• Tidak ada hasil yang ditemukan

Slide TSP308 TSP 308 004 Metoda dan Peralatan Konstruksi

N/A
N/A
Protected

Academic year: 2017

Membagikan "Slide TSP308 TSP 308 004 Metoda dan Peralatan Konstruksi"

Copied!
24
0
0

Teks penuh

(1)

Compaction and Stabilization

Equipment

Lecture 4

Ferdinand Fassa TSP-308 MPK

(2)

2

OUTLINE

1.

Introduction

2.

Type of Compacting Equipment

3.

Soil Stabilization

(3)

3

Introduction (1)

Compaction

Process of increasing the density of a soil by

mechanically forcing the soil particles closer

together

If performed improperly, settlement of the soil could

occur and result in unnecessary maintenance costs

(4)

4

Introduction (2)

What is soil?

Soil is formed in place or deposited by various forces of

nature such as glaciers, wind, lakes and rivers, residually or

organically.

Following are important elements in soil compaction:

Soil type

Soil moisture content

(5)

Introduction (3)

5

Compaction seeks to improve the Quality (property) of Soil

 Reduce or prevent settlement

 Increase strength

 Improve bearing capacity

 Control volume changes

 Lower permeability

(6)

Compaction Actions

6

Kneading

Static Weight

Vibration

Dynamic / Impact

(7)

Tamping Roller

– Effective on all soil

– Working speed 8 – 12 mph

Vibration Compactor

– Have one or two drums

– Working speed 2 – 4 mph

Pneumatic-Tire Rollers

– Used in compacting asphalt, base and sub-base material

7

(8)

8

(9)

9

(10)

10

Soil conditions are often unstable,

They are subject to differential expansion

and shrinkage when undergoing changes

in moisture content

Improvement through chemical and/or

mechanical stabilization

(11)

11

Soil density tests

To determine if proper soil compaction is achieved for any specific construction application, several methods were developed. The most prominent by far is soil density.

Why test

Soil testing accomplishes the following:

• Measures density of soil for comparing the degree

of compaction vs specs

• Measures the effect of moisture on soil density vs

specs

• Provides a moisture density curve identifying

optimum moisture

(12)

12

(13)

13

(14)

Proctor Test

14

(15)

Sand Cone Test (ASTM D1556-90)

15

• Dig compacted soil from a hole (6” diam by 6” deep) • Weighed the soil (wet weight)

• Dry the soil

• Weigh the soil (dry weight)

• Fill the hole with dry sand and measure its volume

(16)

16

Compaction Mechanism (type of equipment)

Type of Soil

Thickness of layer (lift)

Weight of Compactor

Efficiency

Factors Affecting the Effectiveness of Compaction

(17)

17

Method of Soil Stabilization

Chemical Stabilization

 Incorporating lime (w/ fly ash) for high clay content soil

 Incorporate Portland cement for granular soil

(18)

18

Lime Stabilization Construction Procedure

Soil Stabilization (8)

• Scarification and pulverization

• Lime Spreading

• Preliminary Mixing and additional water

• Preliminary curing (cure 24 to 48 hours)

• Final mixing

• Compaction

(19)

19

Soil Cement Stabilization Construction Procedure

Soil Stabilization (9)

• Spreading

• Mixing

• Compaction

(20)

20

Compactor Productivity

Compacted Quantity / Hour (Productivity)

(21)

21

Compactor Productivity

Q

=

16.3 W

x

S

x

L x E

(22)

A self-propelled tamping foot compactor will be used to compact a fill being constructed of clay material. Field tests have shown that the

required density can be achieved with four passes of the roller

operating at an average speed 3 mph. the compacted lift will have a thickness of 6 in. The compacting width of this machine is 7 ft. one bcy equals 0.83 ccy. The scraper production, estimated for the project is 510 bcy/hr. how many roller will be required to maintain this

production? Assume a 50 min hour efficiency.

Solution…??

22

(23)

23

(24)

24

Homework

Find article (s) on soil (chemical) stabilization

Describe and discuss method of work in a paper

of at least 5 pages (A4) printed on one side

Presented in PPT format

Referensi

Dokumen terkait

The purposes of this study are to obtain the optimum yield of biodiesel from creamer wastes as revealed by the neutralization process, catalyst concentration,

 Predict and calculate the cash flow, The owner is obligated to make timely progress payments to the contractor and other parties along the life of the project. Project Owner

– The earliest and latest start times for each activity which will not alter the earliest completion time of the project. – The earliest finish times for each activity which will

In 1958, this tool was developed under the name program evaluation and review technique and later became known by its acronym, PERT1. The PERT system was adopted in its early days

Therefore, alternatively, instead of completely halting activity B during intervals, we can reduce the crew size to slow the rate until there is a safe time buffer (a. combination

This is a more significant change order that includes widening the door openings, that is, demolition of part of the masonry walls covered by drywall and painted, and installing

Impact durability refers to the property that the steel resist loads without being damaged. The impact durability of the steel can be influenced by temperature

From Lab to Field: Enhancing Bioremediation Process by Increasing Bioavailability of the Contaminant Case: Crude Oil Contaminated Soil Bioremediation Agus Jatnika Effendi Faculty