Menjamin Infrastruktur Indonesia
Guarantee
Indonesia’s Infrastructure
Penjaminan Investasi
Proyek Kerjasama Pemerintah Badan Usaha
disampaikan pada
Seminar Talk Show
“Pembiayaan Infrastruktur Berkelanjutan”
Jakarta,
28 Januari 2016
oleh:
Arianto Wibowo
Executive Vice President
2
Total investasi infrastruktur tersebut dibutuhkan untuk mencapai
target pertumbuhan ekonomi 7% per tahun
SEKTOR
APBN
APBD
BUMN
Swasta/KP
S
Total
Jalan
268
200
65
200
733
Perkeretaapian
93
-
11
122
226
Transportasi Laut
260
-
238
93
591
Transportasi Udara
64
5
50
25
144
Angkutan Sungai dan
Penyeberangan
37
-
10
-
47
Transportasi Perkotaan
61
15
5
5
86
Ketenegalistrikan
120
-
445
435
1000
Minyak & Gas
4.3
-
152
352
507
Teknologi Informasi dan
Komunikasi (ICT)
15
15
27
223
280
Sumber Daya Air
196
68
7
180
451
Persediaan Air dan Sanitasi
131
198
44
30
403
Perumahan Rakyat
184
44
13
87
328
Total kebutuhan dana
1.433,3
545,3
1.066
1.751
4.796
Persentase berdasarkan alokasi
29,88%
11,37%
22,23% 36,52%
100%
Dalam Rp triliun
Kebutuhan Investasi Proyek-Proyek Infrastruktur Masing-Masing Sektor (2015-2019)
Sumber: BAPPENAS
Indonesia membutuhkan Rp 4.796 triliun untuk investasi proyek-proyek
infrastruktur di berbagai sektor pada Tahun 2015-2019
K
ON
TEKS
KPS
DI
IND
O
NE
SIA
Berbagai Fasilitas Fiskal Pemerintah untuk mendukung pembangunan
infrastruktur
Pemerintah Indonesia
Tantangan KPS yang juga umum di negara lain
Nilai tambah PT PII mengatasi tantangan KPS
LandFund
Guarantee Fund (IIGF)
Infrastructure Fund
(PT SMI, IIF, PIP) Capital market and regulatory reform Private Investors / Lenders Land Acquisition & Clearance Political Risks Project Financing
Preparation Bidding Construction Operation Cost of financing Refinancing
Viability Gap Fund (VGF)
KPS
Regulasi Koordinasi• Meningkatkan kepastian transaksi KPS Dukungan Pemerintah Kapasitas sektor publik
• Mendukung PJPK dan mendorong
persiapan proyek KPS yang berkualitas dan
bankable
• Mendorong proses yang transparan, kompetitif dan akuntabel
• Mengindikasikan penyempurnaan peraturan terkait (sektor, dll.)
Beragam
fasilitas fiskal
telah
dibentuk
sejak 2009
Project ViabilitySupport Letter Confirmation Note Letter of Guarantee Guarantee Agreement 1 Periode / Proyek Awal 1990 / 27 IPP (1st Gen) Pertengahan 2000 / Cirebon (2nd Gen) 2009 / 10,000 MW Fast Track I – EPC (PLN)
2011 / PLTU Jawa Tengah (signed); 2015/ Minemouth; Tol Soroja (IPA)
2 Sektor yg bisa
didukung Listrik Listrik Listrik
Utilitas (Listrik, SPAM); Transportasi (Jalan, Bandara, ); Sosial
3 Penerima
Jaminan Project Company
• Lender (JBIC)*
• Insurer (NEXI)* Chinese Lenders Project Company
4 Issuer Menteri Keuangan Menteri Keuangan Menteri Keuangan PT PII
5 Lingkup
Penjaminan Blanket Blanket
Cicilan
(Principal + Interest)
Kewajiban Finansial PJPK tertentu sebagaimana dalam PPP Agreement
6
Ketentuan Pembayaran Klaim
Tidak disebutkan Tidak disebutkan 45 hari
• Kejelasan jumlah hari pada setiap pembayaran, baik pembayaran bulanan maupun terminasi • Dirinci mekanisme klaim dan
pembayarannya
*) Mengacu padaUmbrella Note of Mutual Understanding antara Kementerian Keuangan Republik Indonesia dan Japan Bank for International Cooperation (JBIC), dan dengan Nippon Export and Investment Insurance (NEXI);
“Regulasi Penjaminan Infrastruktur” adalah:
1.
Perpres No 78/2010
tentang Penjaminan Infrastruktur Dalam Proyek Kerja Sama Pemerintah Dengan Badan Usaha Yang
Dilakukan Melalui Badan Usaha Penjaminan Infrastruktur
2.
Peraturan Menteri Keuangan No 260/2010
tentang Petunjuk Pelaksanaan Penjaminan Infrastruktur Dalam Proyek Kerja Sama Pemerintah Dengan
Badan Usaha
Dasar Hukum untuk Penjaminan Infrastruktur
Keduanya mengacu pada konteks Pengelolaan Risiko dan Prinsip Alokasi
Risiko KPS
6
Model Bisnis PT PII Dirancang Agar Proses Penjaminan
Pemerintah Menjadi Konsisten, Transparan, Dan Efisien
PJPK
(Kementerian, Pemda,
BUMN)
Investor
Perjanjian KPS 2 Proposal Penjaminan Perjanjian Regres 1 3a 3b A Kementerian KeuanganMOF
Multilateral Development Agency / LainnyaKebijakan Penjaminan & Penyertaan Modal Co unt er Gu ara nt ee unt uk F asilit as Penj am inan MDA Fasilitas Kredit/Penjaminan B Note:
ada hanya jika ada, yaitu jika merupakan bagian dari struktur penjaminan yang diberikan kepada investor
B A A
4. Structuring
2. Screening 3.Appraisal
1. Consultation
CA
Role
Seek info on IIGF guarantees & process Submit “Screening Form” Submit “Guarantee Application Package” (GAP) Finalize T&C of Guarantee & Recourse Agreement
IIGF
Role
Provide info on guarantee product & process Issue “Confirmation to Proceed” for eligible project Issue “Letter of Intent” for guarantee provision Issue “In-Principle Approval” to be used for biddingScreening Form: 1. Cover Letter 2. Project brief description 3. Outline Business Case
Guarantee Application Package:
1. Request Letter 2. Pre-feasibility study 3. PPP structure
4. Risk Matrix & Risk Mitigation Plan 5. Draft PPP Agreement
6. Description of Govt support 7. Scope of guarantee required 8. Financial model
9. Env. & social assessment report 10. Project Management Plan 11. CA related information
Risk Monitoring of Guaranteed
Projects
Overall Process Objective is to ensure the Guaranteed Projects are:
•
Feasible
• Fair in Risk Allocation
• Well Structured
• Robust in Risk Mitigation Plan
Kategori Risiko Investasi/Proyek Infrastruktur
Kategori Risiko Proyek Infrastruktur Risiko Lokasi Risiko design, konstruksi & uji operasiRisiko
Sponsor
Risiko Financial Risiko Operasional Risiko Pendapatan Risiko Konektivitas Jaringan Risiko Interface Risiko Politik Risiko Kahar Risiko Kepemilikan AsetNote : Kategori risiko ini bisa sebagai checklist dan tidak bermaksud untuk menjadi
suatu daftar risiko yang kaku untuk setiap proyek.
Situasi dan kondisi spesifik dalam suatu proyek perlu juga dipertimbangkan
Jenis Risiko Pra
Konstruksi Konstruksi Operasi
Lokasi √ √ √
Desain,
Konstruksi dan uji operasi √ √ √ Sponsor √ √ √ Financial √ √ √ Operasi √ Pendapatan √ Konektifitas Jaringan √ √ Interface √ √ Politik √ √ √ Force Majeure √ √ √ Kepemilikan aset √
Alokasi Risiko yang Optimal
Sesuai dengan Prinsip Alokasi Risiko? Risiko Sesuai Definisi Regulasi?Kategori
Risiko
Risiko
Infrastruktur
Ya
Ya
Tidak
Tidak
Referensi:
Acuan Alokasi
Risiko KPBU
Dapat dipertimbangkan untuk DijaminRegulasi Penjaminan:
Risiko Infrastruktur
adalah peristiwa-peristiwa yang mungkin terjadi pada Proyek Kerja
Sama selama berlakunya Perjanjian Kerja Sama yang dapat mempengaruhi secara
negatif investasi Badan Usaha, yang meliputi ekuitas dan pinjaman dari pihak ketiga
Risiko Infrastruktur
yang dapat diberikan Penjaminan Infrastruktur adalah yang:
1.
terjadinya diakibatkan oleh tindakan atau tiadanya tindakan PJPK atau Pemerintah selain PJPK
2.
diakibatkan oleh kebijakan PJPK atau Pemerintah selain PJPK
3.
diakibatkan oleh keputusan sepihak dari PJPK atau Pemerintah selain PJPK
10
IIGF Guarantee Provision Framework
Viability Evaluation & Risk Assessment Approac
h
Viability Evaluation approach
Aspects:• Economic: Development impact, fiscal benefit, etc; • Legal & Regulatory: Compliance
• Technical: Constructability; Operating performance • Financial: Costing, cost of capital, gearing ratio • Social & Environmental: Safeguard implementation Inputs (key components of GAP):
• Project Structure: Revenue/payment model • Pre FS: Evaluation of above viability aspects • Draft PPP Agreement: Rights & obligations • Fiscal Support Evaluation: Extent of cover • CA Information: fiscal & technical capacity Process/Methods: Field survey/data collection, Quantitative/qualitative analysis & modeling Output: Confirmation on the Project & CA Viability
Risk Identification
Risk Evaluation
Risk Mitigation
Risk Monitoring
Risk Assessment approach
Aspects: • Risk exposure • Guarantee capacity • Guarantee pricing • Risk retention • Provisioning Input: • Project Structure • Risk Event Definition • Risk Allocation on
Financial Obligation • Base Financial Model Process/Methods: • Guarantee modeling &
CL Analysis Output:
• Guarantee structure • Risk Mitigation Plan
Aspects: • Risk Monitoring • Claim management • Recourse mechanism • Fee collection Input: • Joint Monitoring Committee (JMC) SOP & Charter • Key Risk Indicators Process/Methods: • JMC meetings & site
visits
• IT-based system Output:
• Early warning of risk • Claim prevention
• Key Project risks • CA-related risks
• Government related risks
• Risk Allocation • Risk Quantification
(impact & likelihood)
• Risk transfer (insurance, etc)
• Residual risk retention
• Risk profile updating • Residual risk retention