STUDI PERBANDINGAN PENJADWALAN PROYEK PADA GEDUNG FAKULTAS ILMU ADMINISTRASI UNIVERSITAS BRAWIJAYA MALANG DENGAN MENGGUNAKAN PROGRAM PRIMAVERA PROJECT PLANNER

N/A
N/A
Protected

Academic year: 2017

Membagikan "STUDI PERBANDINGAN PENJADWALAN PROYEK PADA GEDUNG FAKULTAS ILMU ADMINISTRASI UNIVERSITAS BRAWIJAYA MALANG DENGAN MENGGUNAKAN PROGRAM PRIMAVERA PROJECT PLANNER"

Copied!
2
0
0

Teks penuh

(1)

STUDI PERBANDINGAN PENJADWALAN PROYEKPADA GEDUNG

FAKULTAS ILMU ADMINISTRASIUNIVERSITAS BRAWIJAYA

MALANGDENGAN MENGGUNAKANPROGRAM PRIMAVERA PROJECT

PLANNER

Oleh: ENY KRISTANTI (00520064) Civil Engineering

Dibuat: 2007-02-05 , dengan 3 file(s).

Keywords: Penjadwalan, Biaya, Waktu, Primavera

Persaingan antar perusahaan jasa konstruksi dalam memperebutkan pasar semakin ketat. Untuk memenangkan persaingan, perusahaan harus memiliki keunggulan daya saing yang tidak mudah ditiru oleh pesaingnya. Salah satunya adalah manajemen yang diterapkan dalam perusahaan. Manajemen di tiap perusahaan tidak akan pernah sama, karena manajemen bersifat unik.

Keunikan dari manajemen perusahaan ini disebabkan cukup bervariasinya proses yang ada, yaitu merencanakan, mengorganisasi, mengarahkan, memantau, dan mengendalikan. Perusahaan dengan manajemen yang baik akan mampu memenangkan persaingan karena dapat melakukan efisiensi tinggi tanpa mengorbankan kualitas dan kepuasan pelanggan.

Metodologi yang digunakan adalah rescedulling (penjadwalan ulang) proyek pembangunan gedung Fakultas Ilmu Administrasi Universitas Brawijaya Malang dengan menggunakan program Primavera Project Planner dan analisa perbandingan biaya dan waktu antara proyek dengan hasil analisa program Primavera.

Dari hasil perhitungan yang dilakukan dengan menggunakan program Primavera Project Planner 3.0, diketahui durasi/ waktu pelaksanaan total untuk tahap I sebesar 156 hari kerja dari waktu pelaksanaan awal 166 hari yang berarti ada percepatan sebesar 10 hari kerja (6.024 %). Untuk tahap II sebesar 122 hari kerja dari waktu pelaksanaan awal 148 hari yang berarti ada percepatan sebesar 30 hari kalender atau 26 hari kerja (18 %). Sedangkan untuk biaya proyek tahap I hasil analisa Primavera diperoleh total biaya sebesar Rp 3.136.516.191,60 (termasuk keuntungan kontraktor dan PPN 10%) dari biaya proyek keseluruhan yang dianggarkan sebesar Rp.

3.100.000.000,00. (termasuk keuntungan kontraktor dan PPN 10%). Untuk tahap II, hasil analisa dengan Primavera diperoleh total biaya sebesar Rp 2.123.901.122,20 (sudah termasuk

keuntungan kontraktor dan PPN 10%) dari biaya proyek keseluruhan yang dianggarkan sebesar Rp. 2.206.000.000,00 (sudah termasuk keuntungan kontraktor dan PPN 10%). Hal tersebut di atas berarti terjadi selisih biaya minus Rp. 36.516.191,60 (kekurangan dana sebesar 1.18 %) untuk tahap I dan plus Rp. 82.098.877,80 (keuntungan sebesar 3.72%) untuk tahap II.

Abstract

(2)

without sacrificing quality and customer satisfaction.

The methodology used is rescedulling (rescheduled) a building site of Administrative Sciences UB Malang by using Primavera Project Planner and comparative analysis of cost and time between projects with Primavera program analysis.

From the results of calculations performed by using Primavera Project Planner 3.0 program, known duration / timing of the total for the first phase of 156 days from the time of the initial 166 days, which means there is acceleration of 10 working days (6024%). For phase II of 122 working days from the time of the initial 148 days, which means there is acceleration of 30 calendar days or 26 working days (18%). As for the phase I project cost analysis results obtained Primavera total cost of Rp 3,136,516,191.60 (including contractor profit and VAT 10%) of the total project cost is budgeted at Rp. 3,100,000,000.00. (Including contractor profit and VAT 10%). For phase II, the results of analysis with Primavera acquired the total cost of Rp 2,123,901,122.20 (including contractor profit and VAT 10%) of the total project cost is budgeted at Rp. 2,206,000,000.00 (including contractor profit and VAT 10%). The above means there is a difference in cost minus Rp. 36,516,191.60 (lack of funds of 1:18%) for stage I and plus Rp.

Referensi

Dokumen terkait

Untuk mengetahui masalah tersebut, peneliti akan mencoba untuk memperbaiki kemampuan berpikir belajar siswa dengan mencoba menggunakan model pembelajaran yang tepat di

Buku Siswa diarahkan agar siswa lebih aktif dalam mengikuti proses pembelajaran melalui kegiatan mengamati, menanya, menalar, mencoba, berdiskusi serta

memakai marketing, BUS bisa memperoleh nasabah yang mencukupi karena mempunyai banyak cabang, mempunyai banyak fasilitas dan tentunya mempunyai dana yang lebih besar ,

Keyakinan yang menegaskan bahwa selaput dara utuh sebelum adanya penetrasi ke vagina adalah tidak benar, terdapat juga kesimpulan yang tidak benar bahwa terdapat

Brojni drugi dokumenti FIP -a predstavljaju politiku FIP-a, zvani č ne stavove ili preporuke o mnogim pitanjima vezanim za oblast farmaceutske delatnosti, ali dva navedena

Metode KCKT fase terbalik untuk penetapan kadar bisfenol A pada air minum dalam botol plastik dan botol air minum yang diberi pengaruh penyinaran matahari tropis

Implementasi Training Kit Water Tank Filling System pada Proses Perkuliahan Mata Kuliah Sistem Kendali ... Respon Mahasiswa Terhadap Penggunaan WTFS pada Perkuliahan Sistem Kendali

menyatakan dengan sesungguhnya bahwa skripsi yang berjudul “ Uji Aktivitas Antibakteri Ekstrak Etanol Biji Kakao (Theobroma cacao) terhadap Staphylococcus aureus