ANALISIS FAKTOR – FAKTOR YANG MEMPENGARUHI WAKTU TUNGGU PROSES PENGADAAN MATERIAL KONSTRUKSI PADA

PROYEK BENDUNG DAN JARINGAN IRIGASI DI PROPINSI SUMATERA BARAT

Yon Pardi¹, Alizar Hasan², M. Nursyaifi Yulius¹

¹Program Studi Teknik Sipil, Program Pascasarjana Universitas Bung Hatta ²Program Studi Teknik Sipil, Program Pascasarjana Universitas Andalas

e-mail : yonpardimakmur6769@gmail.com

ABSTRAK

Pengelolaan material adalah merupakan suatu aspek penting dalam pelaksanaan pembangunan suatu proyek, khususnya pelaksanaan pembangunan proyek bendung dan jaringan irigasi. Keberhasilan suatu proyek bendung dan jaringan irigasi amat bergantung tersedianya material yang diperlukan. Secara umum terdapat beberapa masalah dan faktor berkaitan dengan proses pengadaan material ini sehingga mempengaruhi waktu tunggu proses pengadaan material proyek. Namun secara pasti belum diketahui apa saja faktor proses pengadaan material ini yang mempengaruhi waktu tunggu pelaksanaan pekerjaan khususnya di Propinsi Sumatera Barat. Sehubungan dengan itu, penelitian ini mencoba melihat faktor- faktor proses pengadaan material apa sajakah yang mempengaruhi waktu tunggu ini. Tujuan utama dari penelitian ini ialah untuk mengetahui faktor-faktor proses pengadaan material dan pengaruhnya terhadap waktu tunggu. Untuk memastikan tujuan ini tercapai, beberapa proses penelitian telah dilakukan yaitu; kajian literatur, kuisioner. Sebanyak 156 responden telah dilibatkan dalam penelitian yang terdiri dari kontraktor gred 5 sampai gred 7 dan dari dinas pekerjaan umum serta stakeholder lainnya. Beberapa analisis digunakan untuk mengukur faktor proses pengadaan material diantaranya analisis faktor yang terdiri dari analisis validitas, reliabilitas, korelasi dan regresi. Hasil penelitian menunjukan ada 3 faktor dan 30 variabel proses pengadaan material. Sementara dilihat dari sisi pengaruh faktor proses ini terhadap waktu tunggu pelaksanaan pekerjaan diperoleh 4 faktor dan 40 variabel yang mempengaruhi waktu tunggu pelaksanaan pekerjaan bendung dan jaringan irigasi di Propinsi Sumatera Barat.

(2)

ABSTRACT

Material management is an important aspect of project development, Especially the implementation of the dam project and irrigation network. The success of a dam project and irrigation network is highly dependent on the availability of the necessary materials. In general there are several problems and factors related to the procurement process of this material that affect the procurement waiting time of project materials. However, it is unclear what are the factors of this material procurement process that affect the waiting time for the implementation of work, especially in West Sumatra Province.Accordingly, this study attempts to see what factors of material procurement processes affect the waiting time. The main purpose of this research is to know the factors of material procurement process and its effect on waiting time. To ensure this goal is achieved, several research processes have been conducted, namely; Literature review, questionnaire. A total of 156 respondents have been included in the study consisting of contractors gred 5 to gred 7 and from the public works department as well as other stakeholders. Several analyzes are used to measure procurement process factors such as factor analysis consisting of validity, reliability, correlation and regression analysis. The results showed that there were 3 factors and 30 variables of materials procurement process. While viewed from the side of the influence of this process factors to the waiting time of implementation of work obtained 4 factors and 40 variables that affect the waiting time of the implementation of dam and irrigation networks in West Sumatera Province.

Referensi

Dokumen terkait

Sehubungan dengan pelaksanaan pelelangan PENGA DA A N PERA LATA N PRA KTEK DA N PERA GA SISWA SD pada Dinas Pendidikan, Pemuda dan Olah Raga Kota Bima Tahun

Prinsip pengemasan aseptis adalah baik bahan pangan yang dikemas maupun bahan kemasan harus bebas dari mikroorganisme perusak ketika bahan pangan tersebut dikemas,

Masa Tugas Belajar Program Magister Konsentrasi Tata Kelola Pemilihan Umum selama 2 (dua) tahun. Apabila Penerima Beasiswa tidak dapat menyelesaikan studi sebagaimana

Disahkan dalam rapat Pleno PPS tanggal 26 Februari 2013 PANITIA PEMUNGUTAN SUARA. Nama

Dengan mempertimbangkan pilihan-pilihan adaptasi yang dikembangkan PDAM dan pemangku kepentingan, IUWASH juga merekomendasikan untuk mempertimbangkan aksi-aksi adaptasi

Selanjutnya untuk mencari hubungan biaya reparasi dan service mesin terhadap jam mesin dapat dicari dengan menggunakan metode korelasi product moment (Pearson) karena data yang

The aim of this study are to analyze the text of female sexuality articles that realized in the women magazines (i.e. vocabulary, grammar, cohesion and text

Kebiasaan dalam pengelolaan pembuatan kue rumahan di Desa Lampanah memiliki kebiasaan kurang baik, hal ini di sebabkan karena pengelolaan kue rumahan oleh