MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 26 NOVEMBER 2019

PRESENT

Cameron McKenzie Group Manager – Development & Compliance (Chair) Paul Osborne Manager – Development Assessment

Benjamin Hawkins Manager – Subdivision & Development Certification Angelo Berios Manager – Environment & Health

Craig Woods Manager – Regulatory Services Nicholas Carlton Manager – Forward Planning

Kristine McKenzie Principal Executive Planner

APOLOGIES Nil

TIME OF COMMENCEMENT 8:30am

TIME OF COMPLETION 8:45am

ITEM-1 CONFIRMATION OF MINUTES

RESOLUTION

The Minutes of the Development Assessment Unit Meeting of Council held on 12 November 2019 be confirmed.

ITEM-2 DA 576/2016/JP/A – A SECTION 4.56 MODIFICATION TO A MIXED USE DEVELOPMENT – LOT 12 DP 1169214 YORK ROAD, KELLYVILLE

PUBLIC NOTIFICATION OF THE DETERMINATION PURSUANT TO ITEM 2(2)(c) AND (d) OF SCHEDULE 1 OF THE ENVIRONMENTAL PLANNING 7 ASSESSMENT ACT, 1979

DECISION:

Pursuant to the provisions of Section 4.56 of the Environmental Planning and Assessment Act 1979, the modification be approved as follows:-

(2)

PAGE 2 Conditions Nos. 1, 32, 45 be deleted and replaced as follows:

GENERAL MATTERS

1. Development in Accordance with Submitted Plans

The development being carried out in accordance with the following approved plans and details, stamped and returned with this consent except where amended by other conditions of consent.

REFERENCED PLANS AND DOCUMENTS

DWG NO./DESCRIPTION REV DATE

S34-000 - COVER SHEET J 04/12/2016

S34-010 - EXISTING / DEMOLITION SITE PLAN C 28/09/2016

S34-011 - PROPOSED SITE PLAN F 04/12/2016

S34-021 - PROPOSED SITE REFERENCE PLAN - BASEMENT 02 R 28/09/2016 S34-022 - PROPOSED SITE REFERENCE PLAN - BASEMENT 01 S 04/12/2016 S34-023 - PROPOSED SITE REFERENCE PLAN - GROUND S 04/12/2016 S34-024 - PROPOSED SITE REFERENCE PLAN - LEVEL 01 S 04/12/2016 S34-025 - PROPOSED SITE REFERENCE PLAN - LEVEL 02 S 04/12/2016 S34-026 - PROPOSED SITE REFERENCE PLAN - LEVEL 03 S 04/12/2016 S34-027 - PROPOSED SITE REFERENCE PLAN - LEVEL 04 S 04/12/2016 S34-028 - PROPOSED SITE REFERENCE PLAN - ROOF S 04/12/2016 S34-101 - PROPOSED FLOOR PLAN - LOT 1 EAST - BASEMENT 02 F 28/09/2016 S34-102 - PROPOSED FLOOR PLAN - LOT 1 EAST - BASEMENT 01 F 28/09/2016 S34-103 - PROPOSED FLOOR PLAN - LOT 1 EAST - GROUND G 28/09/2016 S34-104 - PROPOSED FLOOR PLAN - LOT 1 EAST - LEVEL 01 H 04/12/2016 S34-105 - PROPOSED FLOOR PLAN - LOT 1 EAST - LEVEL 02 H 04/12/2016 S34-106 - PROPOSED FLOOR PLAN - LOT 1 EAST - LEVEL 03 H 04/12/2016 S34-107 - PROPOSED FLOOR PLAN - LOT 1 EAST - LEVEL 04 H 04/12/2016 S34-108 - PROPOSED FLOOR PLAN - LOT 1 EAST - ROOF H 04/12/2016 S34-112 - PROPOSED FLOOR PLAN - LOT 1 WEST - BASEMENT 01 G 04/12/2016 S34-113 - PROPOSED FLOOR PLAN - LOT 1 WEST - GROUND H 04/12/2016 S34-114 - PROPOSED FLOOR PLAN - LOT 1 WEST - LEVEL 01 H 04/12/2016 S34-115 - PROPOSED FLOOR PLAN - LOT 1 WEST - LEVEL 02 H 04/12/2016 S34-116 - PROPOSED FLOOR PLAN - LOT 1 WEST - LEVEL 03 H 04/12/2016 S34-117 - PROPOSED FLOOR PLAN - LOT 1 WEST - LEVEL 04 H 04/12/2016 S34-118 - PROPOSED FLOOR PLAN - LOT 1 WEST - ROOF H 04/12/2016 S34-121 - PROPOSED FLOOR PLAN - LOT 2 - BASEMENT 02 F 28/09/2016

(3)

PAGE 3 S34-122 - PROPOSED FLOOR PLAN - LOT 2 - BASEMENT 01 F 28/09/2016 S34-123 - PROPOSED FLOOR PLAN - LOT 2 - GROUND G 28/09/2016 S34-124 - PROPOSED FLOOR PLAN - LOT 2 - LEVEL 01 G 28/09/2016 S34-125 - PROPOSED FLOOR PLAN - LOT 2 - LEVEL 02 G 28/09/2016 S34-126 - PROPOSED FLOOR PLAN - LOT 2 - LEVEL 03 G 28/09/2016 S34-127 - PROPOSED FLOOR PLAN - LOT 2 - LEVEL 04 G 28/09/2016 S34-128 - PROPOSED FLOOR PLAN - LOT 2 - ROOF H 04/12/2016 S34-132 - PROPOSED FLOOR PLAN - LOT 3 - BASEMENT 01 G 28/11/2016 S34-133 - PROPOSED FLOOR PLAN - LOT 3 - GROUND F 24/11/2016 S34-134 - PROPOSED FLOOR PLAN - LOT 3 - LEVEL 01 E 28/09/2016 S34-135 - PROPOSED FLOOR PLAN - LOT 3 - ROOF E 28/09/2016 S34-401 - PROPOSED BUILDING ELEVATIONS - LOT 1 BLDG A H 04/12/2016 S34-402 - PROPOSED BUILDING ELEVATIONS - LOT 1 BLDG B H 04/12/2016 S34-403 - PROPOSED BUILDING ELEVATIONS - LOT 1 BLDG C H 04/12/2016 S34-404 - PROPOSED BUILDING ELEVATIONS - LOT 2 J 04/12/2016 S34-405 - PROPOSED BUILDING ELEVATIONS - LOT 3 E 24/11/2016 S34-411 - PROPOSED BUILDING ELEVATIONS - LOT 1 BLDG A

COURTYARD E 04/12/2016

S34-413 - PROPOSED BUILDING ELEVATIONS - LOT 1 BLDG C

COURTYARD F 04/12/2016

S34-414 - PROPOSED BUILDING ELEVATIONS - LOT 2 COURTYARD F 04/12/2016 S34-421 - PROPOSED BUILDING SECTIONS - LOT 1 BLDG A H 04/12/2016 S34-423 - PROPOSED BUILDING SECTIONS - LOT 1 BLDG B H 04/12/2016 S34-424 - PROPOSED BUILDING SECTIONS - LOT 1 BLDG C J 04/12/2016 S34-425 - PROPOSED BUILDING SECTIONS - LOT 2 H 28/09/2016 S34-427 - PROPOSED BUILDING SECTIONS - LOT 3 C 28/09/2016 S34-510 - DIAGRAMS - SEP 2016 KEY DIMENSIONS A 28/09/2016 S34-800 - SHADOW DIAGRAMS - 21ST DECEMBER E 28/09/2016

S34-801 - SHADOW DIAGRAMS - 21ST JUNE E 28/09/2016

S34-927 - EXTERNAL FINISHES SCHEDULE C 28/09/2016

ARCADIA LANDSCAPE ARCHITECTURE LANDSCAPE PLANS:

001 - Landscape Masterplan E 30/09/2016

101 - Landscape Detail Plan E 30/09/2016

102 - Landscape Masterplan E 30/09/2016

103 - Landscape Masterplan E 30/09/2016

104 - Landscape Masterplan E 30/09/2016

501 - Landscape Masterplan E 30/09/2016

502 - Landscape Masterplan E 30/09/2016

(4)

PAGE 4 ARCADIA LANDSCAPE ARCHITECTURE LANDSCAPE PLANS

APPENDIX SUPPORTING DOCUMENTS: E 30/09/2016

101 - Heritage + History E September 2016

102 - Landscape Principles E September 2016

103 - Landscape Strategy E September 2016

104 - Site Master Plan E September 2016

105 - Landscape Sections E September 2016

106 - Recreation Areas – Character + Principles E September 2016

107 - Landscape Precedents E September 2016

108 - Courtyards – Character + Principles E September 2016 109 - Courtyard and Access Precedents E September 2016 110 - Streetscape + Linear Entrance – Character + Principles E September 2016 111 - Streetscape + Linear Entrance Precedents E September 2016

112 - Indicative Planting Palette E September 2016

113 - Indicative Planting Palette E September 2016

114 - Landscape + Domain Furniture E September 2016

York Road Child Care Centre- Air Quality Assessment 19/08/2016 Design Verification Statement - SEPP 65 / Apartment Design Guide

Compliance Table 4 December 2016

Building Code of Australia Report - proposed residential Development 4 4 October 2016

Waste Management Plan 29/09/2016

Subdivision Plan Reference 14430/204 00 01/10/2015

Statement of Environmental Effects dated October 2015 and Addendum

Statement of Environmental Effects prepared by Urbis Pty Ltd 18/10/2016

Amended Civil Hydraulics Plans 14 October 2016

Air Quality Report prepared by Pacific Environment Limited 24 November 2016 Acoustic Report prepared by Wood and Grieve providing acoustic

information

Updated Acoustic Report prepared by Wood and Grieve providing acoustic information and

17 February 2016

Acoustic Assessment and Report prepared by Wood and Grieve Engineers,

referenced as York Rd, Kellyville 13 October 2015

Staging Plan (4 Stages) (Reference S34-015) A 6 September 2019

No work (including excavation, land fill or earth reshaping) shall be undertaken prior to the issue of the Construction Certificate, where a Construction Certificate is required.

PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

32. Section 7.11 Contribution

The following monetary contributions must be paid to Council in accordance with Section 7.11 of the Environmental Planning and Assessment Act, 1979, to provide for the increased demand for public amenities and services resulting from the development.

Payments comprise of the following:-

(5)

PAGE 5

Stage 1

Stage 3

Stage 4

The contributions above are applicable at the time this consent was issued. Please be aware that Section 7.11 contributions are updated quarterly.

Prior to payment of the above contributions, the applicant is advised to contact Council’s Development Contributions Officer on 9843 0268. Payment must be made by cheque or credit/debit card. Cash payments will not be accepted.

This condition has been imposed in accordance with Contributions Plan No 8.

Council’s Contributions Plans can be viewed at www.thehills.nsw.gov.au or a copy may be inspected or purchased at Council’s Administration Centre.

45. Design Verification

Prior to the release of the relevant Stage 3 or Stage 4 Construction Certificate design verification is required from a qualified designer to confirm the development is in accordance with the approved plans and details and continues to satisfy the design quality principles in SEPP65.

REASONS FOR THE DECISION:

 Section 4.58 (EP&A) Act – Satisfactory.

 SEPP No. 65 – Design Quality of Residential Apartment Development – Satisfactory.

 SEPP Educational Establishments and Child Care Facilities 2017 – Satisfactory.

 State Environmental Planning Policy No. 55 – Remediation of Land – Satisfactory.

 Local Environmental Plan 2012 – Satisfactory.

 Development Control Plan 2012 – Satisfactory.

HOW COMMUNITY VIEWS WERE TAKEN INTO ACCOUNT IN MAKING THE DECISION:

The development application was notified and eight (8) submissions including a petition were

received. The issues raised were discussed in the report.

(6)

PAGE 6

ITEM-3 DA 1701/2017/ZD – SUBDIVISION CREATING 12 COMMUNITY TITLE RURAL RESIDENTIAL LOTS AND ONE ASSOCIATION LOT (RURAL CLUSTER) – LOTS 2 AND 3 DP 585842, 600-620 WISEMANS FERRY ROAD, SOUTH MAROOTA

PUBLIC NOTIFICATION OF THE DETERMINATION PURSUANT TO ITEM 20(2)(c) AND (d) OF SCHEDULE 1 OF THE ENVIRONMENTAL PLANNING & ASSESSMENT ACT, 1979

DECISION:

The application be approved subject to conditions in the report.

REASONS FOR THE DECISION:

 Section 4.15 (EP&A Act) – Satisfactory.

 The Hills LEP 2012 – Satisfactory.

 SEPP No. 55 – Remediation of Land – Satisfactory.

 The Hills DCP – Part B Section 1 – Rural – Variation sought, see report.

 Section 7.12 Contribution - $5,090.00

HOW COMMUNITY VIEWS WERE TAKEN INTO ACCOUNT IN MAKING THE DECISION:

The development application was notified and three (3) submissions were received.

NB: A further submission from a resident was tabled and discussed at the meeting.

Referensi

Dokumen terkait

The noise emitted from barking dogs will not comply with the night time noise criteria of 30dBA for this site nor does the proposal meet the offensive noise test under the EPA Guide for

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 19 OCTOBER 2021 PRESENT Cameron McKenzie Group Manager – Development & Compliance

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 6 APRIL 2021 PRESENT Cameron McKenzie Group Manager – Development & Compliance Chair

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 22 JUNE 2021 PRESENT Cameron McKenzie Group Manager – Development & Compliance Chair

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 24 AUGUST 2021 PRESENT ITEM 1 Cameron McKenzie Group Manager – Development &

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 10 MARCH 2020 PRESENT Cameron McKenzie Group Manager – Development & Compliance Chair

ITEM-2 DA 1712/2017/ZD - SUBDIVISION CREATING 11 COMMUNITY TITLE RESIDENTIAL LOTS AND ONE COMMUNITY ASSOCIATION LOT INCLUDING NEW ROAD AND DEMOLITION - LOT 6 DP 242138, 20 BRUCE

MINUTES OF THE DEVELOPMENT ASSESSMENT UNIT MEETING HELD AT THE HILLS SHIRE COUNCIL ON TUESDAY, 17 JANUARY 2023 PRESENT Cameron McKenzie Group Manager – Development & Compliance