Copyright
IIT Kharagpur
v
List of Tables
Table 2.1 Income group classification 11
Table 2.2 Network based project planning methods 14
Table 2.3 Simulation-based construction scheduling methods 20 Table 3.1 Scope of work for various construction activities – case study I 27 Table 3.2 Questionnaire 1st part: Gross and detailed factors 30 Table 3.3 Top 20 causal factors influencing project progress 33
Table 5.1 Construction activity related data library 59
Table 5.2 Building material prices (in INR) 63
Table 6.1 Activity work-scope: Case Study 1 71
Table 6.2 Construction activity work-scope - Case-Study - II 73 Table 6.3 Construction activity work-scope - Case-Study - III 74 Table 6.4 Constraints considered for determining maximum possible teams for
activities 76
Table 6.5 Case-study I: Activity work-scope and maximum number of teams 77 Table 6.6 Case-study II: Activity work-scope and maximum number of teams 78 Table 6.7 Case-study III: Activity work-scope and maximum number of teams 78
Table 6.8 Fixed and flexible delays 79
Table 6.9 Productivitiy data – non-labour intensive activities 83 Table 6.10 Establishment charges: non-labour intensive activities 85
Table 6.11 Additional charges for high-rise towers 87
Table 7.1 Case-study I: Details of optimized construction schedules 100 Table 7.2 Case-study II: Details of optimized construction schedules 106 Table 7.3 Probable optimum construction schedules for the selection of most
suitable optimum construction schedule 109
Table 7.4 Case study III: Details of optimized construction schedules 115 Table 7.5 Probable optimum construction schedules for the selection of most
suitable optimum construction schedule 118
Copyright
IIT Kharagpur
vi
Copyright
IIT Kharagpur
vii
List of Figures
Figure 1.1 Classification of multi-storey building systems 5
Figure 1.2 Work flow sequence 6
Figure 2.1 Hierarchy in project planning 13
Figure 3.1 Site plan of Case study-I project 25
Figure 3.2 Partial view of completed Case study-I project 26 Figure 3.3 Sequence of implementing the construction work 27 Figure 3.4 Construction schedule adopted for implementing case study I 28 Figure 3.5 Two level decision tree adopted in questionnaire data analysis 32 Figure 3.6 Factors influencing the ‘duration of an activity’ 38 Figure 3.7 Activity resources – duration relationship 39
Figure 3.8 Activity productivity curve 40
Figure 3.9 Components of an activity’s cost 40
Figure 4.1 Dynamics of construction activity duration - 1 42 Figure 4.2 Dynamics of construction activity duration - 2 43 Figure 4.3 Dynamics of a construction activity – 3 44 Figure 4.4 Broad categorization of proposed optimization process 45
Figure 4.5 Optimization process - 1 46
Figure 4.6 Optimization process - 2 47
Figure 4.7 Detailed explanation of the proposed optimization process 48
Figure 5.1 Site plan – Case Study II 54
Figure 5.2 Partial view of case-study II after completion 55
Figure 5.3 Site plan – Case Study III 56
Figure 5.4 Partial view of case-study III after completion 56 Figure 5.5 Price indices for cement, rebars, tiles, bricks and diesel 60 Figure 5.6 Price indices for plywood, paints and sheet glass 61 Figure 5.7 Price indices for electrical fans, fluorescent tubes, PVC cables and
pipes
62
Figure 6.1(a) Block diagram – case study I 66
Figure 6.1(b) Segmentation logic – case study I 66
Figure 6.1(c) Block ‘A’: Construction segmentation 66
Figure 6.2(a) Block diagram – case study II 67
Figure 6.2(b) Segmentation logic – case study II 68
Figure 6.3(a) Block diagram – case study III 68
Figure 6.3(b) Segmentation logic – case study III 68
Figure 6.4 Construction activities in each segment 69 Figure 6.5 Rate of work available per day and maximum possible teams to
work
75
Figure 6.6 Productivity curve: Earthwork 81
Figure 6.7 Productivity curve: ‘Roof shuttering’ 81
Figure 6.8 Productivity curve: ‘Roof rebar’ 81
Figure 6.9 Productivity curve: ‘230 mm brickwork’ 82
Copyright
IIT Kharagpur
viii
Figure 6.10 Productivity curve: ‘112 mm brickwork’ 82 Figure 6.11 Productivity curve: ‘Internal-plastering’ 82 Figure 6.12 Productivity curve: ‘External-plastering’ 82 Figure 6.13 Establishement charges: ‘Roof shuttering’ 84
Figure 6.13 Establishement charges: ‘Roof rebar’ 84
Figure 6.15 Establishement charges: ‘Brickwork’ 85
Figure 6.16 Establishement charges: ‘Plastering’ 85
Figure 6.17 Hire charges: ‘roof shutter’ 86
Figure 6.18 Hire charges: ‘column shutter’ 86
Figure 6.19 Rate of total daily people required 88
Figure 6.20 Required weekly people rate 88
Figure 6.21 Daily cost rate 90
Figure 6.22 Monthly cost rate 90
Figure 6.23 Weekly requirement of rebar 92
Figure 6.24 Weekly requirement of cement 92
Figure 6.25 Weekly requirement of bricks 92
Figure 6.26 Construction activities in ground floor 94 Figure 6.27 Construction activities in first floor 94 Figure 6.28 Construction activities in second floor 94 Figure 6.29 Construction activities in third floor 94
Figure 6.30 Variable in rebar prices 98
Figure 6.31 Variable in cement prices 98
Figure 6.32 Variable in cement prices and its effect on cost of concrete 99 Figure 6.33 Variable in rebar prices of bricks and its effect on cost of 230mm
brickwork
99 Figure 7.1 Correlation between construction-duration and total-construction-
cost
101 Figure 7.2 Correlation between construction-duration and peak-monthly-
expenditure
101 Figure 7.3 Comparison of total-construction-cost and peak-monthly-
expenditure with construction-duration
102 Figure 7.4 Case Study II: Comparison of peak monthly fund requirement 102 Figure 7.5 Correlation between peak-weekly-workforce-demand and
construction-duration
103 Figure 7.6 Comparison of peak weekly workforce demand 103 Figure 7.7 Correlation between peak-weekly-cement-demand and
construction-duration
103
Figure 7.8 Comparison of peak weekly cement demand 103
Figure 7.9 Correlation between peak-weekly-rebar-demand and construction- duration
104 Figure 7.10 Correlation between peak-weekly-rebar-demand 104 Figure 7.11 Correlation between peak-weekly-brick-demand and construction-
duration
104
Figure 7.12 Comparison of peak weekly brick demand 104
Figure 7.13 Case study II: Correlation between construction-duration and total construction cost
107 Figure 7.14 Case study II: Correlation between peak – monthly expenditure and
construction-duration
107
Copyright
IIT Kharagpur
List of Figures
ix Figure 7.15 Case study II: Correlation between construction-duration and
realized rate-of-return
108 Figure 7.16 Correlation between peak-monthly expenditure and construction-
duration
108 Figure 7.17 Case study II: Comparison of peak monthly fund requirement 110 Figure 7.18 Case study 2: Correlation between peak weekly workforce and
construction duration
110 Figure 7.19 Comparison of peak weekly workforce demand 110 Figure 7.20 Correlation between peak-weekly-cement-demand and
construction-duration
111 Figure 7.21 Comparison of peak weekly workforce demand 111 Figure 7.22 Correlation between peak-weekly-rebar-demand and construction-
duration
111 Figure 7.23 Comparison of peak weekly workforce demand 111 Figure 7.24 Correlation between peak-weekly-workforce-demand and
construction-duration
112 Figure 7.25 Comparison of peak weekly workforce demand 112
Figure 7.26 Comparison of shuttering manpower 112
Figure 7.27 Comparison of rebar manpower 113
Figure 7.28 Comparison of masonry manpower 113
Figure 7.29 Comparison of plastering manpower 114
Figure 7.30 Correlation between Construction-duration and Total-construction- cost
116 Figure 7.31 Correlation between Construction-duration and peak-monthly-
expenditure
116 Figure 7.32 Correlation between construction duration and realized rate-of-
return
117
Figure 7.33 Comparison of peak monthly expenditure 117
Figure 7.34 Case Study-III: Correlation between peak-monthly-expenditure and construction-duration
118 Figure 7.35 Correlation between peak-weekly-workforce-demand and
construction-duration
119 Figure 7.36 Comparison of peak weekly workforce demand 119 Figure 7.37 Correlation between peak-weekly-workforce-demand and
construction-duration
119 Figure 7.38 Comparison of peak weekly workforce demand 119 Figure 7.39 Correlation between peak-weekly-workforce-demand and
construction-duration
120 Figure 7.40 Comparison of peak weekly workforce demand 120 Figure 7.41 Correlation between peak-weekly-workforce-demand and
construction-duration
120 Figure 7.42 Comparison of peak weekly workforce demand 120 Figure
7.43(a) and (b)
Case-study I: Comparison of Total construction duration and Total construction cost corresponding to CDminandCDactual
121
Copyright
IIT Kharagpur
x
Figure 7.44 (a) and (b)
Case-study II: Comparison of Total construction duration and Total construction cost corresponding to CDminandCDactual
122
Figure 7.45 (a) and (b)
Case-study III: Comparison of Total construction duration and Total
construction cost corresponding to CDminandCDactual
122