PT.UPADANA SEMESTA BALI Jln. Tukad Badung XVIII C No. 3 Renon Denpasar - Bali

telp : +0361-4783299

[email protected]

www.upadanasemesta.com

PROJECT :

TAROO CAFE

OWNER :

IBU KRISNAWATI

LOKASI :

MAS UBUD, GIANYAR

(2)

PROJECT : TAROO CAFE UBUD CREATED DATED : 11 OKT 2022

OWNER : IBU KRISNAWATI WEEK : 8

LOCATION : MAS UBUD, GIANYAR SUBJECT : SUMMARY OF WORKS

NO URAIAN PEKERJAAN BOBOT LAST WEEK THIS WEEK UNTIL THIS

WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

I PRELIMINARY - TAHAP AWAL 4.99% 84.16% 4.20% 0.00% 0.00% 84.16% 4.20%

II PRELIMINARY - TAHAP 2 4.58% 82.21% 3.77% 2.18% 0.10% 84.39% 3.87%

III PEKERJAAN STRUKTUR TAHAP I

A MAIN BUILDING 27.88% 17.65% 4.92% 0.00% 0.00% 17.65% 4.92%

B AREA PARKIR 1.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

C PAGAR PEMBATAS 4.25% 40.62% 1.72% 24.48% 1.04% 65.10% 2.76%

D POS SATPAM 0.85% 30.46% 0.26% 0.00% 0.00% 30.46% 0.26%

E PEKERJAAN LAIN - LAIN 2.81% 28.37% 0.80% 0.00% 0.00% 28.37% 0.80%

F OUTDOOR SEATING AREA 7.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

G TOILET AREA 3.96% 30.66% 1.21% 2.53% 0.10% 33.19% 1.31%

H PERGOLA 2.35% 2.35% 2.35% 2.35% 2.35% 2.35% 2.35%

I SWIMMING POOL 6.28% 82.86% 5.20% 5.79% 0.36% 88.64% 5.57%

J POOL DECK 0.79% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

K PUMP ROOM 0.95% 1.21% 0.01% 0.00% 0.00% 1.21% 0.01%

L BALANCING TANK CAP. 5 m3 0.55% 1.43% 0.01% 0.00% 0.00% 1.43% 0.01%

IV PEKERJAAN ARSITEKTUR TAHAP I

A MAIN BUILDING 11.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B AREA PARKIR 1.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

C PAGAR PEMBATAS 5.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

D POS SATPAM 0.64% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

E PEKERJAAN LAIN-LAIN 1.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

V PEKERJAAN ARSITEKTUR TAHAP II

A OUTDOOR SEATING AREA 2.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B PERGOLA 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

C TOILET AREA 4.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

D SWIMMING POOL 3.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

E POOL DECK 0.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

F PUMP ROOM 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(3)

% WEIGHT % WEIGHT % WEIGHT

(%)

G BALANCING TANK CAP. 5 m3 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

100.00% 22.10% 1.60% 23.71%

(4)

PROJECT : TAROO CAFE UBUD CREATED DATED : 11 OKT 2022

OWNER : IBU KRISNAWATI WEEK : 8

LOCATION : MAS UBUD, GIANYAR SUBJECT : PRELIMINARY

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

I PRELIMINARY - TAHAP AWAL 4.99% 84.16% 4.20% 0.00% 0.00% 84.16% 4.20%

1 Pembersihan & Perataan 0.95% 100.00% 0.95% 0.00% 0.00% 100.00% 0.95%

2 Pembongkaran Bangunan Existing 0.31% 100.00% 0.31% 0.00% 0.00% 100.00% 0.31%

3 Uitzet 0.98% 100.00% 0.98% 0.00% 0.00% 100.00% 0.98%

4 Bowplank 0.37% 100.00% 0.37% 0.00% 0.00% 100.00% 0.37%

5 Mobilisasi - Demobilisasi Alat 0.12% 100.00% 0.12% 0.00% 0.00% 100.00% 0.12%

6 Urugan Tanah Levelling Lawn Area (Tanah

Urug ± 50cm) 1.47% 100.00% 1.47% 0.00% 0.00% 100.00% 1.47%

7 Urugan Tanah Levelling Lawn Area (Tanah

Subur ± 20cm) 0.79% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

II PRELIMINARY - TAHAP 2 4.58% 82.21% 3.77% 2.18% 0.10% 84.39% 3.87%

1 Pembersihan & Perataan 0.40% 100.00% 0.40% 0.00% 0.00% 100.00% 0.40%

2 Bangunan Sementara

Kantor Sementara 0.40% 100.00% 0.40% 0.00% 0.00% 100.00% 0.40%

Bedeng & Gudang 1.71% 100.00% 1.71% 0.00% 0.00% 100.00% 1.71%

Toilet Untuk Pekerja Proyek dan Septic Tank 0.10% 100.00% 0.10% 0.00% 0.00% 100.00% 0.10%

3 Listrik Sementara

Sambungan Listrik Sementara 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%

Pemakaian Listrik Kerja 0.20% 46.50% 0.10% 6.60% 0.01% 53.10% 0.11%

4 Air Kerja

Tandon Air 0.08% 100.00% 0.08% 0.00% 0.00% 100.00% 0.08%

Pemakaian Air Kerja 0.06% 46.50% 0.03% 6.60% 0.00% 53.10% 0.03%

5 Izin Tenaga Kerja (Kipem) 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

6 Keselamatan Kerja (K3) 0.12% 100.00% 0.12% 0.00% 0.00% 100.00% 0.12%

7 Manajemen Project 0.67% 46.50% 0.31% 6.60% 0.04% 53.10% 0.36%

- Supervisor - Logistik 8 Administrasi

Shop Drawing 0.17% 50.00% 0.09% 10.00% 0.02% 60.00% 0.10%

As Built Drawing 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Laporan Mingguan 0.09% 46.50% 0.04% 6.60% 0.01% 53.10% 0.05%

9 Mobilisasi - Demobilisasi Alat 0.23% 46.50% 0.11% 6.60% 0.02% 53.10% 0.12%

(5)

10 Soil Test 0.12% 100.00% 0.12% 0.00% 0.00% 100.00% 0.12%

(6)

PROJECT : TAROO CAFE UBUD CREATED DATED : 11 OKT 2022

OWNER : IBU KRISNAWATI WEEK : 8

LOCATION : MAS UBUD, GIANYAR SUBJECT : PEKERJAAN STRUKTUR

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

III PEKERJAAN STRUKTUR TAHAP I 59.02% 23.95% 14.14% 2.55% 1.50% 26.50% 15.64%

A MAIN BUILDING 27.88% 17.65% 4.92% 0.00% 0.00% 17.65% 4.92%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.27% 87.40% 0.24% 0.00% 0.00% 87.40% 0.24%

- Pek. Urugan pasir bawah pondasi 50 mm 0.12% 87.40% 0.11% 0.00% 0.00% 87.40% 0.11%

- Pek. Pondasi Batu Kali 1.96% 87.40% 1.71% 0.00% 0.00% 87.40% 1.71%

- Anti termite 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

2 Pedestal / Stump (15x15 cm)

- Pek. Bekisting Plywood Pedestal 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Pedestal 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Pedestal (4D13, Sengkang Ø8-

100) 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Tie Beam (20x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.44% 87.50% 0.38% 0.00% 0.00% 87.50% 0.38%

- Pek. Beton K-250 Tie Beam 0.28% 87.50% 0.24% 0.00% 0.00% 87.50% 0.24%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.65% 87.50% 0.57% 0.00% 0.00% 87.50% 0.57%

4 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai T=1,05 m 1.28% 72.70% 0.93% 0.00% 0.00% 72.70% 0.93%

- Pek. Lantai kerja 50mm 0.39% 23.30% 0.09% 0.00% 0.00% 23.30% 0.09%

- Anti Termite 0.33% 100.00% 0.33% 0.00% 0.00% 100.00% 0.33%

- Pek. Bekisting Plywood Plat Lantai 0.04% 72.70% 0.03% 0.00% 0.00% 72.70% 0.03%

- Pek. Beton K-250 Plat Lantai 0.68% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.39% 16.60% 0.06% 0.00% 0.00% 16.60% 0.06%

5 Kolom

- Bekisting Plywood Kolom Praktis 15x15 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Beton K-250 Kolom Praktis 15x15 T= 3m 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pembesian Kolom Praktis 15x15 (4D13,

Sengkang Ø8-100/150) 0.37% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 15x15 Kolom Kayu Ulin H = 3,7m (recycled

wood) 0.97% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 15x15 Kolom Kayu Ulin H = 1m (recycled

wood) 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(7)

- 15x15 Kolom Kayu Ulin H = 2,7m (recycled

wood) 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Balok

- Bekisting Plywood Ring Balok Praktis 15x15 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Beton K-250 Ring Balok Praktis 15x15 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pembesian Ring Balok Praktis 15x15 (4D13,

Sengkang Ø8-150) 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 15x15 Balok Kayu Bengkirai 4.87% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 6x12 Balok Kayu Bengkirai 0.76% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Struktur Atap

- Pek. Bekisting Plywood Plat Lantai 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton Plat Lantai 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M7 Single Layer 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite Struktur Atap Kayu 0.51% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Kuda-kuda Kayu Bengkirai 8/15 2.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Balok Nok Kayu Bengkirai 8/15 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Usuk Kayu Bengkirai 5/7 @60cm 3.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Penutup Atap Alang-alang 3.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Bubungan 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Ikut Celedu 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Kanopi Kayu Gelam 1.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Polycarbonate + Rangka 1.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B AREA PARKIR 1.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Perkerasan parkir

- Pek. Lantai Kerja 100 mm + Wiremesh M5 1

Layer 1.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

C PAGAR PEMBATAS 4.25% 40.62% 1.72% 24.48% 1.04% 65.10% 2.76%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.26% 57.00% 0.15% 22.20% 0.06% 79.20% 0.21%

- Pek. Urugan pasir bawah pondasi 50 mm 0.17% 51.40% 0.09% 27.80% 0.05% 79.20% 0.14%

- Pek. Pondasi Batu Kali 2.23% 51.40% 1.15% 27.80% 0.62% 79.20% 1.77%

2 Tie Beam (15x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.60% 21.50% 0.13% 19.80% 0.12% 41.30% 0.25%

- Pek. Beton K-250 Tie Beam 0.29% 21.50% 0.06% 19.80% 0.06% 41.30% 0.12%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.69% 21.50% 0.15% 19.80% 0.14% 41.30% 0.28%

(8)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

D POS SATPAM 0.85% 30.46% 0.26% 0.00% 0.00% 30.46% 0.26%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Pondasi Batu Kali 0.05% 100.00% 0.05% 0.00% 0.00% 100.00% 0.05%

- Anti termite 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

2 Tie Beam (15x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%

- Pek. Beton K-250 Tie Beam 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.03% 100.00% 0.03% 0.00% 0.00% 100.00% 0.03%

3 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai T=0,4 m 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Lantai kerja 50mm 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Anti Termite 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Bekisting Plywood Plat Lantai 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Beton K-250 Plat Lantai 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Wiremesh M5 Single Layer 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

4 Kolom

- Bekisting Plywood Kolom Praktis 15x15 0.03% 100.00% 0.03% 0.00% 0.00% 100.00% 0.03%

- Beton K-250 Kolom Praktis 15x15 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pembesian Kolom Praktis 15x15 (4D13,

Sengkang Ø8-100/150) 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

6 Balok

- 15x15 Balok Kayu Bengkirai 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Struktur Atap

- Usuk Kayu Bengkirai 5/7 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Penutup Atap Alang-alang 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Listplank 2x25 cm 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

E PEKERJAAN LAIN - LAIN 2.81% 28.37% 0.80% 0.00% 0.00% 28.37% 0.80%

1 Pekerjaan Urugan Levelling

- Urugan Tanah Peninggian Lantai T=0,60 m 1.60% 50.00% 0.80% 0.00% 0.00% 50.00% 0.80%

- Urugan Levelling Lahan Outdoor (Tanah Subur

20cm) 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(9)

2 Pekerjaan Pondasi Batu Kali Entrance (20x30 cm)

- Pek. Galian Tanah 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pondasi Batu Kali Service Area (20x30 cm)

- Pek. Galian Tanah 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Lantai, Tebal 10cm Entrance

- Pek. Lantai kerja 50mm 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Plat Lantai, Tebal 10cm Service Area

- Pek. Lantai kerja 50mm 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

F OUTDOOR SEATING AREA 7.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Tie Beam (15x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Tie Beam 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(10)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

3 Pedestal / Stump (15x15 cm)

- Pek. Bekisting Plywood Pedestal 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Pedestal 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Pedestal (4D13, Sengkang Ø8-

100) 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai T = 0,65 m 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Lantai kerja 50mm 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plat Lantai 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer Plat Lantai 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Kolom

- 15x15 Kolom Kayu Bengkirai H = 3,15m 0.95% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 15x15 Kolom Kayu Bengkirai H = 2,7m 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Balok

- 6x12 Balok Kayu Bengkirai 0.78% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Penutup Atap

- Kanopi Kayu Gelam 1.46% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Solaf tuff 3mm + Rangka 1.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Stair

- Pek. Pasangan Batako 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

G TOILET AREA 3.96% 30.66% 1.21% 2.53% 0.10% 33.19% 1.31%

1 Pekerjaan Pondasi Batu Kali (30x60cm)

- Pek. Galian Tanah 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

- Pek. Urugan pasir bawah pondasi 50 mm 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

- Pek. Pondasi Batu Kali 0.47% 100.00% 0.47% 0.00% 0.00% 100.00% 0.47%

- Anti termite 0.07% 100.00% 0.07% 0.00% 0.00% 100.00% 0.07%

2 Tie Beam (15x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.14% 100.00% 0.14% 0.00% 0.00% 100.00% 0.14%

- Pek. Beton K-250 Tie Beam 0.07% 100.00% 0.07% 0.00% 0.00% 100.00% 0.07%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%

(11)

3 Pedestal / Stump (15x15 cm)

- Pek. Bekisting Plywood Pedestal 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Pedestal 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Pedestal (4D13, Sengkang Ø8-

100) 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai T=0,65 m 0.12% 0.00% 0.00% 80.00% 0.10% 80.00% 0.10%

- Pek. Lantai kerja 50mm 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.05% 100.00% 0.05% 0.00% 0.00% 100.00% 0.05%

- Pek. Bekisting Plywood Plat Lantai 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Kolom

- Bekisting Kolom Praktis 15x15 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Beton K-250 Kolom Praktis 15x15 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pembesian Kolom Praktis 15x15 (4D13,

Sengkang Ø8-100/150) 0.23% 50.00% 0.11% 0.00% 0.00% 50.00% 0.11%

- 15x15 Kolom Kayu Bengkirai H = 2,35m 0.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Balok

- Bekisting Plywood Ring Balok Praktis 15x15 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Beton K-250 Ring Balok Praktis 15x15 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pembesian Ring Balok Praktis 15x15 (4D13,

Sengkang Ø8-150) 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- 6x12 Balok Kayu Bengkirai 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Struktur Atap

- Penutup Atap Kayu Gelam 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Solaf Tuff + Rangka 0.58% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

H PERGOLA 2.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.43% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Tie Beam (15x30 cm)

(12)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

- Pek. Bekisting Plywood Tie Beam 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Tie Beam 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pedestal / Stump (15x15 cm)

- Pek. Bekisting Plywood Pedestal 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Pedestal 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Pedestal (4D13, Sengkang Ø8-

100) 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Lantai kerja 50mm 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Kolom

- 15x15 Kolom Kayu Bengkirai (H = 2,7m) 0.58% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Balok

- 6x12 Balok Kayu Bengkirai 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Penutup Atap

- Penutup Atap Kayu Gelam 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Solar Tuff 3mm + Rangka 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

I SWIMMING POOL 6.28% 82.86% 5.20% 5.79% 0.36% 88.64% 5.57%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.13% 100.00% 0.13% 0.00% 0.00% 100.00% 0.13%

- Pek. Urugan pasir bawah pondasi 50 mm 0.07% 100.00% 0.07% 0.00% 0.00% 100.00% 0.07%

- Pek. Pondasi Batu Kali 0.55% 100.00% 0.55% 0.00% 0.00% 100.00% 0.55%

- Pek. Urugan Tanah Kembali 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

- Pek. Buangan Tanah Sisa Galian 0.05% 100.00% 0.05% 0.00% 0.00% 100.00% 0.05%

- Anti termite 0.12% 100.00% 0.12% 0.00% 0.00% 100.00% 0.12%

2 Tie Beam (20x40 cm)

- Pek. Bekisting Plywood Tie Beam 0.31% 100.00% 0.31% 0.00% 0.00% 100.00% 0.31%

(13)

- Pek. Beton K-250 Tie Beam 0.20% 100.00% 0.20% 0.00% 0.00% 100.00% 0.20%

- Pek. Pembesian Tie Beam (6D13, Sengkang Ø8-

150) 0.38% 100.00% 0.38% 0.00% 0.00% 100.00% 0.38%

3 Plat Lantai Swimming Pool, Tebal 20cm

- Pek. Galian Tanah 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

- Pek. Urugan pasir bawah plat 50 mm 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

- Pek. Lantai kerja 50mm 0.12% 100.00% 0.12% 0.00% 0.00% 100.00% 0.12%

- Anti Termite 0.10% 100.00% 0.10% 0.00% 0.00% 100.00% 0.10%

- Pek. Bekisting Plywood Plat Lantai 0.00% 100.00% 0.00% 0.00% 0.00% 100.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.43% 100.00% 0.43% 0.00% 0.00% 100.00% 0.43%

- Pek. Pembesian (D10-150 2 layer) 0.59% 100.00% 0.59% 0.00% 0.00% 100.00% 0.59%

4 Plat Dinding Swimming Pool, Tebal 20cm

- Pek. Bekisting Batako 0.07% 100.00% 0.07% 0.00% 0.00% 100.00% 0.07%

- Pek. Bekisting Plywood 0.33% 100.00% 0.33% 0.00% 0.00% 100.00% 0.33%

- Pek. Beton K-250 Plat Dinding 0.24% 20.00% 0.05% 80.00% 0.19% 100.00% 0.24%

- Pek. Pembesian (D10-150 2 layer) 0.38% 100.00% 0.38% 0.00% 0.00% 100.00% 0.38%

5 Plat Lantai Gutter, Tebal 20cm

- Pek. Galian Tanah 0.05% 100.00% 0.05% 0.00% 0.00% 100.00% 0.05%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%

- Pek. Lantai kerja 50mm 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%

- Anti Termite 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%

- Pek. Bekisting Plywood Plat Lantai 0.00% 100.00% 0.00% 0.00% 0.00% 100.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.07% 100.00% 0.07% 0.00% 0.00% 100.00% 0.07%

- Pek. Pembesian (D10-150 2 layer) 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%

6 Plat Dinding Gutter, Tebal 20cm

- Pek. Bekisting Batako 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

- Pek. Bekisting Plywood 0.29% 100.00% 0.29% 0.00% 0.00% 100.00% 0.29%

- Pek. Beton K-250 Plat Dinding 0.23% 25.00% 0.06% 75.00% 0.17% 100.00% 0.23%

- Pek. Pembesian (D10-150 2 layer) 0.19% 100.00% 0.19% 0.00% 0.00% 100.00% 0.19%

7 Waterproofing

- Waterproofing Lantai ex. Sika + screed 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Waterproofing Dinding ex. Sika + screed 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

J POOL DECK 0.79% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

(14)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

- Pek. Galian Tanah 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Tie Beam (15x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Tie Beam 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Plat Lantai, Tebal 10cm

- Urugan Tanah Peninggian Lantai 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Lantai kerja 50mm 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M5 Single Layer 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Stair

- Pek. Pasangan Batako 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

K PUMP ROOM 0.95% 1.21% 0.01% 0.00% 0.00% 1.21% 0.01%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.02% 60.00% 0.01% 0.00% 0.00% 60.00% 0.01%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan Tanah Kembali 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Buangan Tanah Sisa Galian 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Tie Beam (20x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Tie Beam (4D13, Sengkang

Ø8-150) 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Tie Beam 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Plat Lantai Pump Room, Tebal 20cm

- Pek. Galian Tanah 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah plat 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(15)

- Pek. Lantai kerja 50mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti Termite 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Dinding Pump Room, Tebal 15cm

- Pek. Bekisting Batako 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Dinding 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Plat Tutup Pump Room, Tebal 20cm

- Pek. Bekisting Plywood Plat Lantai 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Waterproofing

- Waterproofing Lantai ex. Sika + screed 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Waterproofing Dinding ex. Sika + screed 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

L BALANCING TANK CAP. 5 m3 0.55% 1.43% 0.01% 0.00% 0.00% 1.43% 0.01%

1 Pekerjaan Pondasi Batu Kali (30x60 cm)

- Pek. Galian Tanah 0.01% 60.00% 0.01% 0.00% 0.00% 60.00% 0.01%

- Pek. Urugan pasir bawah pondasi 50 mm 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pondasi Batu Kali 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan Tanah Kembali 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Buangan Tanah Sisa Galian 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anti termite 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Tie Beam (20x30 cm)

- Pek. Bekisting Plywood Tie Beam 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Tie Beam 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pembesian Tie Beam (4D13, Sengkang Ø8-

150) 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Plat Lantai Balancing Tank, Tebal 20cm

- Pek. Galian Tanah 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Urugan pasir bawah pondasi 50 mm 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Lantai kerja 50mm 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(16)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

- Anti Termite 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood Plat Lantai 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Plat Dinding Balancing Tank, Tebal 15cm

- Pek. Bekisting Batako 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Bekisting Plywood 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Dinding 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Plat Tutup Balancing Tank, Tebal 15cm

- Pek. Bekisting Plywood Plat Lantai 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Beton K-250 Plat Lantai 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wiremesh M8 Double Layer 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6 Waterproofing

- Waterproofing Lantai ex. Sika + screed 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Waterproofing Dinding ex. Sika + screed 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(17)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

IV PEKERJAAN ARSITEKTUR TAHAP I 20.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

A MAIN BUILDING 11.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pasangan Bata Ringan T = 100 mm dengan

perekat mortar 0.97% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Dinding Dan Lantai Waterproofing Dasar Semen

ex. Sika 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Plesteran Dinding 0.81% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Semen Polish fin. Beige 2.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pasangan Keramik 60x60 Putih ex. Dura Floor 0.97% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Anyaman Bambu (Bedek) 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Ornamen Kayu Gelam 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 10x10 (Bar area) 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Concrete Rough Finish fin. Beige 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wayang Stone 1.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wooden Deck ex. Kayu Bengkirai 1.37% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pasangan Keramik 60x60 Putih ex. Dura Floor 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Langit - Langit

- Plafond Gypsum 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Bubungan Alang - Alang 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Pekerjaan Pintu Dan Jendela

- Pintu D1 (1200x2200 mm), Kusen Kayu

Bengkirai & Daun Pintu Multiplex 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pintu D2 (800x2200 mm), Kusen Kayu

Bengkirai & Daun Pintu Multiplex 1.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Jendela J1 (1800x1200 mm) Kayu Bengkirai 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Jendela J2 (3000x1200 mm) Kayu Bengkirai 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Kaca Mati 8 mm Area Chef Office 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B AREA PARKIR 1.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Lantai

- Pek. Pasangan Paving 200x200x80 mm 1.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(18)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

C PAGAR PEMBATAS 5.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pasangan Batako Pagar Tebal 15cm 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Kolom Praktis 15x15 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Ring Praktis 15x15 0.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Plesteran 0.73% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek Cat exterior ex. Dulux Weathershield 0.71% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Paint Texture incld. Plesteran (Area

Entrance) 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Cement Comprout incld. Plesteran (Service

Area) 0.43% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Dinding Kayu Gelam 0.97% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Sloof Dinding Kayu Gelam

- Pek. Plesteran 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Acian 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

D POS SATPAM 0.64% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pasangan Bata Ringan T = 100 mm dengan

perekat mortar 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Ring Praktis 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Paint Texture fin. Beige incld. Plesteran 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Concrete Rough Finish fin. Beige 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Langit - Langit

- Plafond Gypsum 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Pekerjaan Pintu Dan Jendela

- Pintu D2 (800x2200 mm), Kusen Kayu

Bengkirai & Daun Pintu Multiplex 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Jendela J3 Fix Glass 8 mm (800x1200 mm) 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Jendela J4 Fix Glass 8mm (800x1200 mm) 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

E PEKERJAAN LAIN-LAIN 1.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Area Entrance

- Wooden Deck ex. Kayu Bengkirai 0.89% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Area Service

(19)

- Concrete Rough Finish fin. Beige 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pintu P3 ex. Kayu bengkirai 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

V PEKERJAAN ARSITEKTUR TAHAP II 11.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

A OUTDOOR SEATING AREA 2.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Lantai

- Concrete Rough Finish fin. Beige 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wooden Deck ex. Kayu Bengkirai 1.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wayang Stone 0.52% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B PERGOLA 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Lantai

- Wayang Stone 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

C TOILET AREA 4.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pasangan Bata Ringan T = 100 mm dengan

perekat mortar 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Dinding Dan Lantai Waterproofing Dasar Semen

ex. Sika 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Paint Texture fin. Beige incld. Plesteran 1.65% 0.00% ` 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 10x10 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Wayang Stone 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Concrete Rough Finish fin. Beige 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wayang Stone 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Langit - Langit

- Balok Decoratif 300x225 mm 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Pekerjaan Pintu Dan Jendela

- Pintu D2 (800x2200 mm), Kusen Kayu

Bengkirai & Daun Pintu Multiplex 0.99% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Cermin 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

D SWIMMING POOL 3.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Batu Hijau Sukabumi 1.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

(20)

NO URAIAN PEKERJAAN BOBOT

LAST WEEK THIS WEEK UNTIL THIS WEEK

% WEIGHT % WEIGHT % WEIGHT

(%)

- Batu Andesit tebal 200x400x20mm 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Batu Hijau Sukabumi 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Batu Andesit tebal 200x400x50mm 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Lain-lain

- Batu Boulder 0.43% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

E POOL DECK 0.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Lantai

- Wooden Deck ex. Kayu Bengkirai 0.73% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Wayang Stone 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Concrete Rough Finish fin. Beige 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

F PUMP ROOM 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pek. Plesteran 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 30x30 ex. Asia Tile 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Pek. Plesteran 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 30x30 ex. Asia Tile 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Langit - Langit

- Pek. Plesteran 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Acian 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Manhole 100x100 cm, Hollow 40 x 40 mm + Plat

Strip 2 mm fin. Matte Black 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

G BALANCING TANK CAP. 5 m3 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

1 Finishing Dinding

- Pek. Plesteran Dinding 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 30x30 ex. Asia Tile 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Finishing Lantai

- Pek. Plesteran 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Pasangan Keramik 30x30 ex. Asia Tile 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Langit - Langit

(21)

- Pek. Plesteran 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

- Pek. Acian 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

100.00% 22.10% 1.60% 23.71%

(22)

Web. www.upadanasemesta.com

TIME SCHEDULE

PROJECT : TAROO CAFE UBUD CREATED DATED : 11 OKT 2022

OWNER : IBU KRISNAWATI WEEK : 8

LOCATION : MAS, UBUD

NO URAIAN PEKERJAAN BOBOT AGUSTUS 2022 SEPTEMBER 2022 OKTOBER 2022 NOVEMBER 2022

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(%) 22-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30

I PRELIMINARY - TAHAP AWAL 4.99% 0.53% 1.60% 2.86%

II PRELIMINARY - TAHAP 2 4.58% 2.21% 0.99% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.19%

III PEKERJAAN STRUKTUR TAHAP I

A MAIN BUILDING 27.88% 0.62% 2.00% 2.68% 3.17% 4.60% 4.37% 4.74% 4.59% 1.11% 0.00% 0.00% 0.00%

B AREA PARKIR 1.26% 0.63% 0.63%

C PAGAR PEMBATAS 4.25% 0.26% 0.80% 0.80% 1.59% 0.79%

D POS SATPAM 0.85% 0.14% 0.12% 0.59%

E PEKERJAAN LAIN - LAIN 2.81% 0.80% 1.14% 0.26% 0.62%

F OUTDOOR SEATING AREA 7.10% 0.26% 0.57% 0.14% 0.38% 0.82% 1.87% 1.53% 1.53%

G TOILET AREA 3.96% 0.42% 0.47% 0.46% 1.03% 0.47% 0.56% 0.56%

H PERGOLA 2.35% 0.62% 0.39% 0.58% 0.18% 0.29% 0.29%

I SWIMMING POOL 6.28% 1.03% 1.45% 2.36% 0.72% 0.71%

J POOL DECK 0.79% 0.03% 0.56% 0.20%

K PUMP ROOM 0.95% 0.23% 0.34% 0.24% 0.14%

L BALANCING TANK CAP. 5 m3 0.55% 0.16% 0.19% 0.12% 0.08%

IV PEKERJAAN ARSITEKTUR TAHAP I

A MAIN BUILDING 11.12% 0.48% 0.98% 1.65% 1.09% 1.04% 2.70% 2.51% 0.68%

B AREA PARKIR 1.65% 1.65%

C PAGAR PEMBATAS 5.65% 0.80% 0.80% 2.66% 1.26% 0.14%

D POS SATPAM 0.64% 0.11% 0.05% 0.23% 0.25%

E PEKERJAAN LAIN-LAIN 1.24% 1.24%

V PEKERJAAN ARSITEKTUR TAHAP II

A OUTDOOR SEATING AREA 2.25% 0.53% 0.86% 0.86%

B PERGOLA 0.34% 0.17% 0.17%

C TOILET AREA 4.06% 0.28% 0.68% 0.55% 0.57% 0.58% 0.34% 0.97% 0.09%

D SWIMMING POOL 3.02% 1.38% 1.21% 0.43%

E POOL DECK 0.88% 0.44% 0.44%

F PUMP ROOM 0.40% 0.18% 0.13% 0.09%

G BALANCING TANK CAP. 5 m3 0.17% 0.12% 0.02% 0.02%

DAILY PROGRESS 100.00% 0.53% 1.60% 2.86% 3.51% 5.28% 6.33% 9.96% 9.99% 11.37% 10.84% 12.20% 9.49% 7.64% 6.47% 1.93%

ACCUMULATIVE PROGRESS 0.00% 0.53% 2.13% 4.99% 8.50% 13.78% 20.11% 30.07% 40.05% 51.43% 62.27% 74.47% 83.96% 91.60% 98.07% 100.00%

ACTUAL 16.03% 6.00% 1.60%

ACTUAL ACCUMULATIVE 16.03% 22.10% 23.71%

DEVIASI

Referensi

Dokumen terkait

Penelitian ini bertujuan untuk mengidentifikasi lingkup pekerjaan dalam proyek konstruksi yang paling banyak dilakukan pekerjaan ulang dan identifikasi perbedaan

Dengan memperhatikan Dokumen Kualifikasi Pekerjaan Barang Jasa Pemerintah, serta sesuai Dokumen Kualifikasi perusahaan saudara, setelah dilakukan evaluasi yang berdasarkan

Dengan memperhatikan Dokumen Kualifikasi Pekerjaan Barang Jasa Pemerintah, serta sesuai Dokumen Kualifikasi perusahaan saudara, setelah dilakukan evaluasi yang berdasarkan

Pada bab ini akan memaparkan gambaran umum mengenai rework pada pekerjaan konstruksi jalan, memberikan definisi rework dari sudut pandang proyek konstruksi

Penelitian terkait penerapan metode TFIDF pada ringkasan otomatis dokumen bahasa indonesia berbasis bobot kata dilakukan dalam tujuh langkah yang dapat dilihat pada Gambar 1..

(16) Foto dokumentasi adalah dokumen rekaman gambar hasil pekerjaan proyek minimal tentang keadaan sekitar ruang manfaat jalan menggunakan peralatan eleKronik yang

| Data Laporan Akhir Proyek Laporan Akhir Proyek disusun oleh direksi pekerjaan berdasarkan Laporan Akhir direksi teknis, dilengkapi dengan informasi kegiatan yang dilakukan selama

Dokumen ini mengulas proyek peningkatan sungai di Namo dan Kulawi beserta estimat biaya dan pekerjaan yang