• Tidak ada hasil yang ditemukan

A CASE OF THE CAPITAL TOWERS (ATHENS)

N/A
N/A
Protected

Academic year: 2023

Membagikan "A CASE OF THE CAPITAL TOWERS (ATHENS)"

Copied!
6
0
0

Teks penuh

(1)

THE USE OF CONSTRUCTION SEQUENCE ANALYSIS IN THE RETROFITTING OF A MISALIGNED BEAM – A CASE OF THE

CAPITAL TOWERS (ATHENS)

CASHLEY FELTON TRINIDAD CHUA 2003 – 01403

SUBMITTED TO THE FACULTY OF THE

COLLEGE OF ENGINEERING AND AGRO-INDUSTRIAL TECHNOLOGY UNIVERSITY OF THE PHILIPPINES LOS BANOS

IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE

DEGREE OF

BACHELOR OF SCIENCE IN CIVIL ENGINEERING

APRIL 2010

(2)

ii

The report attached hereto entitled THE USE OF CONSTRUCTION SEQUENCE ANALYSIS IN THE RETROFITTING OF A MISALIGNED BEAM – A CASE OF THE CAPITAL TOWERS (ATHENS), prepared and submitted by Cashley Felton T. Chua in partial fulfillment of the requirements for the degree of Bachelor of Science in Civil Engineering is hereby accepted.

___________________________ ___________________________

ENGR. JENNYL R. ESTIL ENGR. SUNSEEHRAY Panel Member ALESSANDRA B. TIRAZONA

Panel Member

_______________________ _______________________

Date Signed Date Signed

__________________________

PROF. MARLOE B. SUNDO Adviser

______________________

Date Signed

__________________________

PROF. MARLOE B. SUNDO Chairman, CE Department

______________________

Date Signed

_________________________________

DR. ARSENIO N. RESURRECCION Dean

College of Engineering and Agro-Industrial Technology University of the Philippines Los Baños

______________________

Date Signed

(3)

vi TABLE OF CONTENTS

Title Page i

Acceptance Sheet ii

About the Author iii

Acknowledgements iv

Table of Contents vi

List of Tables and Figures viii

1. INTRODUCTION

1.1 Project Background 1

1.2 Background of the Study 2

1.3 Significance of the Study 3

1.4 Objectives of the Study 3

1.5 Scope and Limitations 4

1.6 Date and Place of Study 4

2. REVIEW OF RELATED LITERATURE

2.1 Concrete Construction 6

2.1.1 Formwork Installation 6

2.1.2 Concrete Vibration 6

2.1.3 Concrete Curing 8

2.2 Rehabilitation Approaches 8

2.2.1 Global Modification 8

2.2.2 Local Modification 9

2.3 Seismic Retrofitting Strategies 10

2.3.1 Conventional Retrofitting Methods 10

2.3.2 Innovative Retrofitting Methods 11

2.3.2.1 Stiffness Reduction 12

2.3.2.2 Ductility Increase 12

2.3.2.3 Damage Control 12

2.3.2.4 Composite Materials 13

2.3.2.5 Active and Passive Control 13

2.4 Structural Elements 15

2.4.1 Reinforced Concrete Beam 15

2.4.2 Flat Slab 16

2.4.3 Columns 18

2.4.3.1 Slenderness Ratio 19

2.4.3.2 Lateral Buckling 20

2.4.3.3 Reinforcing Bars 20

2.5 Shoring 21

2.5.1 Shoring Types 22

2.5.2 Placing of Shoring 22

2.5.3 Removal of Shoring 23

3. STUDY METHODOLOGY 24

4. OBSERVATIONS

4.1 Beam Misalignment 25

4.2 Installation of Scaffoldings 26

(4)

vii 4.3 Installation of I-Beams as Lateral Bracings 27

4.4 Demolition of Existing Beam 32

4.5 Rebar Works 35

4.6 Concrete Works 36

5. DISCUSSION AND ANALYSIS

5.1 Origin of Misalignment 38

5.1.1 Column Misalignment 38

5.1.2 Beam Misalignment 39

5.2 Preliminary Correction Methodology 39

5.3 Evaluation of Beam-Deprived System 40

5.3.1 Designation of Loadings 40

5.3.1.1 Loading Coefficient 41

5.3.1.2 Loading Combo 41

5.3.2 Design of Reinforced Concrete Sections 42 5.3.3 Tower Membrane Without Reinforced Concrete Beam 42

5.4 Analysis of System with New RC Beam 44

5.5 Summary of Analysis 45

5.6 Selection of Retrofitting Methodology 46

5.7 Retrofitting Approaches 47

5.7.1 Conventional Retrofitting Approaches 47

5.7.2 Innovative Retrofitting Methods 48

5.8 Final Correction Methodology 49

5.9 Factors Considered in Concrete Construction 49

5.9.1 Offsetting 49

5.9.2 Formworks 50

5.9.3 Quantity 50

5.9.4 Transport 50

5.9.5 Vibration 50

5.9.6 Finishing 51

5.9.7 Curing 51

6. CONCLUSION 52

7. RECOMMENDATIONS 53

REFERENCES 54

APPENDICES

Appendix A. Floor Plan (8th to 36th) 56

Appendix B. Rebar Cutting List of Beams and Girders (9th to 15th Floor) 57

Appendix C. Off-Setting (Tower 1) 58

Appendix D. Approved Plan (Installation of Additional Rebars) 59 Appendix E. Approved Plan (Installation of I-Beams as Lateral Bracings) 60 Appendix F. Design Strength for Structural Members (Tower 1) 61 Appendix G. Concrete Testing Results (June 8, 2009) 62 Appendix H. Column Schedule (9th Floor Level to 15th Floor Underside) 63

Appendix I. Sample Computations 64

Appendix J. Sample Computations 65

(5)

viii LIST OF TABLES and FIGURES

Table/ Figure No. Title Page

Figure 1-1 The Capital Towers 2

Figure 1-2 The Capital Towers Location Map 5

Figure 2-1 Global Modification of the Structural System 9 Figure 2-2 Local Modification of the Structural System 9 Figure 2-3 Conventional Strengthening Methods Used for Seismic

Retrofitting 11

Figure 2-4 Applications of Conventional Strengthening Methods 11

Figure 2-5 Damage Controlled Structure 13

Figure 2-6 Energy Dissipation Devices 15

Figure 2-7 Section Through a Flat Slab 17

Figure 2-8 Section Through a Flat Slab with Drops 17 Figure 2-9 Section Through a Flat Slab with Enlarged Column Heads 17

Figure 2-10 Column with Lateral Ties 19

Figure 2-11 Column with Spirals 19

Figure 2-12 Patented Shores 22

Figure 4-1 Correction with Existing Structure Present 25 Figure 4-2 Shoring Installed (Unit I – 8th Floor) 26 Figure 4-3 Shoring Installed (Unit J – 8th Floor) 26 Figure 4-4 Drilled Holes for Steel Plate Installation (On Beams) 27 Figure 4-5 Manual Drilling of Holes for Steel Plate Installation 27 Figure 4-6 Drilled Holes for Steel Plate Installation (on Columns) 28

Figure 4-7 Torching of Steel Plates 28

Figure 4-8 Acetylene Tanks 29

Figure 4-9 I-Beams Staged On Site 29

Figure 4-10 I-Beams Used as Lateral Bracings 30

Figure 4-11 Welding of I-Beams onto Steel Plates 30

Figure 4-12 Welded I-Beam on Unit I (9th Floor) 31 Figure 4-13 Welded I-Beam on Unit J (9th Floor) 31

Figure 4-14 Manual Demolition of Slab Edges 32

Figure 4-15 Slab Edges Chipped Off (Unit I) 32

Figure 4-16 Misaligned Beam Surface Chipped Off (w/o Bracing) 33 Figure 4-17 Demolition of Misaligned Beam w/ Lateral Bracing 34 Figure 4-18 Demolition of Misaligned Beam (Units I & J) 34

Figure 4-19 Demolished RC Beam (Unit I) 35

Figure 4-20 Demolished RC Beam (Unit J) 35

Figure 5-1 Column Misalignment 38

Figure 5-2 Beam Misalignment 39

Figure 5-3 Load Definition 41

Figure 5-4 Loading Coefficient Modification 41

Figure 5-5 Loading Combination Selection 42

Figure 5-6 3-D View of TCT-Athens Membrane with Elevation View 43 Figure 5-7 Elevation View of Columns C2 and C3 (without beam) Showing

the Required Design Reinforcement Area 44

(6)

ix Figure 5-8 3-D View of TCT-Athens Membrane with pinned Beam

Replacement 44

Figure 5-9 Elevation View of Columns C2 and C3 (with beam) Showing

the Required Design Reinforcement Area 45

Figure 5-10 Original Rebar Cutting List (Beam G-4) 46 Figure 5-11 Cutting List with Additional Rebars (Beam G-4) 46

Figure 5-12 Post-Cast Shear Wall 48

Figure 5-13 External Steel Bracing 48

Table 4.1 Values for Strength of Concrete for Percent Age of 28 Days

Strength 37

Referensi

Dokumen terkait

XIV LIST OF FIGURES Page Figure 1 Lateral view of adult penaeid prawn 4 Figure 2 Distribution view of banana shrimp and catch in 1990–2018 5 Figure 3 The ovarian development at

\caption{...}% caption below the object \end{figure} Figure 2: Without any Options only the fbox package option Code for figure 2: 1 \hvFloat{figure}{\includegraphics{rose}}{Without