KOMITMEN DAN KONTINJENSI SIGNIFIKAN AND CONTINGENCIES

Komitmen belanja modal Capital expenditures commitments

Pembangunan pabrik-pabrik kelapa sawit Construction of palm oil mills

Pada bulan Februari 2014, KGP mengadakan perjanjian konstruksi dengan PT Sumber Andalan Mandiri, untuk membangun pabrik kelapa sawit dengan kapasitas olah sebesar 40 metrik ton TBS per jam (yang dapat ditingkatkan menjadi 80 metrik ton TBS per jam), di propinsi Kalimantan Barat, dengan nilai kontrak sebesar Rp126.620 dan US$961.430.

In February 2014, KGP entered into a construction agreement with PT Sumber Andalan Mandiri, whereby the latter is committed to construct palm oil mill with a processing capacity of 40 metric tonnes of FFB per hour (which can be increased into 80 metric tonnes of FFB per hour), at a location in the province of West Kalimantan, for a contract value of Rp126,620 and US$961,430.

Pembelian Mesin Pabrik Purchases of Factory Machineries

Pada tahun 2014, Divisi Minyak dan Lemak Nabati SIMP mengadakan perjanjian dengan Lipico Technologies Pte. Ltd., Singapura, untuk penyediaan mesin dan peralatan pabrik penyulingan minyak kelapa sawit (MKS) di Surabaya, dengan kapasitas olah masing-masing sebesar 1.000 metrik ton per hari untuk pabrik penyulingan (physical refining plant) dan pabrik fraksinasi (dry fractination plant), dengan total nilai kontrak sebesar SGD7.128.000.

In 2014, the SIMP’s Edible Oil and Fats Division engaged Lipico Technologies Pte. Ltd., Singapore, for the supply of machinery and equipment of a crude palm oil (CPO) refinery plant located at Surabaya, with each processing capacity of 1,000 metric tonnes per day for the physical refining plant and the dry fractination plant, respectively, with total contract value of approximately SGD7,128,000.

Tagihan Penyelesaian Pabrik Penyulingan Gula Claim for Settlement of a Sugar Refinery Plant Pada tahun 2008, LPI mengadakan perjanjian

pemasokan (“Supply Agreement”) dengan China CAMC Engineering Co. Ltd., yang akan menyediakan mesin dan peralatan pabrik penyulingan gula dengan kapasitas olah sebesar 8.000 metrik ton tebu per hari di propinsi Sumatera

Selatan, dengan nilai kontrak sebesar

US$84.328.040. Di samping itu, LPI juga mengadakan perjanjian konstruksi dengan CAMCE- MPS JO (“CAMCE”) untuk membangun pabrik penyulingan gula tersebut dengan nilai kontrak sebesar US$33.741.960.

In 2008, LPI entered into a Supply Agreement with China CAMC Engineering Co. Ltd., whereby the latter is to supply machinery and equipment for a sugar refinery plant with daily processing capacity of 8,000 metric tonnes of sugar cane located at the province of South Sumatera for a contract value of US$84,328,040. LPI also entered into a Construction Agreement with CAMCE-MPS JO (“CAMCE”) whereby the latter is committed to construct and erect the aforesaid sugar refinery plant with a contract value of US$33,741,960.

CAMCE tidak dapat memenuhi kewajibannya sesuai kontrak di atas, sehingga LPI harus melakukan pekerjaan tambahan agar pabrik tersebut siap digunakan. Pada bulan Desember 2016, LPI dan CAMCE menyepakati saling hapus antara piutang klaim atas pekerjaan tambahan tersebut dengan utang retensi yang belum dibayarkan oleh LPI, sehingga selisih sebesar Rp107.308 dicatat sebagai

CAMCE failed to meet its obligations under the said contract, forcing LPI to perform remedial works to make the plant ready for use. In December 2016, LPI and CAMCE agreed to offset the claim receivables arising from the said remedial works and the related retention payables not yet paid by LPI, and thus the difference amounting to Rp107,308 was recorded as part of “Other

(lanjutan)

Komitmen belanja modal (lanjutan) Capital expenditures commitments (continued)

Jumlah Komitmen dan Realisasi Total Commitments and Realized Amounts

Pada 31 Desember 2016, Kelompok Usaha memiliki berbagai kontrak untuk memperoleh aset tetap dan pengembangan tanaman perkebunan senilai US$78.651.837, Rp671.156, JPY243.739.590,

SGD8.700, EUR27.492.115, CHF47.344

(31 Desember 2015: US$105.142.094,

Rp3.823.678, JPY471.532.800, SGD140.247,

AUD320.000, GBP40.846, EUR25.987.227,

THB130.576.100, MYR494.413 dan 31 Desember

2014: Rp3.849.692, US$99.261.416,

EUR28.225.683, SGD22.500, THB130.132.300, GBP32.146, MYR494.413, CHF267.500 dan JPY448.042.800).

As of December 31, 2016, the Group has various contracts to acquire fixed assets and development of plantations totaling US$78,651,837, Rp671,156, JPY243,739,590, SGD8,700, EUR27,492,115, CHF47,344 (December 31, 2015: US$105,142,094, Rp3,823,678, JPY471,532,800, SGD140,247,

AUD320,000, GBP40,846, EUR25,987,227,

THB130,576,100, MYR494,413 and December 31,

2014: Rp3,849,692, US$99,261,416,

EUR28,225,683, SGD22,500, THB130,132,300, GBP32,146, MYR494,413, CHF267,500 and JPY448,042,800).

Pada tanggal 31 Desember 2016, jumlah yang direalisasi dari nilai kontrak di atas adalah sebesar

US$30.756.735, Rp251.554, JPY51.334.662, SGD8.700, CHF23.849 EUR18.332.519, (31 Desember 2015: US$33.707.970, Rp2.090.750, JPY44.589.481, SGD14.239, GBP8.700, EUR14.211.556, THB117.698.125, MYR161.346 dan 31 Desember 2014: Rp2.037.572,

US$26.410.092, EUR8.266.516, MYR161.346, CHF80.250 dan JPY45.092.981).

As of December 31, 2016, the amount realized from the above-mentioned contract values was US$30,756,735, Rp251,554, JPY51,334,662,

SGD8,700, CHF23,849 EUR18,332,519,

(December 31, 2015: US$33,707,970,

Rp2,090,750, JPY44,589,481, SGD14,239, GBP8,700, EUR14,211,556, THB117,698,125,

MYR161,346 and December 31, 2014:

Rp2,037,572, US$26,410,092, EUR8,266,516, MYR161,346, CHF80,250 and JPY45,092,981).

Komitmen penjualan Sales commitment

Pada tanggal 31 Desember 2016, SIMP memiliki komitmen penjualan untuk menyerahkan karet, minyak kelapa sawit, inti kelapa sawit, teh dan kakao sebanyak 38.462 ton (31 Desember 2015: 47.500 ton dan 31 Desember 2014: 26.500 ton) dan benih bibit kelapa sawit sebanyak 122.225 butir (31 Desember 2015: 1.075.153 butir dan 31 Desember 2014: 1.648.090 butir) kepada pelanggan pihak ketiga dalam dan luar negeri.

As of December 31, 2016, SIMP has sales commitments to deliver rubber, CPO, palm kernel, tea and cacao of approximately 38,462 tonnes (December 31, 2015: 47,500 tonnes and December 31, 2014: 26,500 tonnes) and palm oil seed of 122,225 pieces (December 31, 2015: 1,075,153 pieces and December 31, 2014: 1,648,090 pieces) to third party local and overseas customers.

Seluruh komitmen penjualan di atas akan terealisasi dalam satu bulan setelah tiap-tiap tanggal pelaporan.

All of the above sales commitments will be realized in one month after each reporting date.

Uang Muka Pembelian Tanah Advances for Land Acquisitions

Uang muka pembelian tanah merupakan biaya-

biaya sehubungan dengan akuisisi lahan

perkebunan sebagai bagian dari rencana LSIP, Entitas Anak, untuk mengamankan pasokan tandan buah segar. LSIP telah menunjuk PT Dwi Reksa Usaha Perkasa (“DRUP”), dahulu entitas anak yang telah dijual pada bulan Oktober 2006, untuk membantu dan mengelola proses akuisisi lahan

Advances for land acquisitions represent costs related to the acquisitions of plantation areas as part of LSIP, Subsidiary, plan to secure supplies of fresh fruit bunches. LSIP appointed PT Dwi Reksa Usaha Perkasa (“DRUP”), a former subsidiary disposed in October 2006, to facilitate and manage the land acquisition process and the handover of the land to LSIP. The advances will be settled when the land is

KOMITMEN DAN KONTINJENSI SIGNIFIKAN