analisa pekerjaan Overflow pada manhole

No sat vol code unit rate total

2.4.6.1 Manhole 0190

Supply HDPE Pipe dia. 450 mm m 7.6 2,925,945 22,295,701

Pipe installation HDPE dia. 450 mm m 7.6 B-2-7-1 4,574,213 34,764,019

Flap Gate pcs 1.0 11,125,000 11,125,000

Demolition of manhole shaft (Include cement grouting) no 1.00 C-54-1-1 2,354,179 2,354,179

Join mortar for manhole shaft m3 0.02 C-7-2-5 1,471,205 35,340

Demolition of canal shaft m3 0.07 C-7-6-1 3,203,149 212,159

Join mortar fot canal shaft m3 0.04 C-7-2-5 1,471,205 62,364

Overflow PVC pipes fitting dia. 450 mm no 1.00 8,523,800 8,523,800

79,372,561 2.4.6.2 Manhole 1149

Supply HDPE Pipe dia. 600 mm m 4.0 5,751,725 23,006,900

Pipe installation HDPE dia. 600 mm m 4.0 B-2-6-1 4,901,255 19,605,020

Flap Gate pcs 1.0 13,000,000 13,000,000

Demolition of manhole shaft (Include cement grouting) no 1.00 C-55-1-1 3,374,330 3,374,330

Join mortar for manhole shaft m3 0.03 C-7-2-5 1,471,205 45,942

Demolition of canal shaft m3 0.91 C-7-6-1 3,203,149 2,914,188

Join mortar fot canal shaft m3 0.49 C-7-2-5 1,471,205 724,258

Description

(2)

Overflow PVC pipes fitting dia. 600 mm pcs 1.00 15,143,200 15,143,200 77,813,838 2.4.6.3 Manhole 1389

Supply HDPE Pipe dia. 450 mm m 20.5 2,925,945 59,981,873

Pipe installation HDPE dia. 450 mm m 20.5 B-2-7-1 4,574,213 93,771,367

Flap Gate pcs 1.0 11,125,000 11,125,000

Demolition of manhole shaft (Include cement grouting) no 1.00 C-54-1-1 2,354,179 2,354,179

Join mortar for manhole shaft m3 0.02 C-7-2-5 1,471,205 35,340

Demolition of canal shaft m3 0.65 C-7-6-1 3,203,149 2,093,298

Join mortar fot canal shaft m3 0.42 C-7-2-5 1,471,205 615,329

Overflow PVC pipes fitting dia. 450 mm no 1.00 8,523,800 8,523,800

178,500,184

Referensi

Dokumen terkait

In this research, in total 68 construction related companies, which belong to three different interconnected sectors (manufacturing, construction and finance), are ranked according

Hierarchy 1 Hierarchy 2 Influencing factors Project costs Wages and related costs Production engineering Operators Project managers Maintenance Acquisition costs Equipment

12.6.5 Kaizen costing takes into consideration costs related to manufacturing stage, which include: a Costs of supply chain b Costs of product redesign c Legal costs d Manufacturing

The document details the purchase of pumps and related equipment for a media

Through the Indices system, the commodity and services included in the construction cost index basket classified according to the classification of construction stages Sixth: Survey

The document outlines a comprehensive safety training program for construction

The document outlines the various types of construction projects and

The document contains a list of construction project tasks, along with their expected start and end