Variance Analysis

• When the actual costs are compared with the standard costs some deviations normally occur.

• These deviation of actual from the standard is known as variance

• Variance analysis involves the measurement of the deviation of actual

performance form the intended performances.

(3)

Variances

Favourable

Also known as positive or credit variance

When the actual cost incurred is less than the standard cost

Unfavourable

Also known as negative or debit variance.

When the actual cost incurred is more than the standard cost

(4)

Variances

Controllable

Deviation caused by such factors which could be influenced by the executive action

E.g. excess usage of materials, excess time taken by a worker

Uncontrollable

When variance is due to the factors beyond the control of the concerned person or department E.g. wage rate increased on account of strike, government restrictions, change in market price

(5)

Variances can be found out with respect to all the elements of cost, i.e.,

direct material, direct labour and overheads

(6)

Material Variances

(7)

Material Cost Variance (MCV)

• It is the difference between the standard cost of direct materials specified for the output achieved and the actual cost of direct materials used.

• This difference in material cost maybe partly due to difference in usage of raw material and partly due to difference in prices.

= Standard cost for actual output- Actual Cost

= (Standard Quantity for actual output * Standard Price) - (Actual Quantity * Actual Price)

= (SQ * SP) - (AQ * AP)

(8)

Material Price Variance (MPV)

• It is that portion of the Materials cost variance which is due to the difference between the standard price specified and the actual price paid for the direct materials used

• The reasons for price variance can be fluctuations in market prices, increase or

decrease in prices on account of agreement between various suppliers or on account of government interference, buying efficiency or inefficiency, high or low cost of

transportation and carriage of goods etc.

=Actual Quantity* (Standard Price-Actual Price)

= AQ* (SP-AP)

(9)

Material Usage (Quantity) Variance (MUV)

• It is that portion of the materials cost variance which is the difference between the

standard quantity specified for the production achieved, whether completed or not, and the actual quantity used, both valued at standard prices

• The reasons for price variance can be inefficiency, lack of skills or training and faulty workmanship, incorrect processing of materials whereby wastages may occur, pilferage, use of defective or substandard material, use of substitute material etc.

= Standard Price* (Standard quantity for actual output-Actual quantity)

= SP (SQ-AQ)

(10)

The algebraic sum of material price variance and material usage variance should be equal to material cost variance

MCV= MPV+MUV

(11)

Material Mix Variance (MMV)

• It arises when two or more materials are used in the manufacture of a product

• The difference between the standard composition and the actual composition of

material mix is the material mix variance. It represents the variation in cost arising as a result of change in in the ratio in which the different materials are used compared to the standard fixed for the purpose.

= Standard Price * (Revised Standard Quantity – Actual quantity)

= SP * (RSQ- AQ)

RSQ = Total weight of actual mix

--- *Standard Quantity Total weight of standard mix

(12)

Material Sub-usage Variance (MRUV)

• This is a sub-variance of the material usage variance and represents that portion of the material usage variance which is attributed to reasons other than those which give rise to material mix variance

= Standard price*(Standard Quantity- Revised standard quantity)

= SP*(SQ-RSQ)

(13)

Material Yield variance (MYV)

• It is that portion of the material usage variance which is due to the difference between the standard yield specified and the actual yield obtained.

• The variance arises due to abnormal contingencies like spoilage, chemical reaction etc.

= Standard output price *(Actual Yield-Standard Yield)

= SOP* (AY-SY)

Referensi

Dokumen terkait

For the same level of activity there is a stark difference in the variable prices of channel expense (8.26 lakhs; actual vs. flexible), newsprint costs (2.30 lakhs) and the

The mean variance optimal VWAP trading strategy is the sum of two distinct trading strategies, a minimum variance VWAP hedging strategy and a ‘directional’ price strategy independent

From the output of such an FMRR generation routine we can obtain the mean and variance of the annual compounded rate of return, adjusted for optimal holding period,

As discussed, the estimated residual variance, σ ˆ ǫ 2 , rep- resents the pooled variance estimate for the experimental variation as well as higher ordered interaction effects such

We have seen that the standard Monte Carlo method is a good numerical method to approximate the price and the Greeks. Furthermore, there are a lot of general variance

It is appropriate to use standard costing applying in land cost components of real estate development activities in PT Subur Agung of ciputra because of conducted research and survey,

Data Validity No Cost Based on Total Cost 1 Quantity of building damage Rp110,718,795, 02 2 Percentage of damage to buildings IDR 110,718,795.02 Difference IDR 0 Source: Data

Hence, the relationship is specified as follows: YUNP = f NTI, DPI, GCE, CPI, µt 3.1 The econometric form is specified as follows: YUNP = α + β1NTI + β2DPI + β3GCE + β4CPI + µt 3.2