CONSTRUCTION OF LAMPESUE BRIDGES
Commulative Progess for This Week Based on Schedule Revisi-2 (January 2024 - August 2024)
Description Previous Now Up To Description % Up to This Rencana
Week Deviasi
A1. CONTRACTOR OVERHEAD 12.435% 0.149% 12.584% A1. CONTRACTOR OVERHEAD 15.261% 12.584% 12.490% 0.094%
A2.1. MAJOR WORK (ROAD) 15.008% 0.061% 15.070% A2.1. MAJOR WORK (ROAD) 80.868% 15.070% 18.669% -3.600%
A3. VARIATION CONTRACT 0.959% 0.075% 1.035% A3. VARIATION CONTRACT 3.871% 1.035% 1.035% 0.000%
Grand Total 28.402% 0.286% 28.688% Grand Total 100.00% 28.688% 32.194% -3.505%
Work Item for This Week
Work Item Previous Now Up To Description Up To This
Week Plan Dev Complete Remark
7.1.3. Mobilization and Demobilization 0.789% 0.000% 0.789% 7.1.3. Mobilization and Demobilization 0.789% 0.557% 0.232% 32.4%
7.1.24. Bore Pile Concrete Cast-in-place D=80cm, (Bertulang) 2.678% 0.000% 2.678% 7.1.4. Field Office and Facilities 1.042% 1.230% -0.188% 100.0%
7.1.4. Field Office and Facilities 1.042% 0.000% 1.042% 7.1.5. Overhead 10.753% 10.702% 0.051% 91.2%
7.1.5. Overhead 10.603% 0.149% 10.753% 7.1.6(a). Land Clearing and Grubbing 0.292% 1.269% -0.977% 23.0%
7.1.6(a). Land Clearing and Grubbing 0.292% 0.000% 0.292% 7.1.10(a). Cut to Fill Haul Less than 2 Km 0.000% 0.002% -0.002% 0.0%
7.1.22. Reinforcement BJTD 40 7.911% 0.061% 7.972% 7.1.21d. Concrete Fc'=30 MPa Abutment, Pile cap,
Plat Injak 0.000% 0.635% -0.635% 0.00%
7.1.28. Gabion 4.127% 0.000% 4.127% 7.1.22. Reinforcement BJTD 40 7.972% 8.252% -0.280% 86.2%
1. Penyediaan lahan untuk workshop dan kantor kontraktor 0.355% 0.000% 0.355% 7.1.24. Bore Pile Concrete Cast-in-place D=80cm,
(Bertulang) 2.678% 4.069% -1.392% 19.8%
2. Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal
0.604% 0.075% 0.679% 7.1.28. Gabion 4.127% 4.441% -0.314% 48.6%
Grand Total 28.402% 0.286% 28.688% 1. Penyediaan lahan untuk workshop dan kantor kontraktor 0.355% 0.355% 0.000% 100.0%
2. Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal
0.679% 0.679% 0.000% 27.3%
No Highlight Grand Total 28.688% 32.194% -3.505% 528.57%
Detail Faktor Keterlambatan terhadap Schedule Revisi-2 (January 2024 - August 2024) Faktor Keterlambatan terhadap Schedule Revisi-2 (January 2024 - August 2024)
2 Unit Excavator & 3 unit DT, 1 unit Vibro & Dozer, Borepile Machine & Crane,
(Proses Rekruitment, Akad & Training karyawan)
2 titik (besi, bor, conc) + 25 nos pabrikasi menunggu pembebasan lahan antara pt. vale dgn pemilik tanah di lokasi AB-1
Menunggu Pekerjaan Borepile Selesai Kontrak
Mulai Add-1 Selesai Add-1 Total Terpakai Sisa
01 January 2024 31 August 2024 243 hari
71 hari 172 hari
29%
13 March'23 - 14 Jan'24
Weekly Progress Report
Periode W51 26 February 2024 s/d 03 March 2024
Fatality Near Miss LTI (Lost Time Injury) JSA/SOP SOI TBM
Safety Performance Status Prev Now Up to 0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
83 0 83
85 0
85 20 47 17
Safety Performance Status Prev Now Up to Number of Staff
Number of Local Manpower Number of Non Local Manpower
20 0 20
47 0 47
17 0 17
Total Manpower
Staff Lokal Power Subkon
Monitoring Material & Alat Total Status
Gabion 2883 Unit (MOS)
Reinforcement BJTD 40 208.91 Ton (MOS)
84 Org
Dump Truck Excavator
Borepile machine (Drilling & Crane)
2 Unit (on Site) 2
2
Unit (on Site) Unit (on Site)
Vibro Roller 1 Unit (on Site)
Buldozer 1 Unit (on Site)
S/D
PROJECT : CONSTRUCTION OF LAMPESUE BRIDGES
OWNER : PT. VALE INDONESIA, Tbk.
CONTRACTOR : PT. NUSA KONSTRUKSI ENJINIRING, Tbk.
CONTRACT REF. : 4600075570
CONTRACT AMD-1
2 3 4 5 6 7 8 9 10 11 12 13 14 15
CONTRACTOR OVERHEAD
7.1.3 Mobilization and Demobilization 1.00 ls 2.530% 903,650,000.00 903,650,000.00 2.432% 0.324 0.789% - 0.000% 0.324 0.789% 0.557% 0.23% 32.44%
7.1.4 Field Office and Facilities 1.00 ls 1.084% 387,200,000.00 387,200,000.00 1.042% 1.000 1.042% - 0.000% 1.000 1.042% 1.230% -0.19% 100.00%
7.1.5 Overhead 1.00 ls 12.261% 4,378,835,000.00 4,378,835,000.00 11.787% 0.900 10.603% 0.013 0.149% 0.912 10.753% 10.702% 0.05% 91.23%
MAJOR WORK (ROAD) 7.1.6(a) Land Clearing and Grubbing
Land Clearing and Grubbing. Scope Land Clearing pada pekerjaan ini adalah pembersihan area sekitar jembatan yang telah bersih dari pepohonan dan tidak ada pekerjaan grubbing lagi.
7,200.00
m2 1.321% 65,500.23 471,601,656.00 1.269% 1,656.000 0.292% - 0.000% 1,656.000 0.292% 1.269% -0.98% 23.00%
7.1.6(b) Sub Grade Preparation Sub Grade Preparation. Scopenya berupa persiapan sub grade pada pangkal
jembatan kanan dan kiri, hanya berupa jasa persiapan saja. 3,600.00 m2 0.202% 20,032.33 72,116,388.00 0.194% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.10(a) Cut to Fill Haul Less than 2 Km
Cut to Fill Haul Less than 2 Km. Scope pekerjaan adalah penggalian dan penghamparan material jembatan dengan estimasi kurang dari 2 km (kanan-kiri dari sisi jembatan mulai dari plat injak sampai ke titik temu jalan hauling.
10.91
m3 0.002% 74,153.65 809,016.32 0.002% - 0.000% - 0.000% - 0.000% 0.002% 0.00% 0.00%
7.1.12(a) Fill Borrow material (5 km)
Fill Borrow material (5 km). Scope adalah menyediakan timbunan untuk pembatas jalan (safety berm) yang dapat diambil dari lokasi Quarry yang ditetapkan oleh PTVI dengan estimasi 45 km.
8,623.23
m3 6.343% 262,678.94 2,265,140,915.78 6.097% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.12(c) Safety Berm
Safety Berm. Scope adalah menyediakan timbunan dan memasang timbunan untuk pembatas jalan (safety berm) yang dapat diambil dari lokasi Quarry yang ditetapkan oleh PTVI dengan estimasi 45 km.
801.00
m3 0.589% 262,678.94 210,405,830.94 0.566% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.16(a1) Quarrying, Crushing and Stockpiling (aggregate Ap.35
Quarrying, Crushing and Stockpiling (aggregate Ap.35. Scope hanya untuk pengambilan AP35 dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.
648.00
m3 0.686% 378,217.57 245,084,985.36 0.660% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.16(a2) Load, Haul, Dump, (aggregate Ap.35) (distance 7.5 km)
Load, Haul, Dump, (aggregate Ap.35) (distance 7.5 km). Scope berupa meloading dan dumping material aggregate AP35. Untuk AP35 diambil dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.
648.00
m3 0.000% - - 0.000% - 0.000% - 0.000% - 0.000% 0.000% 0.00% #DIV/0!
7.1.16(a3) Spreading, watering and compacting (aggregate Ap35)
Spreading, watering and compacting (aggregate Ap35). Scope berupa menghampar material sambil penyiraman dan pemadatan dengan menggunakan aggregat AP35.
540.00
m3 0.187% 123,492.04 66,685,701.60 0.179% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.16(b3) Loading Hauling Batu Rejected Pembatas Jalan
Loading Hauling Batu Rejected Pembatas Jalan. Scope berupa meloading material batu reject sebagai pembatas jalan. Untuk batu Reject diambil dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.
220.50
m3 0.261% 423,069.26 93,286,771.83 0.251% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.19 Tack coat (on slab) Tack coat (on slab). Scope berupa pengadaan tack coat dan penghamparan. 432.00 litre 0.037% 30,566.58 13,204,762.56 0.036% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.20 Asphalt Concrete Wearing Course Asphalt Concrete Wearing Course. Scope berupa pengadaan aspal dan
penghamparan aspal. 62.10 ton 0.633% 3,640,664.30 226,085,253.03 0.609% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.21a Concrete Fc'=30 MPa Lantai Jembatan Concrete Fc'=30 MPa Lantai Jembatan. Scope berupa pengadaan beton dan
pengecoran. 146.25 m3 2.617% 6,390,401.01 934,596,147.71 2.516% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.21b Concrete Fc'=30 MPa Diagfragma Concrete Fc'=30 MPa Diagfragma. Scope berupa pengadaan beton dan
pengecoran. 20.79 m3 0.521% 8,944,675.07 185,959,794.71 0.501% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.21c Concrete Fc'=30 MPa Barrier Concrete Fc'=30 MPa Barrier. Scope berupa pengadaan beton dan pengecoran. 34.20 m3 0.617% 6,441,252.62 220,290,839.60 0.593% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.21d Concrete Fc'=30 MPa Abutment, Pile cap, Plat Injak Concrete Fc'=30 MPa Abutment, Pile cap, Plat Injak. Scope berupa pengadaan
beton dan pengecoran. 587.95 m3 7.265% 4,412,803.00 2,594,523,409.94 6.984% - 0.000% - 0.000% - 0.000% 0.635% -0.63% 0.00%
7.1.22 Reinforcement BJTD 40 Reinforcement BJTD 40, Scope berupa pengadaan besi tulangan dan
pembentukan, pembengkokan sesuai Bar Bending Schedule. 140,935.49 kg 9.621% 24,380.46 3,436,072,062.23 9.249% 120,550.100 7.911% 931.337 0.061% 121,481.437 7.972% 8.252% -0.28% 86.20%
7.1.23 PC-I Girder 45m, H=2.10m PC-I Girder 45m, H=2.10m. Scope berupa pembuatan PC-I Girder dan
pemasangan PC-I Girder. 6.00 unit 29.940% 1,782,087,615.00 10,692,525,690.00 28.781% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.24 Bore Pile Concrete Cast-in-place D=80cm, (Bertulang) Bore Pile Concrete Cast-in-place D=80cm, (Bertulang). Scope berupa pengeboran,
pemasangan casing, pengecoran tiang bor. Include tulangan dan Testing PDA Test 540.00 Lin.m 14.048% 9,290,352.61 5,016,790,409.40 13.504% 107.086 2.678% - 0.000% 107.086 2.678% 4.069% -1.39% 19.83%1 titik (Besi, instal l, cor)
7.1.25 Elastomeric Bearing Pad 450 x 650 x 56
Elastomeric Bearing Pad 450 x 650 x 56. Scope adalah pengadaan Material dan pemasangan Elastometric Bearing.
B10M (aggr 10-14mm)
12.00
unit 0.206% 6,134,802.49 73,617,629.88 0.198% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.26 Rubber Bearing Sheet 200 x 200 x 20 Rubber Bearing Sheet 200 x 200 x 20. Scope adalah pengadaan Material dan
pemasangan Rubber Bearing. 12.00 unit 0.015% 456,866.67 5,482,400.04 0.015% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.27 Deck Drain Tipe 1 dengan perlengkapan Deck Drain Tipe 1 dengan perlengkapan. Scope adalah pengadaan Material dan
pemasangan Deck Drain. 20.00 unit 0.179% 3,199,748.75 63,994,975.00 0.172% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
7.1.28 Gabion Gabion. Scope adalah pengadaan Material (keranjang dan batu) dan
pemasangan Gabion. Untuk batu diambil dari Quarry yang ditetapkan PTVI 2,678.00 m3 8.834% 1,178,086.37 3,154,915,298.86 8.492% 1,301.592 4.127% - 0.000% 1,301.592 4.127% 4.441% -0.31% 48.60%
VARIATION CONTRACT
1 Penyediaan lahan untuk workshop dan kantor kontraktor 1.00 ls 132,000,000.00 132,000,000.00 0.355% 1.000 0.355% - 0.000% 1.000 0.355% 0.355% 0.00% 100.00%
2 Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal
Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal,
penambahan kendaraan operational 1(satu) unit L/V & penambahan 1 (satu) unit 1.00 ls 925,590,000.00 925,590,000.00 2.491% 0.242 0.604% 0.030 0.075% 0.273 0.679% 0.679% 0.00% 27.27%
3 Pekerjaan pembuatan barrier di tengah jembatan untuk
pemisahan jalan hauling dan jalan umum 1.00 ls 380,619,880.00 380,619,880.00 1.025% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%
100% 37,151,084,818.79 100%
28.402% 0.286% 28.688%
29.708% 2.486% 32.194%
-1.306% -2.199% -3.505%
Approved by
0.231590251 23.108%Prepared by
The Consultant
0.051% 0.00The Contractor
PT Wiratman
9.538%PT.Nusa Konstruksi Enjiniring,Tbk
9.488%
( ) NOVRI KUSUMATHALHAH
Project Manager REALISASI PROGRESS PEKERJAAN
26-Feb-2024 3-Mar-2024
NO QTY UNIT BOBOT
(%) KET.
QTY BOBOT
(% ) QTY BOBOT
(% ) QTY BOBOT
(% )
Komulatif Realisasi Mingguan Komulatif Rencana Mingguan Deviasi
ITEM DESCRIPTION
A2.1 1 A1
A2.1
HARSAT JUMLAH BOBOT
(%)
% COMPLETE
Total Bobot
S/D MINGGU LALU MINGGU INI S/D MINGGU INI REN CA N A S/D MIN GGU
W51 DEVIA SI