• Tidak ada hasil yang ditemukan

3.4 Planning

3.4.3 Critical Path Method (CPM)

 

Both  the  Critical  Path  Method  (CPM)  and  Program  Evaluation  and  Review  

Technique  (PERT)  are  developed  from  simple  network  diagrams.    The  network   consists  of  lines  which  represent  activities  and  nodes  (round  circles)  that  

represent  the  beginning  or  end  of  an  activity,  sort  of  like  the  Paris  Métro  system   maps.  

 

A"Simple"Network"Diagram"

Figure  10  Network  Diagram    

Simple  network  diagrams  are  the  basis  for  CPM  and  PERT.  While  both  systems   were  developed  separately  in  the  1950s  in  the  United  States  -­‐  PERT,  by  the  U.S.  

Navy  and  consultants  Booz  Allen  to  manage  the  Polaris  missile  project  and  CPM   by  employees  of  DuPont  and  Remington  Rand  (Wikipedia,  n.d.)  -­‐  there  is  enough   similarity  to  consider  them  of  the  same  family  of  critical  path  users.  (Fontana,   1990)  

 

Critical  Path  Analysis  refers  to  analyzing  the  network  to  find  the  shortest  time   for  project  realization.  (Fontana,  1990)  The  critical  path  is  the  sequence  of   stages  determining  the  minimum  time  needed  to  complete  a  project  by  plotting   out  the  longest  timeline.    If  the  line  is  too  long,  then  each  activity  is  revisited  to   see  how  and  where  time  requirements  can  be  improved.  Using  CPM,  DuPont  was   able  to  reduce  from  four  years  to  two-­‐and-­‐a-­‐half  years  the  time  required  to  close   a  chemical  plant  for  maintenance  and  reopen  for  production.      

 

Nowadays,  CPM  is  used  for  repetitive  project  planning,  when  reliable  estimates   of  time  and/or  the  deadline  are  known.    PERT  is  preferred  if  no  reliable  time   estimates  are  available,  but  a  cost  analysis  is  essential  to  reduce  project  time.    

 

Both  CPM  and  PERT  have  two  phases:      

 

1)  qualitative,  involving  an  inventory  of  tasks  required  to  attain  the  goal,   establishing  dependency  of  tasks,  and  designing  the  network;  and    

 

2)  quantitative,  establishing  the  time  required  to  finish  each  task  by  specifying   both  the  earliest  and  the  latest  possible  termination  dates.    

 

It  is  usual  for  students  to  want  to  rush  to  the  second  phase,  to  spontaneously   draw  the  arrows  and  nodes  of  a  network.    But  this  will  cause  problems  and   errors  in  planning,  so  it  is  important  to  spend  sufficient  time  brainstorming  the   inventory  before  attempting  to  apply  chronology.

   

At  ESH,  we  use  a  Creative  Problem  Solving  -­‐derived  method  of  "breathing"  

(Wolfe,  2007)  to  brainstorm  in  order  to  sufficiently  develop  the  qualitative  task   inventory  in  phase  one.      

 

Figure  11  "Breathing"  creativity  (Wolfe,  2007);  drawing  by  C.  Konold    

 

Thoroughness  rather  than  chronology  takes  precedence  in  this  step.    Then  we   look  at  dependency  of  tasks  which  will  thus  establish  the  order  in  which  tasks   may  be  undertaken  but  allowing  for  parallel  activity.  

 

The  easiest  way  to  do  this  before  putting  anything  to  paper  is  to  jot  the  tasks'  key   words  on  large-­‐sized  Post-­‐Its  ("papillons")  which  can  then  be  easily  plotted  on   the  classroom  wall.    This  juggling  process  is  important  to  elicit  discussion  on  the   team  of  how  and  when  things  will  be  done.  More  actions  may  be  discovered  and   added  to  the  inventory.    (For  complex  projects,  a  ball  of  twine  may  be  used  to   express  the  inter-­‐relatedness  of  each  task.)    This  is  the  planning  rough  sketch.    

 

When  your  rough  draft  has  been  sufficiently  developed,  you  can  complete  a   project  task  inventory  as  follows,  where  tasks  are  each  given  a  letter  of  the   alphabet  and  dependency  is  entered  into  the  right-­‐hand  column.  

 

 

                                                       

Sample'CPM'or'PERT'Task'Inventory'on'Home'Moving

So,$you$decide$to$move…

Code Task'/'Activity Dependency

A Get$bank$loan$to$pay$deposit,$movers 0

B Look$for$a$new$apartment 0

C Sign$new$lease A

D Get$estimates$from$movers B,$A

E Give$notice$to$landlord$that$you$are$moving C

F Pack$belongings$into$boxes D

G Cancel$or$transfer$contracts$(EDF,$phone…) E

H Move F

I Pay$movers G,H

J Settle$into$new$premises H,$I

N.B. Do not attemtp to establish chronology while taking this inventory.

Only the resultant task dependency will determine chronology. When the Task list is complete, take a look at each task to determine what it is dependent upon. It may be dependent on several other tasks. Mark those letters in the dependency column. Do not attempt to draft the network until you$have$established$the$dependencies.

  Figure  12  Sample  Task  Inventory  with  dependencies)  

Using  the  task  inventory,  plot  out  the  tasks  on  paper  from  left  to  right.      Arrows   ( )  represent  tasks  and  circles  (    )  or  boxes  (  !  )  denote  "nodes"  (beginning   and  end  of  tasks).    Each  arrow  is  labeled  with  its  activity  code  (letter)  written   above  the  line.      Time  Estimates  (TE)  for  completion  of  each  task  are  written   below  the  task  arrow.    A  relationship  between  nodes  is  indicated  by  a  "dummy"  

line  or  dotted  arrow  (-­‐-­‐-­‐ )  to  show  that  a  particular  action  must  be  finished   before  the  one  that  the  dummy  line  points  to  can  be  completed.      

 

             

!!

Get!es&mates!

from!movers! Moving'House'Network'

!!!

!!!!

Get!ban k!loan!

Pack!! Find!ne

w!!

apartment! !!!

!!!

Sign!new!

lease!

!!

Give!

no&ce!

!!!

4! !!

Move!

1!

Key:!

Arrow!=!ac&vity!

Circle!or!“node”!=!event!(end!or!beginning)!

TE!or!Time!Es&mate!–!in!days!(red)!

N.B.!There!is!no!propor&onality!intended!in!the!length!of!lines!

10!

15!

2! 1!

7! !5!

2!

Change!

u&lity!

contracts!

Pay!!!

SeSle!in! !!!

1!

  Figure  13  Sample  CPM  "Moving  House"