LAPORAN KONSTRUKSI JEMBATAN LAMPESUE

N/A
N/A
Imron Sjamsuddin

Academic year: 2024

Membagikan "LAPORAN KONSTRUKSI JEMBATAN LAMPESUE"

Copied!
2
0
0

Teks penuh

(1)

CONSTRUCTION OF LAMPESUE BRIDGES

Commulative Progess for This Week Based on Schedule Revisi-2 (January 2024 - August 2024)

Description Previous Now Up To Description % Up to This Rencana

Week Deviasi

A1. CONTRACTOR OVERHEAD 12.435% 0.149% 12.584% A1. CONTRACTOR OVERHEAD 15.261% 12.584% 12.490% 0.094%

A2.1. MAJOR WORK (ROAD) 15.008% 0.061% 15.070% A2.1. MAJOR WORK (ROAD) 80.868% 15.070% 18.669% -3.600%

A3. VARIATION CONTRACT 0.959% 0.075% 1.035% A3. VARIATION CONTRACT 3.871% 1.035% 1.035% 0.000%

Grand Total 28.402% 0.286% 28.688% Grand Total 100.00% 28.688% 32.194% -3.505%

Work Item for This Week

Work Item Previous Now Up To Description Up To This

Week Plan Dev Complete Remark

7.1.3. Mobilization and Demobilization 0.789% 0.000% 0.789% 7.1.3. Mobilization and Demobilization 0.789% 0.557% 0.232% 32.4%

7.1.24. Bore Pile Concrete Cast-in-place D=80cm, (Bertulang) 2.678% 0.000% 2.678% 7.1.4. Field Office and Facilities 1.042% 1.230% -0.188% 100.0%

7.1.4. Field Office and Facilities 1.042% 0.000% 1.042% 7.1.5. Overhead 10.753% 10.702% 0.051% 91.2%

7.1.5. Overhead 10.603% 0.149% 10.753% 7.1.6(a). Land Clearing and Grubbing 0.292% 1.269% -0.977% 23.0%

7.1.6(a). Land Clearing and Grubbing 0.292% 0.000% 0.292% 7.1.10(a). Cut to Fill Haul Less than 2 Km 0.000% 0.002% -0.002% 0.0%

7.1.22. Reinforcement BJTD 40 7.911% 0.061% 7.972% 7.1.21d. Concrete Fc'=30 MPa Abutment, Pile cap,

Plat Injak 0.000% 0.635% -0.635% 0.00%

7.1.28. Gabion 4.127% 0.000% 4.127% 7.1.22. Reinforcement BJTD 40 7.972% 8.252% -0.280% 86.2%

1. Penyediaan lahan untuk workshop dan kantor kontraktor 0.355% 0.000% 0.355% 7.1.24. Bore Pile Concrete Cast-in-place D=80cm,

(Bertulang) 2.678% 4.069% -1.392% 19.8%

2. Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal

0.604% 0.075% 0.679% 7.1.28. Gabion 4.127% 4.441% -0.314% 48.6%

Grand Total 28.402% 0.286% 28.688% 1. Penyediaan lahan untuk workshop dan kantor kontraktor 0.355% 0.355% 0.000% 100.0%

2. Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal

0.679% 0.679% 0.000% 27.3%

No Highlight Grand Total 28.688% 32.194% -3.505% 528.57%

Detail Faktor Keterlambatan terhadap Schedule Revisi-2 (January 2024 - August 2024) Faktor Keterlambatan terhadap Schedule Revisi-2 (January 2024 - August 2024)

2 Unit Excavator & 3 unit DT, 1 unit Vibro & Dozer, Borepile Machine & Crane,

(Proses Rekruitment, Akad & Training karyawan)

2 titik (besi, bor, conc) + 25 nos pabrikasi menunggu pembebasan lahan antara pt. vale dgn pemilik tanah di lokasi AB-1

Menunggu Pekerjaan Borepile Selesai Kontrak

Mulai Add-1 Selesai Add-1 Total Terpakai Sisa

01 January 2024 31 August 2024 243 hari

71 hari 172 hari

29%

13 March'23 - 14 Jan'24

Weekly Progress Report

Periode W51 26 February 2024 s/d 03 March 2024

Fatality Near Miss LTI (Lost Time Injury) JSA/SOP SOI TBM

Safety Performance Status Prev Now Up to 0 0 0

0 0 0

0 0 0

0 0 0

0 0 0

83 0 83

85 0

85 20 47 17

Safety Performance Status Prev Now Up to Number of Staff

Number of Local Manpower Number of Non Local Manpower

20 0 20

47 0 47

17 0 17

Total Manpower

Staff Lokal Power Subkon

Monitoring Material & Alat Total Status

Gabion 2883 Unit (MOS)

Reinforcement BJTD 40 208.91 Ton (MOS)

84 Org

Dump Truck Excavator

Borepile machine (Drilling & Crane)

2 Unit (on Site) 2

2

Unit (on Site) Unit (on Site)

Vibro Roller 1 Unit (on Site)

Buldozer 1 Unit (on Site)

(2)

S/D

PROJECT : CONSTRUCTION OF LAMPESUE BRIDGES

OWNER : PT. VALE INDONESIA, Tbk.

CONTRACTOR : PT. NUSA KONSTRUKSI ENJINIRING, Tbk.

CONTRACT REF. : 4600075570

CONTRACT AMD-1

2 3 4 5 6 7 8 9 10 11 12 13 14 15

CONTRACTOR OVERHEAD

7.1.3 Mobilization and Demobilization 1.00 ls 2.530% 903,650,000.00 903,650,000.00 2.432% 0.324 0.789% - 0.000% 0.324 0.789% 0.557% 0.23% 32.44%

7.1.4 Field Office and Facilities 1.00 ls 1.084% 387,200,000.00 387,200,000.00 1.042% 1.000 1.042% - 0.000% 1.000 1.042% 1.230% -0.19% 100.00%

7.1.5 Overhead 1.00 ls 12.261% 4,378,835,000.00 4,378,835,000.00 11.787% 0.900 10.603% 0.013 0.149% 0.912 10.753% 10.702% 0.05% 91.23%

MAJOR WORK (ROAD) 7.1.6(a) Land Clearing and Grubbing

Land Clearing and Grubbing. Scope Land Clearing pada pekerjaan ini adalah pembersihan area sekitar jembatan yang telah bersih dari pepohonan dan tidak ada pekerjaan grubbing lagi.

7,200.00

m2 1.321% 65,500.23 471,601,656.00 1.269% 1,656.000 0.292% - 0.000% 1,656.000 0.292% 1.269% -0.98% 23.00%

7.1.6(b) Sub Grade Preparation Sub Grade Preparation. Scopenya berupa persiapan sub grade pada pangkal

jembatan kanan dan kiri, hanya berupa jasa persiapan saja. 3,600.00 m2 0.202% 20,032.33 72,116,388.00 0.194% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.10(a) Cut to Fill Haul Less than 2 Km

Cut to Fill Haul Less than 2 Km. Scope pekerjaan adalah penggalian dan penghamparan material jembatan dengan estimasi kurang dari 2 km (kanan-kiri dari sisi jembatan mulai dari plat injak sampai ke titik temu jalan hauling.

10.91

m3 0.002% 74,153.65 809,016.32 0.002% - 0.000% - 0.000% - 0.000% 0.002% 0.00% 0.00%

7.1.12(a) Fill Borrow material (5 km)

Fill Borrow material (5 km). Scope adalah menyediakan timbunan untuk pembatas jalan (safety berm) yang dapat diambil dari lokasi Quarry yang ditetapkan oleh PTVI dengan estimasi 45 km.

8,623.23

m3 6.343% 262,678.94 2,265,140,915.78 6.097% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.12(c) Safety Berm

Safety Berm. Scope adalah menyediakan timbunan dan memasang timbunan untuk pembatas jalan (safety berm) yang dapat diambil dari lokasi Quarry yang ditetapkan oleh PTVI dengan estimasi 45 km.

801.00

m3 0.589% 262,678.94 210,405,830.94 0.566% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.16(a1) Quarrying, Crushing and Stockpiling (aggregate Ap.35

Quarrying, Crushing and Stockpiling (aggregate Ap.35. Scope hanya untuk pengambilan AP35 dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.

648.00

m3 0.686% 378,217.57 245,084,985.36 0.660% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.16(a2) Load, Haul, Dump, (aggregate Ap.35) (distance 7.5 km)

Load, Haul, Dump, (aggregate Ap.35) (distance 7.5 km). Scope berupa meloading dan dumping material aggregate AP35. Untuk AP35 diambil dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.

648.00

m3 0.000% - - 0.000% - 0.000% - 0.000% - 0.000% 0.000% 0.00% #DIV/0!

7.1.16(a3) Spreading, watering and compacting (aggregate Ap35)

Spreading, watering and compacting (aggregate Ap35). Scope berupa menghampar material sambil penyiraman dan pemadatan dengan menggunakan aggregat AP35.

540.00

m3 0.187% 123,492.04 66,685,701.60 0.179% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.16(b3) Loading Hauling Batu Rejected Pembatas Jalan

Loading Hauling Batu Rejected Pembatas Jalan. Scope berupa meloading material batu reject sebagai pembatas jalan. Untuk batu Reject diambil dari Quarry yang ditetapkan PTVI dengan estimasi jarak 45 km.

220.50

m3 0.261% 423,069.26 93,286,771.83 0.251% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.19 Tack coat (on slab) Tack coat (on slab). Scope berupa pengadaan tack coat dan penghamparan. 432.00 litre 0.037% 30,566.58 13,204,762.56 0.036% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.20 Asphalt Concrete Wearing Course Asphalt Concrete Wearing Course. Scope berupa pengadaan aspal dan

penghamparan aspal. 62.10 ton 0.633% 3,640,664.30 226,085,253.03 0.609% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.21a Concrete Fc'=30 MPa Lantai Jembatan Concrete Fc'=30 MPa Lantai Jembatan. Scope berupa pengadaan beton dan

pengecoran. 146.25 m3 2.617% 6,390,401.01 934,596,147.71 2.516% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.21b Concrete Fc'=30 MPa Diagfragma Concrete Fc'=30 MPa Diagfragma. Scope berupa pengadaan beton dan

pengecoran. 20.79 m3 0.521% 8,944,675.07 185,959,794.71 0.501% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.21c Concrete Fc'=30 MPa Barrier Concrete Fc'=30 MPa Barrier. Scope berupa pengadaan beton dan pengecoran. 34.20 m3 0.617% 6,441,252.62 220,290,839.60 0.593% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.21d Concrete Fc'=30 MPa Abutment, Pile cap, Plat Injak Concrete Fc'=30 MPa Abutment, Pile cap, Plat Injak. Scope berupa pengadaan

beton dan pengecoran. 587.95 m3 7.265% 4,412,803.00 2,594,523,409.94 6.984% - 0.000% - 0.000% - 0.000% 0.635% -0.63% 0.00%

7.1.22 Reinforcement BJTD 40 Reinforcement BJTD 40, Scope berupa pengadaan besi tulangan dan

pembentukan, pembengkokan sesuai Bar Bending Schedule. 140,935.49 kg 9.621% 24,380.46 3,436,072,062.23 9.249% 120,550.100 7.911% 931.337 0.061% 121,481.437 7.972% 8.252% -0.28% 86.20%

7.1.23 PC-I Girder 45m, H=2.10m PC-I Girder 45m, H=2.10m. Scope berupa pembuatan PC-I Girder dan

pemasangan PC-I Girder. 6.00 unit 29.940% 1,782,087,615.00 10,692,525,690.00 28.781% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.24 Bore Pile Concrete Cast-in-place D=80cm, (Bertulang) Bore Pile Concrete Cast-in-place D=80cm, (Bertulang). Scope berupa pengeboran,

pemasangan casing, pengecoran tiang bor. Include tulangan dan Testing PDA Test 540.00 Lin.m 14.048% 9,290,352.61 5,016,790,409.40 13.504% 107.086 2.678% - 0.000% 107.086 2.678% 4.069% -1.39% 19.83%1 titik (Besi, instal l, cor)

7.1.25 Elastomeric Bearing Pad 450 x 650 x 56

Elastomeric Bearing Pad 450 x 650 x 56. Scope adalah pengadaan Material dan pemasangan Elastometric Bearing.

B10M (aggr 10-14mm)

12.00

unit 0.206% 6,134,802.49 73,617,629.88 0.198% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.26 Rubber Bearing Sheet 200 x 200 x 20 Rubber Bearing Sheet 200 x 200 x 20. Scope adalah pengadaan Material dan

pemasangan Rubber Bearing. 12.00 unit 0.015% 456,866.67 5,482,400.04 0.015% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.27 Deck Drain Tipe 1 dengan perlengkapan Deck Drain Tipe 1 dengan perlengkapan. Scope adalah pengadaan Material dan

pemasangan Deck Drain. 20.00 unit 0.179% 3,199,748.75 63,994,975.00 0.172% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

7.1.28 Gabion Gabion. Scope adalah pengadaan Material (keranjang dan batu) dan

pemasangan Gabion. Untuk batu diambil dari Quarry yang ditetapkan PTVI 2,678.00 m3 8.834% 1,178,086.37 3,154,915,298.86 8.492% 1,301.592 4.127% - 0.000% 1,301.592 4.127% 4.441% -0.31% 48.60%

VARIATION CONTRACT

1 Penyediaan lahan untuk workshop dan kantor kontraktor 1.00 ls 132,000,000.00 132,000,000.00 0.355% 1.000 0.355% - 0.000% 1.000 0.355% 0.355% 0.00% 100.00%

2 Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal

Penambahan 4 (empat) orang tenaga kerja yang direkrut dari tenaga lokal,

penambahan kendaraan operational 1(satu) unit L/V & penambahan 1 (satu) unit 1.00 ls 925,590,000.00 925,590,000.00 2.491% 0.242 0.604% 0.030 0.075% 0.273 0.679% 0.679% 0.00% 27.27%

3 Pekerjaan pembuatan barrier di tengah jembatan untuk

pemisahan jalan hauling dan jalan umum 1.00 ls 380,619,880.00 380,619,880.00 1.025% - 0.000% - 0.000% - 0.000% 0.000% 0.00% 0.00%

100% 37,151,084,818.79 100%

28.402% 0.286% 28.688%

29.708% 2.486% 32.194%

-1.306% -2.199% -3.505%

Approved by

0.231590251 23.108%

Prepared by

The Consultant

0.051% 0.00

The Contractor

PT Wiratman

9.538%

PT.Nusa Konstruksi Enjiniring,Tbk

9.488%

( ) NOVRI KUSUMATHALHAH

Project Manager REALISASI PROGRESS PEKERJAAN

26-Feb-2024 3-Mar-2024

NO QTY UNIT BOBOT

(%) KET.

QTY BOBOT

(% ) QTY BOBOT

(% ) QTY BOBOT

(% )

Komulatif Realisasi Mingguan Komulatif Rencana Mingguan Deviasi

ITEM DESCRIPTION

A2.1 1 A1

A2.1

HARSAT JUMLAH BOBOT

(%)

% COMPLETE

Total Bobot

S/D MINGGU LALU MINGGU INI S/D MINGGU INI REN CA N A S/D MIN GGU

W51 DEVIA SI

Referensi

Dokumen terkait

Berdasarkan Surat Nomor : 17/TAP.PMNG/POKJA/DPU-KBS/VIII/2015 Tanggal 24 Agustus 2015 Tentang Pengumuman Pemenang Lelang Pekerjaan "Pembangunan jembatan Beton Wae wetnawen "

Berdasarkan Penetapan Pemenang Nomor : 19.6/POKJA II-ULP/2016 Tanggal 11 Agustus 2016 Pekerjaan Jasa Konsultansi Perencanaan Studi Kelayakan Pembangunan Jembatan

Adapun Penyedia Jasa yang ditetapkan sebagai Pemenang untuk Paket Pekerjaan Pembangunan Jembatan Jalan Purwahamba - Blubuk Desa Purwahamba Kecamatan Suradadi adalah

Selanjutnya pada setiap minggu kedua bulan Juli dan minggu kedua bulan Januari tahun berikutnya Kepala Kantor Wilayah menyampaikan Laporan Hasil Pembinaan Kantor

Hanya untuk Keperluan Kantor Saja Nama Jembatan 110.460196 -7.033356 Koordinat BERLIAN I Tanggal Pemeriksaan NIP dari Semarang km. Apabila data tidak betul, perbaikan dapat dibuat

Kesimpulan Berdasarkan hasil penelitian maka dapat ditarik kesimpulan bahwa: Untuk waktu pekerjaan Metode pelaksanaan pada pekerjaan pengecoran plat lantai pada Pembangunan Jembatan