1. Diketahui : = 5% = 5% = 26 ton = 16 ton = 4 ton Ditanyakan : K = 5% Jawab : = 1. TR = = W x % K = 1.3 ton 2.
TR = Tahanan Kelandaian (GR) + Tahanan Gelinding (RR) = = 2 ton = 3.3 ton 2. Diketahui : = 8% = 4500 kg = 18 ton = 4 ton = 0.65 K = 8% Ditanyakan : Jawab : 1. TR = = W x % K = 1.44 ton 2. TR = 4500 kg + Tahanan Kelandaian (GR) = = 4.82 ton = 6.26 ton = W x ct = 11.7 ton TK > TR = Mampu Traksi Kritis Bulldozer (TK)
Mampukah Bulldozer menarik harraw ?
Tenaga yang dibutuhkan Bulldozer (TR) Bulldozer ( Roda Rantai )
Tahanan Kelandaian (GR)
Scraper ( Roda Rantai )
4500 kg + ( W x % K ) 1.Kelandaian ( K ) 2.Harraw ditarik pada datar 3.Berat Bulldozer ( W ) 4.Berat Harraw ( W ) 5.Koef. Traksi Kritis ( ct ) ANALISA BEBAN DAN TENAGA
TUGAS
Tenaga yang dibutuhkan Beban Total ( TR )
Jadi tenaga yang dibutuhkan traktor adalah 1.Kelandaian ( K )
2.Koef. Tahanan Gelinding ( r ) 3.Berat Traktor ( W ) 4.Berat Scraper ( W ) 5.Muatan Scraper
Berapa besar tenaga yang dibutuhkan untuk menarik scraper ?
Tahanan Kelandaian (GR)
Scraper ( Roda Karet )
( W x % K ) + ( W x % r ) Traktor ( Roda Rantai )
: 1. 0.83 p = 4000 m 2. Sweel = 20% t = 1.8 m p = 2000 m t = 1.2 m 1. = 2. = 3.2 m 3. = 1.1 m 4. = 5. = 6. = 8 thn 7. = jam 8. = 9. = = 1 = 2 = 3 = 0.83 4 = 4.5 km/jam = 5 = 6 km/jam = 6 = 7 = 140 jam 8 = 0.3 m : 1 2 3 4 5 6 : Diketahui Tanah Biasa =
Durasi 20 hari @ 7 jam a. Data Pekerjaan & alat
dari harga pembelian Galian
Timbunan
Proyek jalan raya Latihan 1
STA 00 STA 6000
= 24
galian timbunan galian timbunan galian
b. Kondisi Tanah
Alat Bulldozer type s Lebar blade
Tinggi blade
Biaya Pemblian Rp19,000,000,000
Nilai Sisa Waktu Investasi Masa guna alat Biaya Operasional Biaya Investasi 10% 10000 Rp900,000 18% Rp3,420,000,000 c. Metode kerja Metode kerja
Waktu kerja 50 menit/jam Operator Pandai
V mendorong
Slot and Dozing
V mundur
Bekerja waktu kemarau
75 100
Jawab
m/menit m/menit
Ditanyakan Produksi alat dalam 1 jam ( Q ) Hitung jumlah alat
Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15% Jadwal
GALIAN Perataan timbinan perlapis
● = m³ ● = ● = Lm³ ● = Lm³ ● = m 0.02 m ( J ) ● = menit ● = 1 Q = Q' x E Q' = 60 x B CT = 232.32 = 164.571 Lm³/jam 1.412 Q = 134.949 2 = Lm³ = Jam = Jam Jam
Jumlah Alat = 10.9756
~
11 UNIT3 BP ● = ● = + BP = /jam O = /jam + BP & O = /jam = = = = + = 4 = Rp m³ = Rp m³ HSP Pekerjaan = Rp/m³ 5 = + + Pajak 15% Biaya Aktual Rp4,989,600,000 Rp28,875
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit vol . Bank Rp4,989,600,000 172800 Rp453,600,000 Profit 10 % Rp4,536,000,000 Q x 207360 134.949 x Rp2,952,000 BP & O Jumlah Alat 1537 140
Biaya Aktual Vol. Loose
Jarak Operasi Blade , dengan kedalaman 60.5
Kapasitas Blade ( B ) 3.872 Rp900,000 Rp2,952,000 CT 1.412 E 0.82 Lm³/jam Durasi Alat 207360 134.9485714 Lm³/jam 1537 Depresiasi / jam Investasi / jam Rp1,710,000 Rp342,000 Rp2,052,000 Volume Pekerjaan Galian ( bank )
Volume Pekerjaan Galian ( loose )
172800 20% sweel
= + =
Rp4,989,600,000 Rp748,440,000
Rp5,738,040,000 Harga Penawaran
m
● = m³ ● = ● = Lm³ ● = Lm³ ● = m 0.3 m ( J ) ● = menit ● = 1 Q = Q' x E Q' = 60 x B CT = 232.32 = 2468.571 Lm³/jam 0.094 Q = 2024.229 2 = Lm³ = Jam
Jumlah Alat = Jam
Jam
Jumlah Alat = 0.243902
~
1 UNIT3 BP ● = ● = BP = O = BP & O = = = = = + = 4 HSP Pekerjaan = Rp m³ = Rp m³ HSP Pekerjaan = Rp/m³ 5 = + + Pajak 15%
Volume Pekerjaan Galian ( bank ) 57600
sweel 20%
Volume Pekerjaan Galian ( loose ) 69120
Kapasitas Blade ( B ) 3.872
Jarak Operasi Blade , dengan kedalaman 4.033
Rp1,710,000 Investasi / jam Rp342,000 Rp2,052,000 CT 0.094 E 0.82 Lm³/jam Durasi Alat 69120 2024.228571 Lm³/jam Rp100,800,000 Profit 10 % Rp10,080,000 Biaya Aktual Rp110,880,000
Biaya act + profit vol . Bank Rp110,880,000
57600 Rp1,925
Harga Penawaran Biaya Actual Profit
Rp900,000 Rp2,952,000
Biaya Aktual Vol. Loose
x BP & O Q 69120 x Rp2,952,000 2024.229 34 34 140 Depresiasi / jam
= + =
Rp748,440,000 Rp110,880,000
Rp127,512,000 Harga Penawaran
+ /jam /jam + /jam Pajak 15%
4.47 CL 4 m 2 : 1 2.5 m Diketahui : 1. ● = ● = 0.85 m³ 2. ● = 2000 m ● = 1.1 ● = 20% ● = 1 ● = 15 detik ● = 0.83 ● = 210 jam ● BP & O = Ditanyakan : 1. 2. 3. 4. 5. 6. Jawab : 1. = 22350 m³ = 26820 Lm³ Q = Q ' x E Q' = 60 x q CT (menit ) q = q ' x K Q = 46.563 0.25 Q = 186.252 Lm³/jam
Volume pekerjaan galian ( loose )
Rp1,200,000 tanah biasa ( K )
sweel
digging condition 60 % swing angle 70°
Koefisien efesiensi ( E ) "good" panjang galian Data alat Excavator PC 180 Latihan 2 Data pekerjaan Kapasitas ( q ' ) Jadwal
Durasi 30 hari @ 7 jam kerja
Produksi alat dalam 1 jam ( Q ) Hitung jumlah alat
Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15%
2. 26820 Lm³ 186.252
= 143.998 Jam
Jumlah Alat = 143.998 Jam
210 Jam
Jumlah Alat = 0.685706922
~
1 UNIT3. Biaya Aktual = Vol. Loose Q = 26820 186.252 = Rp172,798,144 Rp17,279,814 + Biaya Aktual = Rp190,077,959
4. HSP pekerjaan = Biaya act + profit Rp vol . Bank m³ = Rp190,077,959 Rp
22350 m³
HSP pekerjaan = Rp8,505 Rp/m³
5. Biaya actual + Profit +
= + Rp218,589,653 X Rp1,200,000 Harga Penawaran = Rp190,077,959 Durasi alat = Lm³/jam BP & O X Harga Penawaran = Profit 10% =
Pajak 15 % Rp28,511,694
Tanah 12 m 12 m : 1 = 138240 Lm³ 2 = 3.4 m³ 3 = 0.95 4 = /Jam 5 = 0.2 menit 6 = 0.83 1 = 12 m 2 = 2.5 km/jam = 41.67 3 = 4 km/jam = 66.67 4 = 210 jam : 1. 2. 3. 4. 5. 6. : 1. CT = J1 = J2 = 2J kecp. Isi = 0.576 + + 0.2 = 1.136 Latuhan 3 Diketahui
Pengangkutan tanah dengan Vol. Pekerjaan 2/3 dari hasil galian bulldozer
b. Metode kerja
V shape ,dengan jarak
Koefisien efesiensi ( E ) "good" Bucket Kapasitas ( q ' ) Faktor Bucket ( K ) a. Data pekerjaan & alat
BP & O FT
kecepatan isi kecepatan kosong waktu 30 hari @ 7 jam
Rp1,250,000
Produksi alat dalam 1 jam ( Q ) Ditanyakan
Jawab
Hitung jumlah alat
Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15% Jadwal 2J + FT 0.36 + menit kecp. Kosong DT
= 115200 m³ = 20% = 138240 Lm³ Q = Q ' x E Q' = 60 x q CT (menit ) q = q ' x K Q = 160.854 1.136 Q = 141.597 2. = Lm³ = jam = jam jam =
~
5 3. = = = = + = 4. = Rp m³ = Rp m³ = Rp/jam 5. = + = = volume pekerjaan ( loose )sweel
volume pekerjaan ( bank )
Lm³/jam Durasi alat 138240 141.597 976.293 Lm³/jam Jumlah alat 976.293 210 4.649014457
Biaya Aktual Vol. Loose
Q X Jumlah alat 141.597 X Rp1,250,000 Rp1,220,366,295 BP&O 138240 Vol. Bank Rp1,342,402,924 115200 Rp11,653 Profit 10% Rp122,036,629 Rp1,342,402,924
HSP Pekerjaan Biaya Act. + profit
Biaya Aktual
HSP Pekerjaan
Rp1,342,402,924 1,543,763,363 Rp
Harga Penawaran Biaya Act. Profit
m/menit m/menit
UNIT + + Rp1,250,000 Pajak 15% 201,360,439 Rp Rp1,342,402,924 Profit
Latihan 4 10% 750 m 600 m Diketahui : 1. ● ● = 27.2 ton ● = 52.3 ton
● = V max Flat = Isi = 40
Kosong = 60 = = Isi = 20 Kosong = 40 ● = Rp2,100,000 /hari = 2. ● = 115200 m³ = 138240 lm³
● = Membawa sama dengan kembali
● = Kering dan kurang terpelihara =
● = 1.6 ton/m³
● =
● = Lancar Tanpa Ada Hambatan
● = Lancar Tanpa Ada Hambatan
Ditanyakan : 1 2 3 4 5 6 Jawab : 1 CT = T1 + T2 + T3 + T4 + T5 T1 = n X CT wheel loader n = Datar Tabel T2 dan T4
tipe angkut Segmen kondisi Membawa (isi)
q WL x K x γt Managemen Baik
Dumping Spot & Delay Kondisi Jalan
γ Tanah Volume Pekerjaan
q DT ( kg ) Sewa Dump Truck
Route Pengangkutan Data Alat
Dump Truck HD 325 Berat Kosong
Jadwal
Produksi alat dalam 1 jam ( Q ) Hitung Durasi
Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15%
Rp262,500 Data Pekerjaan
Berat Bermuatan Max Batasan Kacapatan V max Turunan/ tanjakan DUMP TRUCK
n = n = 25100 5168 n = 4.8568111
~
5 T1 = 5 x 1,136 menit T3 = 0.6 T1 = 5.68 T5 = 0.15 CT = T1 + T2 + T3 + T4 + T5 CT = 8.69 menit M = CT dt n X CT wl M = 8.69 5.68 M = 1.53~
2 unit Q = Q' x E x M E ( GOOD ) = 0.83 Q' = 60 x q DT CT q DT = n x q L Q' = 60 x 9 x 3,4 8.69 Q' = 46.95 Q = 194,48 x 0,83 x 9 Q = 77.93 2 Volume ( Bank ) = 115200 m² Sweel = 20% Volume ( Loose ) = 138240 Lm³ Waktu Pelaksanaan = Vol. looseQ = 138240
77.93
= 1773.88 jam
Waktu Pelaksanaan = 253.41 Hari
~
254 Hari3. = = = 138240 x Rp262,500 77.931 Rp465,644,005 Lm³/jam Lm³/jam Hitung Durasi
Biaya Aktual Vol. Loose
x BP & O Q Tanjakan menit Datar Datar Turunan Datar Membawa (isi) Kembali ( kosong ) (52,3 t - 27,2 t )x 1000 3,4 x 0,95 x 1600
= + = 4. = Rp m³ = Rp m³ HSP Pekerjaan = Rp/m³ 5. = + = = Profit Rp512,208,405 Harga Penawaran Rp589,039,666 vol . Bank Rp512,208,405 115200 Rp4,446
Harga Penawaran Biaya Actual
Profit 10 % Rp46,564,400
Biaya Aktual Rp512,208,405
350 m = m/menit = m/menit = m/menit = m/menit /jam 8%
jarak RR GR TR F Vmax SF V rata2
600 8% 0% 8% 667 0.72 480 667 1000 333 667 T2 tahanan kecepatan Time Datar 1.393443 Segmen kondisi Km/jam Km/jam Km/jam Jadwal
Produksi alat dalam 1 jam ( Q ) Hitung Durasi
Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15%
750 8% 10% 18% 333 0.78 260 350 8% 0% 8% 667 0.72 480 600 8% 0% 8% 1000 0.72 720 750 8% -10% -2% 667 0.78 520 350 8% 0% 8% 1000 0.72 720 menit menit Rp262,500 Hitung Durasi BP & O 0.867347 T2 T4 Tanjakan 1.393443 Datar Datar Turunan Datar
+ +
Profit Pajak 15%
Return
Houling
Diketahui : 1.
● Kapasitas bowel (q ) = 10 m³
● Kecp. Digging (VD) = 1.5 km/jam = 25
● Kecp. Houling (VH) = 10 km/jam = 166.6667 ● Kecp. Spreading (VS) = 3 km/jam = 50.00
● Kecp. Returning (VR) = 12 km/jam = 200
2. ● Jarak Digging (D) = 35 m ● Jarak Houling (H) = 175 m ● Jarak Spreading (S) = 25 m ● Jarak Returning (R) = 200 m ● Vulome Galian = 500000 m³ ● Volume Urugan = 500000 m³
● Banyak Alat = 5 Unit
● BP & O = Rp1,500,000 per jam
● FT = 1 Ditanyakan : 1. 2. 3. 4. 5. 6. Dijawab : 1. CT = CT = 35 175 25 + HSP pekerjaan
Biaya penawaran dengan pajak 15% Jadwal
+ +
Biaya aktual apabila profit 10% Latihan 5
Data Alat
Data Pekerjaan
Produksi alat dalam 1 jam ( Q ) Hitung waktu pelaksanaa
175 m 200 m 𝐷 𝑉𝐷
+
𝐻 𝑉𝐻+
𝑆 𝑉𝑆+
𝑅 𝑉𝑅+ FT
25 166.67 50.00 CT = 4.95 menit
E = E1 X E2 X E3 Dimana : E1 = Waktu Kerja 50m/j
E = 1.008 E2 = Operator Baik E3 = Tanah Biasa Q' = 60 X q CT Q' = 600 4.95 Q' = 121.212121 Q' = Q' X E Q = 122.181818 2. Volume ( Bank ) = 500000 m³ Sweel = 20% Volume ( Loose ) = 600000 Lm³ Waktu Pelaksanaan = Vol. loose
Q = 600000
122.18
= 4910.71 jam / 5 unit = 982.14 per unit
Waktu Pelaksanaan = 140.31 Hari
~
1413. = = = = + = 4. = Rp m³ = Rp m³ HSP Pekerjaan = Rp/m³ 500000 Rp16,205 Biaya Aktual Rp8,102,678,571
HSP Pekerjaan Biaya act + profit vol . Bank Rp8,102,678,571 600000 x Rp1,500,000 122.182 Rp7,366,071,429 Profit 10 % Rp736,607,143 Lm³/jam Lm³/jam
Biaya Aktual Vol. Loose
x BP & O
Q
+
5. = + =
=
Rp8,102,678,571
Harga Penawaran Rp9,318,080,357
m/menit m/menit m/menit m/menit 200 + 1 𝐷 𝑉𝐷
+
𝐻 𝑉𝐻+
𝑆 𝑉𝑆+
𝑅 𝑉𝑅+ FT
200 = 0.84 = 1 = 1.2 Hari Rp1,500,000 + 1 BP & O
+ +
Rp8,102,678,571 Rp1,215,401,786
lo L α Diketahui : 1. ● Lebar Blade ( L ) = 3.1 m ● Sudut Kerja ( α ) = 60 °
● Kecepatan rata2 = 4 km/jam =
● BP & O / jam =
● Jumlah alat = 1 unit
2.
● Lebar lapisan = 12 m
● Laluan Subgrade (n) = 6 kali
● Laluan sub base (n) = 4 kali
● Laluan base course (n) = 3 kali
● Lebar overlap (lo) = 0.25 m
● E faktor ( good ) = 0.83 Ditanyakan : 1. 2. 3. 4. 5. 6. Dijawab : 1. Q = Q' X E Q' = le = sin α x L le = sin 60 x 3,1 Q' = le = 2.68 Q' = 9720 6 Q' = 1620.00 Q = 1620 x 0,83 Q = 1344.60 m²/jam 2. Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q SUBGRADE le 6 6000 Data Alat Rp2,200,000 Data Pekerjaan 6
Produksi alat dalam 1 jam ( Q ) Hitung waktu pelaksanaa Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15% Jadwal
60 X V .( le - lo ) n
60 x 66,67 . ( 2,68 - 0,25 ) 6
= 72000 1344.60
= 53.55 jam
= 53.55 per unit
Waktu Pelaksanaan = 7.65 Hari
~
3. = = = = + = 4. = Rp m² = Rp m² HSP Pekerjaan = Rp/m² 5. = + = =
Biaya Aktual Luas
x Q 72000 x 1344.600 Rp117,804,552 Profit 10 % Rp11,780,455 Harga Penawaran Rp149,022,758 Rp1,800
Harga Penawaran Biaya Actual
Biaya Aktual Rp129,585,007
HSP Pekerjaan Biaya act + profit
Luas Rp129,585,007
72000
66.67 m/menit 1. sin 60 x 3,1 m 2. SUB BASE
8 Hari 3. 4. + 5. + BP & O Rp2,200,000 Profit Pajak 15% Rp129,585,007 Rp19,437,751
Q = Q' X E Q' = le = sin α x L le = sin 60 x 3,1 Q' = le = 2.68 m Q' = 9720 4 Q' = 2430.00 Q = 2430 x 0,83 Q = 2016.90 m²/jam Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q SUB BASE 60 X V .( le - lo ) n 60 x 66,67 . ( 2,68 - 0,25 ) 4
= 72000 2016.90
= 35.70 jam
= 35.70 per unit
Waktu Pelaksanaan = 5.10 Hari
~
6 Hari= = = = + = = Rp m² = Rp m² HSP Pekerjaan = Rp/m² = + = = Rp86,390,004 Harga Penawaran Rp99,348,505 Rp1,200
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit
Luas Rp86,390,004 72000 Rp78,536,368 Profit 10 % Rp7,853,637 Biaya Aktual Rp86,390,004 Luas x BP & O Q 72000 x Rp2,200,000 2016.900 Biaya Aktual
1. Q = Q' X E Q' = Q' = Q' = 9720 3 Q' = 3240.00 Q = 3240 x 0,83 Q = 2689.20 m²/jam 2. Luas Perataan = Waktu Pelaksanaan = BASE COURSE 60 X V .( le - lo ) n 60 x 66,67 . ( 2,68 - 0,25 ) 3
= = = Waktu Pelaksanaan = 3. = = = = = 4. = = HSP Pekerjaan = + 5. = + = = Profit 10 % Biaya Aktual Rp12,958,501 Biaya Aktual HSP Pekerjaan Harga Penawaran Harga Penawaran Pajak 15% BP & O Rp2,200,000
le = sin α x L le = sin 60 x 3,1 le = 2.68 m 72000 m² Luas Q
72000 2689.20 26.77 jam 26.77 per unit 3.82 Hari
~
4 Hari + Rp m² Rp m² Rp/m² + + + Rp74,511,379Biaya Actual Profit Pajak 15%
Rp64,792,503 Rp9,718,876
Biaya act + profit Luas Rp64,792,503 72000 Rp900 Rp58,902,276 Rp5,890,228 Rp64,792,503 Luas x BP & O Q 72000 x Rp2,200,000 2689.200
Pajak 15% Rp9,718,876
Diketahui : 1.
● Lebar roda (w) = 2 m
● Kecp. Rata2 = 3 km/jam =
● Overlap (wo) = 0.3 m
● BP & O = Rp2,000,000 /jam
2.
● Laluan Subgrade = 4 kali
● Laluan Subbase = 3 kali
● Laluan Base course = 3 kali
Ditanyakan : 1. 2. 3. 4. 5. 6. Dijawab : 1. Q= Q' X E Q'= Q'= Q'= 21250 m²/jam Q= Q' X E E faktor ( good ) = Q= 21250 x 0,83 Q= 17637.5 m²/jam 2. Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q
= 72000
17637.50
= 4.08 jam
= 4.08 per unit
Waktu Pelaksanaan = 0.58 Hari
~
3. = = = = + = SUBGRADE
Biaya Aktual Luas
x Rp8,164,422 Profit 10 % Rp816,442 Biaya Aktual Rp8,980,865 Q 72000 x 17637.500 4 Data Alat Data Pekerjaan
Produksi alat dalam 1 jam ( Q ) Hitung waktu pelaksanaa Biaya aktual apabila profit 10% HSP pekerjaan
Biaya penawaran dengan pajak 15% Jadwal
1000 . V . ( w - Wo ) n
4. = Rp m² = Rp m² HSP Pekerjaan = /m² 5. = + = = Rp8,980,865 Harga Penawaran Rp10,327,994 Luas Rp8,980,865 72000 Rp125
Harga Penawaran Biaya Actual
50 m/menit 1. 0.83 2. 1 Hari 3. SUB BASE BP & O Rp2,000,000
4.
+ 5.
+
Profit Pajak 15%
Q= Q' X E Q'= Q'= Q'= 28333.33 m²/jam Q= Q' X E E faktor ( good ) = 0.83 Q= 28333,3 x 0,83 Q= 23516.67 m²/jam Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas Q
= 72000
23516.67
= 3.06 jam
= 3.06 per unit
Waktu Pelaksanaan = 0.44 Hari
~
1 Hari= = = = + = SUB BASE Rp6,123,317 Profit 10 % Rp612,332 Biaya Aktual Rp6,735,648 Luas x BP & O Q 72000 x Rp2,000,000 23516.667 1000 . V . ( w - Wo ) n 85000 3 Biaya Aktual
= Rp m² = Rp m² HSP Pekerjaan = Rp/m² = + = = Rp6,735,648 Harga Penawaran Rp7,745,996 Rp94
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit Luas Rp6,735,648
1. Q= Q' X E Q'= Q'= Q'= 28333.33 m²/jam Q= Q' X E Q= 28333,3 x 0,83 Q= 23516.67 m²/jam 2. Luas Perataan = Waktu Pelaksanaan = = = = Waktu Pelaksanaan = 3. = = = = = BASE COURSE Profit 10 % Biaya Aktual 1000 . V . ( w - Wo ) n 85000 3 Biaya Aktual BP & O Rp2,000,000
4. = = HSP Pekerjaan = + 5. = + = = Rp1,010,347 HSP Pekerjaan Harga Penawaran Harga Penawaran Pajak 15%
E faktor ( good ) = 0.83 72000 m² Luas Q 72000 23516.67 3.06 jam 3.06 per unit 0.44 Hari
~
1 Hari + Rp6,123,317 Rp612,332 Rp6,735,648 Luas x BP & O Q 72000 x Rp2,000,000 23516.667Rp m² Rp m² Rp/m² + + + Rp7,745,996
Biaya Actual Profit Pajak 15%
Rp6,735,648 Rp1,010,347
Biaya act + profit Luas Rp6,735,648
72000 Rp94
Pajak 15% Rp1,010,347
Diketahui : 1.
● Lebar roda (w) = 3 m
● Kecp. Rata2 = 2.5 km/jam =
● BP & O = Rp2,500,000 /jam 2. ● Tebal = 5 cm Ditanyakan : 1. 2. 3. 4. 5. 6. Dijawab : 1. Q = Q' X E Q' = 60 X V X W Q' = 60 X 41,67 X 3 Q' = 7500 m²/jam Q = Q' X E E faktor ( good ) = Q = 7500 X 0,83 Q = 6225 m²/jam 2. Luas Permukaan = 72000 m²
Waktu Pelaksanaan = Luas Q
= 72000
6225.00
= 11.57 jam
= 11.57 per unit
Waktu Pelaksanaan = 1.65 Hari
~
3. = = = = + = 4. = Rp m² Biaya Aktual Rp31,807,229
HSP Pekerjaan Biaya act + profit vol . Bank 72000 x 6225.000 Rp28,915,663 Profit 10 % Rp2,891,566
Biaya penawaran dengan pajak 15% Jadwal
Biaya Aktual Luas
x Q
Data Alat
Data Pekerjaan
Produksi alat dalam 1 jam ( Q ) Hitung waktu pelaksanaa Biaya aktual apabila profit 10% HSP pekerjaan
= Rp m² HSP Pekerjaan = m² 5. = + = = Rp31,807,229 Harga Penawaran Rp36,578,313 72000 Rp442
Harga Penawaran Biaya Actual Rp31,807,229
41.66667 m/menit
0.83
2 Hari
Rp2,500,000 BP & O
+ +
Rp31,807,229 Rp4,771,084
Pemancangan pada abutmen jembatan dengan data sebagai berikut
Diketahui : 1.
● Ukuran = 14 inchi x 14 inchi
● Panjang = 50 Ft
● Bj Beton = 150 Cuft/ton
● Jumlah 1 abutmen = 36 batang
● Berat Pondasi ( P ) = ton
● BP & O = Rp 5,000,000 /jam
● Daya dukung pondasi = 40 ton
● Faktor keamanan = 1.2
2.
● Type Vulcan size 1 (SAS)
● Waktu setting = 10 menit
● BP & O = Rp 5,000,000 /jam
● Berat Hammer (w) = 9700 lbs
● Tinggi Jatuh Hammer ( h ) = 36 inches
● Faktor Hammer (e) = 0.8
● Nilai Restritusi (k) = 0.25
Ditanyakan : 1. Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai . 2. Hitung waktu untuk memancang tiap batang !
3. Hitung untuk semua pek. Pemancangan . 4. Hitung biaya pek. Pemancangan . 5. Hitung HSP
6. Hitung biaya penawaran. Ditanyakan :
→Energi yang dihasilkan hammer E= e x w x h
E= 0,8 x 9700 x 36
E= 279360 inch-lb →Energi yang hilang
● akibat pukulan (I)
I = e x w x h x p x 1 - k² w + p
I = 0,8 x 9700 x 36 x 8166,67 x 1 - 0,25² 9700 + 8166,67 I = 119711.78 inch-lb
● akibat head tiang pancang (CL)
U = daya dukung pondasi x faktor keamanan U = 240000 x 1,2
U = 288000
CL = U x C 1 C1 = tekanan izin sementara kepada kepala tiang dan cap
Data Tiang Pancang
2 C1 = 0.01 CL = 288000 x 0,394 2 CL = 113385.83 2 CL = 56692.91 ● akibat tiang pancang (PL)
PL = U x C 2 C2 = simpanan tiang akibat tekana izin sementara
2 C2 = 0.005 PL = 288000 x 0,197 2 PL = 56692.91 2.00 PL = 28346.46
● akibat ujung tiang pancang (SL)
SL = U x C 3 C3 = tekanan izin sementara
2 C3 = 0.003 SL = 288000 x 0,118 2 SL = 34015.75 2 SL = 17007.87
→Energi bersih yang dapat digunakan US = e x w x h - I - CL - PL - SL US = 279360 - 119711,78 -56692,91 - 28346,46 - 17007,87 1. US = 57600.98 hammer memadai S = US / U S = 57600,98 / 288000 S = 0.200 inchi S = 0.0051 meter T = Le Le = 2/3 dari L S x V xFo Le = 33.33 T = 10.16 Le = 10.16 0,0051 x 60 x 0,83 V = 60 T = 40.16 Menit Fo = 0.83
2. →Waktu yang dibutuhkan untuk memancang 1 tiang pancang adalah = 3. →Waktu yang dibutuhkan untuk memancang semua tiang pancang adalah =
4. waktu pek. Pemancangan X BP&O
= 30,10 jam X Rp. 5.000.000/jam Biaya pemancangan =
150,479,886.44 Rp
Profit 10% = + 5. = Rp m² = Rp m² HSP Pekerjaan = /batang 6. = + = = Rp165,527,875 Harga Penawaran Rp190,357,056
Jumlah tiang pancang Rp165,527,875
36 Rp4,597,997
Harga Penawaran Biaya Actual
15,047,988.64 Rp
Biaya pemancangan = Rp 165,527,875.09
=
= 8166.67 lb
= 240000 lb
Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .
m 0.394 Inchi
simpanan tiang akibat tekana izin sementara
m 0.197 Inchi
tekanan izin sementara
m 0.118 Inchi
ft meter
50.16 menit 30.10 jam
+ +
Profit Pajak 15%
ITEM NUMBER : Sta. 0+000 s/d 20+000 UNIT OF WORK : Cu.m
QUANTITY OF WORK : DAILY/HOURLY OUTPUT :
NO. DESCRIPTION UNIT ALAT QUANTITY UNIT A. Pekerjaan Badan Jalan (Subgrade)
A.1 Penggalian Badan Jalan
Buldozer 11 172,800 M3
A.2 Pengangkutan Galian
Wheel Loader 5 138,240 M3
Dump Truck 10 138,240 M3
A.3 Pemadatan Badan Jalan
Tandem Roller 1 72,000 M3
A.4 Perapian Badan Jalan
Motor Grader 1 72,000 M2
B. Pekerjaan Tebing B.1 Penggalian Tebing
Excavator PC 200 1 22,350 M3
Sub Total = (A + B ) Overhead and Profit TOTAL Before Tax Tax
TOTAL
UNIT PRICE ANALYSIS
Sub Total
Q BP & O Real Cost Durasi ( m3/hour) (Rp/hour) (Rp/m3) hari 134.95 2,952,000 240,625.00 20.0 141.60 1,250,000 44,139.41 33.5 77.93 262,500 33,683.74 30.4 17,637.50 2,000,000 113.39 0.7 1,344.60 2,200,000 1,636.17 9.2 320,197.71 186.25 1,200,000 6,442.88 0.7 6,442.88 326,640.60 % Profit = 15% 48,996.09 375,636.69 % Tax = 15% 56,345.50 431,982.19