TRAINING REPORT

PROJECT MANAGEMENT IN INFRASTRUCTURE DEVELOPMENT FOR CIVIL ENGINEERS

JICA YOKOHAMA, JAPAN 22/10/2018 – 12/10/2018

NAME : SITI SAIMAH BINTI ABDUL RAHMAN DESIGNATION : SENIOR ASSISTANT DIRECTOR

DEPARTMENT OF IRRIGATION AND DRAINAGE MALAYSIA MINISTRY OF WATER, LAND AND NATURAL RESOURCES

(2)

2

This program consists of common subjects for all participants and group studies. It covers very broad management skills on planning and evaluation.

Each participant is requested to review conditions and problems in his/her organization described in his/her Job Report at the beginning. By the end of the training program, he/she shall prepare his/her Action Plan and its summary utilizing the knowledge and technology learned through this course.

1.2 OBJECTIVE

This course aims to provide the project management skills on supervision, inspection, evaluation and accountability on the project in order that the participants can create the strategy or ideas to promote their projects effectively.

1.3 ACTION PLAN

Refer Annex 1

1.4 METHODOLOGY

Refer Annex 1

(3)

3 1.5 CONCLUSION

i. Improve project management skills on supervision, inspection, evaluation and accountability on the project.

ii. Create the strategy or ideas to promote projects effectively.

iii. Propose Action Plan that can be apply and improve project management system.

2.0 ATTACHMENT (ANNEX)

i. Proposed Action Plan

(4)

ANNEX 1 :

ACTION PLAN

JICA YOKOHAMA INTERNATIONAL CENTER

(5)

ACTION PLAN

PROJECT MANAGEMENT IN INFRASTRUCTURE DEVELOPMENT FOR CIVIL ENGINEERS (22 OCTOBER 2018 – 12 DECEMBER 2018)

NAME : SITI SAIMAH BINTI ABDUL RAHMAN COUNTRY : MALAYSIA

ORGANIZATION : DEPARTMENT OF IRRIGATION AND DRAINAGE MALAYSIA DIVISION : DESIGN AND DAM DIVISION

POSITION : CIVIL ENGINEER (SENIOR ASSISTANT DIRECTOR)

JICA YOKOHAMA INTERNATIONAL CENTER

(6)

INTRODUCTION

(7)

TECHNICAL AGENCIES IN MALAYSIA

TECHNICAL AGENCIES

MINISTRY OF WORKS

PUBLIC WORKS DEPARTMENT (P.W.D) - Buildings, road & highway engineering, transportation engineering, structural &

bridge, slope engineering, road maintenance

MINISTRY OF WATER, LAND AND NATURAL RESOURCES

DEPARTMENT OF IRRIGATION

& DRAINAGE (D.I.D)

- Water resources management &

hydrology, flood mitigation management, stormwater management, river

management & coastal management

(8)
(9)

BRANCH OF DEPARTMENT OF IRRIGATION & DRAINAGE MALAYSIA AND

D.I.D CORE BUSINESS

MALAYSIA MAP

Flood Mitigation River Management Coastal

Management Water Resources

Management &

Hydrology

D.I.D CORE BUSINESS D.I.D BRANCH

(10)

ACTION PLAN

(11)

ACTION PLAN PROCESS

PROJECT MANAGEMENT IN INFRASTRUCTURE DEVELOPMENT FOR CIVIL ENGINEERS

WHY WHERE HOW WHEN

(12)

COURSE CONTENTS

COURSE CONTENTS MODULE I : PROJECT MANAGEMENT

MODULE II : CONTRACTING

SYSTEM &

QUALITY CONTROL

MODULE III : ACCOUNTABILITY MODULE IV :

SITE MANAGEMENT

(13)

• IMPROVEMENT OF SAFETY AND HEALTH CONTROL MEASURES

MODULE FOR ACTION PLAN

PROJECT MANAGEMENT IN INFRASTRUCTURE DEVELOPMENT FOR CIVIL ENGINEERS

• NIL

MODULE I :

PROJECT MANAGEMENT

• ISO 9001 : QUALITY MANAGEMENT SYSTEM IN PROJECT/CONSTRUCTION MANAGEMENT

• INTRODUCTION OF i-CONSTRUCTION CONCEPT IN MALAYSIA MODULE II :

CONTRACTING SYSTEM &

QUALITY CONTROL

PUBLIC INVOLVEMENT IN DAM UPGRADING PROJECT/FLOOD MITIGATION PROJECT PLANNING

MODULE III : ACCOUNTABILITY

MODULE IV : SITE MANAGEMENT

(14)

MODULE II : CONTRACTING SYSTEM &

QUALITY CONTROL

ISO 9001 : QUALITY MANAGEMENT SYSTEM IN PROJECT/CONSTRUCTION

MANAGEMENT

(15)

MODULE II :

ISO 9001 : QUALITY MANAGEMENT SYSTEM IN PROJECT/CONSTRUCTION MANAGEMENT

* The quality management has to provide the environment within which related tools, techniques and procedures can be deployed effectively leading to operational success for a

construction project.

* The role of quality management for a construction

company is not an isolated activity, but intertwined with all the operational and managerial processes of the construction project.

* The quality management system (QMS) in construction industry refers to quality planning, quality assurance and quality control.

QUALITY MANAGEMENT

SYSTEM (QMS)

(16)

Current situation :

ISO 9001 : Quality Management System for

construction management is based on initiative of the project office.

Process :

Quality management system process and

certification from authorized certification body for agency (D.I.D).

(17)

Current ISO 9001 certification for DID Malaysia - initiative of the project office

MODULE II :

ISO 9001 : QUALITY MANAGEMENT SYSTEM IN PROJECT/CONSTRUCTION MANAGEMENT

(18)

WHY ?

ISO 9001 : Quality Management System for construction/project management is importance as follow :

•ISO 9001 is a documented process and procedure

•ISO 9001 is good for continuity and continual improvement

•Check and balance procedure : PDCA Concept (Plan, Do, Check & Act)

WHERE ?

Integrated ISO 9001 :

Quality Management System for construction/project

management for Department of Irrigation and Drainage Malaysia (Multi-site

certification for all D.I.D’s project office)

(19)

MODULE II :

ISO 9001 : QUALITY MANAGEMENT SYSTEM IN PROJECT/CONSTRUCTION MANAGEMENT

3 months

Prepare paper proposal including budget certification for ISO 9001 : QMS for construction/project management

3 months

Forward for Approval Process and get the approval

6 months

Prepare documented procedure for ISO 9001 : QMS construction/project management

2 years

Implement the process & certification of QMS

HOW ? WHEN ?

TOTAL DURATION

= WITHIN 3 YEARS

(20)

MODULE II : CONTRACTING SYSTEM &

QUALITY CONTROL

INTRODUCTION OF

i-CONSTRUCTION CONCEPT IN

MALAYSIA

(21)

MODULE II :

INTRODUCTION OF

I-CONSTRUCTION CONCEPT IN MALAYSIA

It is a solution for lack of skill workers

in construction industry

i-construction technology is good

in ensuring good quality control

i-construction

(22)

DEMAND OF SKILL WORKERS IN CONSTRUCTION INDUSTRY IN MALAYSIA

- SOURCE : MALAYSIAN CONTRACTOR SOCIETY

(23)

MODULE II :

INTRODUCTION OF

I-CONSTRUCTION CONCEPT IN MALAYSIA

Current situation :

Lack of manpower (skill workers) - Intake foreign labor

Process :

Adopt and transfer technology for i-construction

(24)

WHY ?

i-construction reduce manpower

Easy method and reduce time

Good quality control

WHERE ?

Adapt and transfer technology for i-

construction for upgrading dam, Department of Irrigation and

Drainage, Malaysia as a pioneer project

(25)

3 months

Prepare paper proposal including budget

3 months

Forward for Approval Process and get the approval

6 months

Training staff/officer for i-construction

2 years

Implementation of i-construction as pilot project

HOW ? WHEN ?

TOTAL DURATION = WITHIN 3 YEARS (NEXT ROLLING PLAN)

MODULE II :

INTRODUCTION OF

I-CONSTRUCTION CONCEPT IN MALAYSIA

(26)

MODULE III : ACCOUNTABILITY PUBLIC INVOLVEMENT IN DAM

UPGRADING PROJECT/

FLOOD MITIGATION PROJECT

PLANNING

(27)

MODULE III :

PUBLIC INVOLVEMENT IN DAM UPGRADING PROJECT/

FLOOD MITIGATION PROJECT PLANNING

This process involvement of public from the beginning : i. Conceptual stage

ii. Planning stage

Process :

Invite citizens in decision making process

Current situation :

Public involvement part very neglected

Public engagement only for federal projects. Not all state project involved public engagement.

No specific guideline for public involvement

(28)

WHY ?

Invite citizens to participate in the conceptual stage to assure :

Transparency, objectivity, rationality and fairness in planning process

Efficient planning process with discussion on pros and cons of each issue

More rational planning process through comparison & evaluation

Achievement for better planning with incorporation of opinion of citizens

Minimum criticism by people for highhandedness of government

WHERE ?

Integrated in the planning process of dam upgrading project/flood mitigation project in DID Malaysia.

(29)

MODULE III :

PUBLIC INVOLVEMENT IN DAM UPGRADING PROJECT/

FLOOD MITIGATION PROJECT PLANNING

3 months

Prepare paper proposal including budget

3 months

Forward for Approval Process and get the approval

6 months

Prepare specific guideline for Public Involvement in planning dam upgrading project/flood mitigation project

2 years

Implement in project where large population is influenced.

HOW ? WHEN ?

TOTAL DURATION = WITHIN 3 YEARS (NEXT ROLLING PLAN)

(30)

MODULE IV : SITE MANAGEMENT IMPROVEMENT OF SAFETY AND

HEALTH CONTROL MEASURES

(31)

MODULE IV :

IMPROVEMENT OF SAFETY AND HEALTH CONTROL MEASURES

Why do we need to pay attention to “Safety & Health”

Workplace safety and health is to create a safe working

environment where workers are able to work without risking their health.

A B

X BAD PRACTICE GOOD PRACTICE

(32)

Why do we need to pay attention to “Safety & Health”

Workers :

Don’t like to get injured, feel pain or feel hardship

Employers :

Want to reduce costs of accidents and have legal and social responsibilities

Quality and productivity improvement will be realized by maintaining high level of safety

Safety level is a determinant of corporate values.

(33)

MODULE IV :

IMPROVEMENT OF SAFETY AND HEALTH CONTROL MEASURES

Current situation :

Safety and health officer is only compulsory for project more than RM20 million (USD4.8 million)

No specific clearly mention in the tender document for

project below RM20 million (USD4.8 million) for safety and health management

(34)

Sample of Bill of Quantities - Project above RM20 million (USD4.8 million)

) :

(35)

CONSTRUCTION SITE

MODULE IV :

IMPROVEMENT OF SAFETY AND HEALTH CONTROL MEASURES

(36)

WHY ?

Some of the safety and health control issue are mentioned in contract document, but

implementation is very poor.

Public have negative thinking of the construction industry

Message in the society that government project is not poor in safety and health management

Very less self satisfaction/bad feeling to implementing engineers due to bad working environment at sites

WHERE ?

In all proposed new/dam upgrading projects

implemented by Dam &

Design Division,

Department of Irrigation &

Drainage, Malaysia

(37)

4 months

Risk assessment regarding safety and health issue must comply for every project.

4 months

Strongly put in the item of tender documents for good provision of safety and health issue

4 months

Add separate provision of cost safety and health control with clearly defined requirements

1 year

Conduct awareness programs for contractors, workers and DID’s engineers/site staffs.

HOW ? WHEN ?

TOTAL DURATION

= WITHIN 2 YEARS

MODULE IV :

IMPROVEMENT OF SAFETY AND HEALTH CONTROL MEASURES

(38)

CONCLUSION

(39)

PROJECT MANAGEMENT IN INFRASTRUCTURE DEVELOPMENT FOR CIVIL ENGINEERS

Improve project management skills on supervision, inspection, evaluation and

accountability on the project.

Create the strategy or ideas to promote projects effectively.

Propose Action Plan that can be apply and improve project management system.

1

2

3

(40)

THANK YOU

ARIGATO GOZAIMUS..

Referensi

Dokumen terkait

The National Multisectoral Action Plan for the Prevention and Control of Non-communicable diseases 2016- 20120 is a result of untiring efforts of the NCD unit of the Ministry

NATIONAL MULTISECTORAL ACTION PLAN FOR THE PREVENTION AND CONTROL OF NONCOMMUNICABLE DISEASES 2016-20201. NATIONAL MULTISECTORAL ACTION PLAN FOR THE PREVENTION

The group elected a management committee then developed an action plan for waste manage- ment and recycling similar to the Kampangpet model of village volunteers collecting,

After a deadly heat wave hit the city of Ahmedabad in May 2010, the Ahmedabad Municipal Corporation (AMC) has taken the initiative to develop a comprehensive heat action plan

Penelitian ini dilakukan di Bukit Duri, Jakarta Selatan, dan objek penelitiannya adalah bagaimana pelaksanaan program Community Action Plan (CAP) di lapangan,

Plan Of Action ini kami susun sebagai instrumen untuk tahun 2016,Harapan kami semoga POA ini bisa menjadi bahan acuan bagi program pelayanan masyarakat Puskesmas Ngronggot

12 University College First-Year Experience Action Plan January 2015 Recommendation Responsible Individual Rationale Timeframe for Development and Planning

OHSAS 18001:2007 Occupational Health and Safety Assessment Series – Construction of Civil, Marine, Building and Infrastructure Project To date, MMESB has successfully built and