BID CONFERENCE – MINUTES  OF MEETING  

RFQ/UNDP/UNODC/016/2013 – CONSTRUCTION OF CHECK POINT POSTS IN  PAPUA 

 

Date & time: 

Tuesday, 18 June 2013 at 10:00 AM, UNDP Office Jakarta (Kendari Room)   

 

Closing Date:  

June 26th, 2013, Received by UNDP by 1300 Hours (Jakarta local time)   

Attendants: 

• Ms. Kristin Moko (Presenter) ‐ UNDP 

• Ms. Bunga Anggia Prameswari ‐ UNDP 

• Mr. Marius Gunawan (Presenter) ‐ UNODC 

• Ms. Iis Wiarsih – UNODC 

• Mr. Helmi Almy – CV Bontar Hannar Jaya 

• Mr. Robby H. – CV Frankar 

• Mr. Harry Ch. – CV Enam Mustika 

• Mr. Rahmat – PT Bhina Papua Karya 

• Mr. Mas MS – CV Florensia Kurnia 

• Mr. Markus S – CV Kiboo – Ho 

• Mr. Boyke (Presenter) ‐ UNODC 

• Ms. Ubat ‐ UNODC   

 

   

 

 

(2)

TO ALL INTERESTED BIDDERS 

 

NO  SUBJECT 

Info  Konferensi untuk penawar dibuka dengan agenda berikut: 

1. Penjelasan singkat tentang konferensi  2. Penjelasan mengenai dokumen tender 

3. Penjelasan mengenai  Lingkup kerja dan Bill of Quantity 

4. Penambahan tempat untuk menyampaikan penawaran tender. Selain melalui  email  dan  menyerahkan  langsung  ke  kantor  UNDP  Jakarta,  penawar  bisa  menyerahkan ke kantor perwakilan UNODC di Papua ‐ Gedung BKPM Lantai 2, Jl. 

Samratulangi No. 32 Jayapura, Phone 0296 7523702 sebelum tanggal penutupan  yaitu jam 1 siang waktu Jakarta tanggal 26 Juni 2013. 

Klarifikasi  ini  dimaksudkan  untuk  memberikan  penjelasan  kepada  penawar. 

Apabila  ada  pertanyaan,  bisa  dikirimkan  melalui  e‐mail  paling  lambat  tiga  hari   sebelum tanggal penutupan tender. 

Q&A session is incorporated into the below minutes. 

Apakah kami menerima uang muka saat memulai pekerjaan? 

Tidak. 

 

Apakah  untuk  pembangunan  ini  sudah  dibebaskan  dari  tanah  adat  dan  urusan  pemerintahan?  Jika  iya  dan  saat  kami  menang  tender,  apakah  kami  bisa  memegang surat dari pemerintah tersebut? 

  Sudah  diurus  dengan  Pemerintah  local  Jayapura  dan  mendapat  dukungan  juga  dari Dinas Kehutanan Jayapura. 

Setelah  menang  tender  dan  telah  memegang  surat  izin  dari  pemerintah,  tapi  misalnya  kemudian  ada  permintaan  biaya  tambahan  dalam  hal  masalah  tanah,  apakah kami juga harus bayar? Dan bila itu terjadi, apakah ada kelonggaran untuk  perpanjangan waktu pembangunan. 

 

Sudah  punya  perjanjian  Dinas  Kehutanan  dan  pemerintah  Papua  dan  tidak  dibebankan kepada vendor. Dan jika nantinya ada halangan masalah tanah yang  disebabkan  dari  internal  UNDP,  akan  dipertimbangkan  untuk  perpanjangan  waktu pembangunan. Tapi apabila masalah datang dari vendor pemenang,maka   tetap sesuai dengan perjanjian yang sudah disepakati. 

 

Jika ingin memberikan penawaran, apakah kami juga memberikan bukti penjamin  dari bank? 

Seperti  yang  tertulis  di  tender  dokumen,  persyaratan  yang  harus  diserahkan  (berdasarkan annex 2) adalah: 

(3)

1. Surat/ sertifikat pendirian perusahaan  2. Company Profile 

3. Data  dari  3  proyek/  pembeli  terbesar  dalam  3  tahun  terakhir  (nama,  jumlah kontrak, periode kontrak, email dan telpon) 

4. Jika  perusahaan  mempunyai  laporan  keunagan,  diwajibkan  untuk  menyerahkan. Jika tidak ada, harus terlampir surat dukungan dari Bank.  

5. Pengajuan jadwal kerja 

6. Lampiran  3  harus  di  serahkan  untuk  melengkapi  pre‐schedule  dari  lampiran 2. 

 

Jadi,  surat  dukungan  Bank  dapat  disampaikan  apabila  vendor  tidak  bisa  memberikan laporan keuangan terakhir. 

  

Untuk Pos Dosay, apa yang akan digunakan untuk dinding kamar dan dan dinding  di luar kamar mandi? 

Untuk WC full dinding kalau diluar tidak full. 

Untuk penggunaan kloset jongkok akan memakai merk apa? 

  American Standard atau yang setara. 

Di pos Yewena, apakah perlu menggunakan tangga? 

  Tidak perlu karena lokasi nya landai. 

Di pos Yewena, apakah septitank akan dibangun di dalam tanah?  

Ya dan menggunakan pipa. 

Batu pecah yang digunakan nantinya akan menggunakan batu apa? 

Batu kali. 

10  Berapa ukuran untuk tebal seng ? 

0.3 mm. 

11  Apakah floor work (VI) di bagian pos Yewena akan ditambah volume nya? 

 

  Iya, penambahan rambat beton setebal 7cm, jadi total volume nya menjadi 0,165  m3.   

12  Untuk bagian Sanitation di Pos Yewena (IX) apakah akan ada penambahan? 

  Iya, akan dilengkapi dengan pembuatan plat seng untuk dinding dengan tebal 0.3  mm sehingga volumenya menjadi 11 meter. 

13  Kami  diperintahkan  untuk  bekerja  dalam  waktu  35  hari,  apakah  itu  tidak  terlalu  cepat dan adakah kemungkinan perpanjangan waktu? 

  Untuk pembangunan kelima pos harus dilaksanakan secara paralel atau serentak  dan  sudah  diperhitungkan  secara  teliti  bisa  selesai  dalam  waktu  35  hari  karena  bangunan yang akan dibuat dianggap tidak terlalu rumit. 

(4)

 

14  Q  Setelah selesai 20% pekerjaan, bagaimana cara pembayarannya? 

  Untuk  proses  pembayaran  baru  bisa  dilaksanakan  setelah  laporan  lengkap  diterima  dan  disahkan  oleh  pihak  UNODCdan  paling  lambat  2  minggu  sudah  terkirim  ke  rekening  vendor  pemenang.  Untuk  mempermudah,  saat  sudah  terpilih menjadi vendor diharapkan mengirimkan copy buku bank beserta vendor  form agar nantinya uang akan bisa di transfer segera setelah vendor didaftarkan  di sistem. 

 

NO  SUBJECT 

Info  Bid conference was opened with the following agendas :  1. Brief explanation order of conference 

2. Explanations of tender documents 

3. Explanations on the Scope of work and Bill of Quantity 

4.  The  addition  of  a  place  to  submit  tender  offers.  In  addition  to  email  and  submit  directly  to  the  UNDP  office  in  Jakarta,  the  bidder  may  submit  to  the  UNODC  office  in  Papua  ‐  BKPM  Building  2nd  Floor,  Jl.  No.  Samratulangi.  32  Jayapura,  Phone  0296  7523702  before  the  closing  date  which  is  1  pm  Jakarta  time on June 26, 2013. 

These clarifications were intended to clear the project for both parties. Questions  should  be  asked  on  the  spot,  and  if  additional  by  e‐mail  at  the  latest  three  days  before closing date. 

Q&A session is incorporated into the below minutes. 

Will we get first payment when we start  to construct the posts? 

Based  on  request  for  quotation  tender  document,  vendor  will  not  get  any  advance payment. 

 

Did  you  manage  all  permission  letter  from  Papua’s  government  regarding  construction of posts? 

  All  permission  letters  already  obtained  from  the  local  Jayapura  government  as  well as support from Ministry of Forestry. 

After  the  vendor  has  been  selected  and  obtained  permission  letter  from  Government, but later there is a request for additional payment due to a problem  of those lands, should we pay for this? And if it’s happen, is there any chance to  extend the duration in construction of those posts?  

 

(5)

Actually,  like  mentioned  before  we  already  managed  for  all  permission  letter  from  Government  and  also  Ministry  of  Forestry  therefore  it  will  not  become  a  concern and the vendor shall not be responsible on this particular matter. More,  if  there  is  any  internal  problem,  we  will  consider  to  extend  the  time  for  construction of those posts. But if the problem occurs from vendor side thus all  consequences shall be at vendor’s responsibility. 

 

If we want to submit quotation, should we also submit insurance/ bank support as  an evindence?  

As mentioned in the RFQ document (see annex 2) there are things that should be  submitted:  

1. Letter/ certificate of company registration  2. Company Profile 

3. Submit three biggest project or major client within 3 years such : name,  period of contract, amount of contract, email and phone  

4. If the company has a latest financial statement, it should be submitted. If  not, they can submit bank support letter. If they want to submit both, it  would be fine 

5. Propose work schedule 

6. Annex 3 shall be submitted to complete pre‐schedule from annex 2   

Thus,  bank  letters  of  support  may  be  submitted  if  the  vendor  can  not  provide  final financial statements. 

At Dosay Post, what will be used for toilet wall and also outside toilet?  

For toilet, you can use full wall, but for outside only a half. 

What brand that we use to toilet jongkok? 

  You can proceed with American Standard or equal to that. 

At Yewena Post, should we construct stairs? 

  No need. 

At Yewena Post, does “septitank” need to construct in the ground?  

Yes, and do use pipe. 

What rock that we can use for batu pecah?  

Batu kali. 

10  How about the size of iron sheet?  

Standard 0.3 mm. 

11  Does floor work (VI) at Yewena Post can be increased its volume? 

 

  Yes, it will add concrete wall 7 cm, so the volume will be 0,165 m3.   

12  Is there any additional volume for Sanitation (IX) at Yewena Pos? 

(6)

  Yes, will be completed with the iron sheet for wall with 0.3 mm in thickness thus  the total volume become 11 meters.  

13  We  asked  to  construct  within  35  days  of  calendar  days,  is  that  too  fast?  Is  there  any chance for extend the time? 

  The  construction  of  the  five  posts  should  be  carried  out  in  parallel  or  simultaneously  and  a  study  before  the  tender  issuance  has  been  carefully  both  conducted and calculated that the work can be reasonably completed within 35  days. 

14  Q  After the vendor is finished the 20% of work, how to get the payment?  

  The payment can be transferred after the acceptance of full report as well as the  approval and the vendor should receive it no later than 2 weeks. For simplicity,  soonest after get appointed as the winner, the vendor is expected to send a copy  of  the  bank  account  along  with  the  filled  vendor  form  so  that  the  payment  process can be smoothly done and will not cause any delay. 

 

Referensi

Dokumen terkait

Tabel 7 menunjukan bahwa interaksi antara suhu pengeringan dengan jenis jagung menunjukkan bahwa suhu pengeringan 60 o C dan 70 o C pada jagung manis dan jagung

Pengujian aspek Maintainability menghitung nilai MI ( maintainability index) dengan bantuan alat Source Code SearchEngine. Sedangkan pengujian aspek portability

10 Syaiful Amir 2013 Analysis Of Effect Of Public Perception, Bank Service and Public Knowledge to Shariah Banking Growth In Indonesia. 11 Hayu Prabowo 2013 An

Tidak ada tindakan yang perlu diambil dalam melakukan penawaran umum dari Instrumen Keuangan tersebut di wilayah yuridiksi lainnya, kecuali disebutkan di dalam prospektus

Dampak Perilaku Seksual Bebas Remaja Perilaku seksual bebas yang dilakukan remaja akan berdampak pada masalah kesehatan yang akan dihadapi, seperti: kehamilan yang tidak

Pengembangan Program Bimbingan Karir Berbasis teori Karir Holland Universitas Pendidikan Indonesia | repository.upi.edu | perpustakaan.upi.edu..

Dalam Kamus Besar Bahasa Indonesia (KBBI), inovasi diartikan sebagai pemasukan atau pengenalan hal-hal yang baru, penemuan baru yang berbeda dari yang sudah ada atau yang

©2010 Prentice Hall Business Publishing, Auditing 13/e, Auditing 13/e, Arens//Elder/Beasley Arens//Elder/Beasley 22 - 22 - 10 10.. Learning Objective 2 Learning