya tugas akhir ini, penulis mendapat banyak sekali bantuan dari berbagai pihak. Maka dari itu, dengan segala kerendahan hati, penulis mengucapkan terima kasih yang tidak terhingga kepada :

1. Allah SWT, tempat dimana penulis mengadu dan selalu memberikan jalan yang terbaik untuk hamba-Nya.

2. Nabi Muhammad SAW, yang telah menuntun kita dari jalan yang gelap menuju jalan yang terang benderang.

3. Ibu Ir. Rofikatul Karimah, M.T., selaku ketua jurusan Teknik Sipil Universitas Muhammadiyah Malang serta sebagai dosen pembimbing.

4. Bapak Erwin Rommel, selaku dosen wali penulis selama masa perkuliahan.

5. Ibu Ir. Rofikatul Karimah, M.T., selaku dosen pembimbing I dan Ibu Rini Febri Utari, S.Pd., MT., selaku pembimbing II yang telah berbaik hati meluangkan waktu untuk membimbing kepada penulis.

6. Seluruh dosen Teknik Sipil Universitas Muhammadiyah Malang yang telah memberikan ilmunya selama menjalani perkuliahan.

7. Pak Yusuf beserta seluruh staf TU yang sangat membantu mahasiswa untuk urusan jurusan dan kampus.

Malang , 13 Juli 2021

Penulis

(6)

vi

ANALISIS KINERJA WAKTU DAN BIAYA DENGAN METODE EARNED VAUE PADA PROYEK PEMBANGUNAN GEDUNG DHARMA

WANITA TAHAP II TARAKAN

Alfian Saiful Anam

1

, Rofikatul Karimah

2

,Rini Febri Utari

3

123

Jurusan Teknik Sipil, Fakultas Teknik Universitas Muhammadiyah malang

Jl.Raya Tlogomas No. 246 Tlp (0341)464318 Faks (0341)460782 Email : Ajipiyan1@gmail.com

ABSTRAK

Proyek konstriksi saat ini mengalami perkembangan yang cukup pesat seiring dengan perkembangan zaman. Pembuatan rencana kerja adalah salah satu langkah awal dalam perencaan. Rencana awal dibuat untuk menentukan tingkat efektivitas dan efisien selama proyek berlangsung. Dengan menggunakan metode earned value ini dapat mempermudah untuk mengetahui proyek berjalan sesuai rencana atau tidak. Tujuan dari penelitian ini adalah untuk mengetahui bagaimana kinerja waktu pada proyek dan untuk mengetahui proyek mengalami kerugian atau tidak. Manfaat dari penelitian ini memberikan gambaran mengenai metode earned value.

Pengambilan data pada penelitian ini langsung kepada instansi terkait yang ada dalam rpoyek tersebut. Lokasi penelitian berada di Kota Tarakan dengan objek penelitian adalah Pembangunan Gedung Dharma Wanita Tahap II. Hasil dari penelitian ini berupa perhitungan waktu dan biaya seusai dengan menggunakan metode earned value. Dari perhitungan dengan metode earned value didapat hasil dengan waktu lebih cepat dari waktu rencana yaitu 35 hari dan baiaya yang dikeluarkan lebih kecil dari biaya rencana sehingga mengalami keuntungan sebesar Rp. 458.517.155,80.

Kata Kunci: Proyek Konstruksi; Metode Earned Value; Kinerja biaya, Kinerja Waktu.

(7)

vii

TIME AND COST PERFORMANCE ANALYSIS USING EARNED VAUE METHOD IN DHARMA WANITA BUILDING CONSTRUCTION

PROJECT PHASE II TARAKAN

Alfian Saiful Anam1, Rofikatul Karimah2, Rini Febri Utari3

123Department of Civil Engineering, Faculty of Engineering, University of Muhammadiyah Malang

Jl. Raya Tlogomas No. 246 Tel (0341)464318 Fax (0341)460782 Email : Ajipiyan1@gmail.com

ABSTRACT

Construction projects are currently experiencing fairly rapid development along with the times. Making a work plan is one of the first steps in planning. Initial plans are made to determine the level of effectiveness and efficiency during the project.

By using the earned value method, it can be easier to find out whether the project is going according to plan or not. The purpose of this study is to find out how the time performance on the project and to find out the project experienced a loss or not. The benefits of this research provide an overview of the earned value method.

Collecting data in this study directly to the relevant agencies in the project. The research location is in Tarakan City with the object of research being the Phase II Dharma Wanita Building. The results of this study are in the form of time and cost calculations after using the earned value method. From the calculation with the earned value method, the results obtained are faster than the planned time, namely 35 days and the costs incurred are smaller than the planned costs so that they experience a profit of Rp. 458,517,155.80.

Keywords: Construction Projects; Earned Value Method; Cost Performance, Time Performance.

(8)

viii

DAFTAR ISI

LEMBAR PENGESAHAN ... ii

SURAT PERNYATAAN ... iii

LEMBAR PERSEMBAHAN ... iv

KATA PENGANTAR ... v

ABSTRAK ... vi

DAFTAR ISI ... viii

BAB I ... 1

PENDAHULUAN ... 1

1.1 Latar Belakang ... 1

2.1 Rumusan masalah ... 4

3.1 Tujuan Masalah ... 4

4.1 Batasan Masalah ... 4

5.1 Manfaat Penelitian ... 5

BAB II ... 6

TINJAUAN PUSTAKA ... 6

2.1 Landasan Teori ... 6

2.2 Manajemen Proyek ... 7

2.3 Proyek ... 7

2.3.1 Perencanaan Proyek ... 9

2.3.2 Pengendalian Proyek ... 11

2.4 Pengendalian Waktu ... 12

2.5 Pengendalian Biaya ... 12

2.6 Kurva S ... 13

(9)

ix

2.7 Barchart ... 14

2.8 Nilai Hasil (Earned Valeu) ... 15

2.9 Metode Konsep Nilai Hasil ... 15

2.9.1 Varians Biaya Dan Jadwal Terpadu ... 17

2.9.2 Indeks Produktivitas Dan Kinerja ... 20

2.9.3 Proyeksi Biaya Dan Jadwal Akhir Proyek ... 20

BAB III ... 24

METODELOGI ... 24

3.1 Metode Penelitian ... 24

3.2 Pengumpulan Data ... 24

3.3 Pengolahn Data ... 24

3.4 Teknik Pegolahan Data ... 26

BAB IV ... 29

PEMBAHASAN ... 29

4.1 Kondisi Eksisting Proyek ... 29

4.2 Analisa Data ... 29

4.2.1 Anggaran Biaya Yang Dijadwalkan (BCWs) ... 29

4.2.2 Analisa Anggaran Biaya Yang Dilaksanakan (BWCP) ... 31

4.2.3 Analisa Anggaran Biaya Realisasi Pekerjaan (ACWP) ... 33

4.3 Analisa Nilai Hasil ... 39

4.3.1 Varian Jadwal (SV) ... 39

4.3.2 Indek Kinerja Jadwal (SPI) ... 41

4.3.3 Perkiraan Waktu Penyelesaian Proyek (ETC) ... 44

4.4 Parameter Biaya ... 45

4.4.1 Varian Biaya ... 45

4.4.2 Indeks Kinerja Biaya (CPI) ... 47

4.4.3 Perkiraan Biaya Menyelesaikan Pekerjaan (EAC) ... 49

BAB V ... 51

(10)

x

KESIMPULAN DAN SARAN ... 51

5.1 Kesimpulan ... 51

5.2 Saran ... 51

DAFTAR PUSTAKA ... 52

LAMPIRAN ... 53

LAMPIRAN LAPORAN BULANAN ... 54

LAMPIRAN RAB ... 65

LAMPIRAN BIAYA AKTUAL ... 72

LAMPIRAN KURVA S ... 82

(11)

xi

DAFTAR PUSTAKA

Soeharto. I, 1998. Manajemen Proyek (Dari Konseptuan Sampai Operasional).

Jakarta: Penerbit Erlangga.

Michel, D, 2015, . Pengendalian Biaya dan Waktu dengan Metode Analisis Nilai dan Hasil dengan Microsoft Project 2010. Jurnal Sipil Statik Vol 3

Ervianto, Wulfram I., 2004, Teori Aplikasi Manajemen Proyek Konstruksi, Salemba Empat, Yogyakarta

Nasir, Ahmad., 2014, Analisis Pengendalian Waktu dan Biaya Dengan Metode Earned Value ( Nilai Hasil ) pada Proyek Pembangunan Gedung Olahraga ( gor ) Tarakan, Borneo University Library

\

(12)

xii

Referensi

Dokumen terkait

Tujuan dari penelitian ini untuk mengetahui kinerja biaya dan waktu, estimasi biaya dan waktu pada akhir penyelesaian proyek serta faktor-faktor yang menyebabkan keterlambatan atau

Konsep Earned Value (nilai hasil) adalah konsep menghitung besarnya biaya yang menurut anggaran sesuai dengan pekerjaan yang telah diselesaikan / dilaksanakan.

pengamatan berdasarkan laporan kemlijuan mingguan. 2) Penerapan metode Earned Value iru dilakukan pada Proyek Pembangunan Show Room HARTONO ELEKTRONlK. 3) Metode yang

Konsep Earned Value Analysis merupakan salah satu metode pengendalian kinerja proyek dari segi biaya dan waktu yang dapat memberikan informasi mengenai posisi kemajuan proyek

o Apabila kecendrungan kinerja waktu dan biaya proyek seperti pada minggu ke – 20 ( akhir waktu rencana ), maka dapat diperkirakan waktu yang dibutuhkan untuk menyelesaikan proyek

Untuk menghindari kerugian dapat dilakukan pengendalian proyek baik dalam aspek biaya dan waktu dengan metode Earned Value.. Pengendalian dilakukan pada proyek Struktur &

Berdasarkan uraian diatas peneliti sangat tertarik untuk meneliti waktu yang diperlukan dengan jumlah biaya yang dikeluarkan selama proyek berlangsung pada pembangunan

Konsep Earned Value (nilai hasil) adalah konsep menghitung besarnya biaya yang menurut anggaran sesuai dengan pekerjaan yang telah diselesaikan / dilaksanakan. Bila