ANALISA BIAYA, WAKTU DAN SUMBER DAYA TERHADAP RENCANA JADWAL PELAKSANAAN PADA PROYEK PEMBANGUNAN SMU UNGGULAN TERPADU KABUPATEN LUMAJANG

N/A
N/A
Protected

Academic year: 2017

Membagikan "ANALISA BIAYA, WAKTU DAN SUMBER DAYA TERHADAP RENCANA JADWAL PELAKSANAAN PADA PROYEK PEMBANGUNAN SMU UNGGULAN TERPADU KABUPATEN LUMAJANG"

Copied!
1
0
0

Teks penuh

(1)

ANALISA BIAYA, WAKTU DAN SUMBER DAYA TERHADAPRENCANA

JADWAL PELAKSANAAN PADA PROYEKPEMBANGUNAN SMU

UNGGULAN TERPADUKABUPATEN LUMAJANG

Oleh: FINA NOVIA RIZKA ( 01520097 )

Civil Engineering Dibuat: 2007-03-28 , dengan 3 file(s).

Keywords: Biaya, Waktu, dan Sumber Daya

Dalam perencanaan proyek terdapat bermacam aktifitas yang jumlahnya banyak, sehingga diperlukan suatu manajemen yang baik agar pelaksanaannya tepat waktu. Dan tidak terjadi fluktuasi sumber daya manusia.

Manajemen proyek memegang peranan yang sangat penting untuk mencapai tujuan secara efisien dan seefektif mungkin. Mengarahkan sumber daya manusia dan sumber daya lain supaya berjalan dijalur yang seharusnya menuju suatu sasaran yang telah ditetapkan. Analisa bertujuan mengungkapkan permasalahan manajemen proyek dan memberikan alternatif dalam bentuk pengembangan dan penyempurnaan yang lebih memenuhi prinsip-prinsip kemudahan, kepraktisan dan keekonomisan proyek. Penganalisaan biaya, waktu dan sumber daya dengan mekanisme penjadwalan ulang (rescedulling) dengan menggunakan program Primavera Project Planner

Dari hasil perhitungan yang dilakukan dengan menggunakan program Primavera Project Planner 3.0, diperoleh total biaya sebesar Rp 8.072.165.470.00 (belum termasuk keuntungan kontraktor dan PPN 10%) dari biaya proyek keseluruhan yang dianggarkan sebesar Rp. 8.075.910.240.42 (belum termasuk keuntungan kontraktor dan PPN 10%). Dan penjadwalan (Reschedulling) dari waktu pelaksanaan awal 206 hari dan dengan adanya pemerataan sumber daya (Resource Levelling) didapat percepatan 27 hari, dari batasan waktu yang telah ditetapkan.

Abstract

In planning the project there are various activities which are numerous, so we need a good management for timely implementation. And no fluctuation of human resources.

Project management plays a very important to achieve objectives efficiently and effectively as possible. Directing human resources and other resources which should so walk dijalur toward a predetermined

goal. The analysis aims to reveal the project management issues and provides an alternative in the form of development and refinement that better meet the principles of simplicity, practicality and economy of the project. Analysing the costs, time and resources to the rescheduling mechanism (rescedulling) using Primavera Project Planner program

From the results of calculations performed by using Primavera Project Planner 3.0 program, obtained a total cost of Rp 8.072.165.470.00 (excluding contractor profit and VAT 10%) of the total project cost is

Referensi

Dokumen terkait

Implementasi Training Kit Water Tank Filling System pada Proses Perkuliahan Mata Kuliah Sistem Kendali ... Respon Mahasiswa Terhadap Penggunaan WTFS pada Perkuliahan Sistem Kendali

Dari penelitian yang dilakukan pada bulan Maret 2007 melibatkan 228 responden, didapatkan 90,7% responden mengalami leukorea, dimana 38,7% di antaranya mengalami

Pengembangan Sistem Informasi Akademik pada SMA ISLAM AL- MUSYAWARAH yang akan dibuat mampu mengolah Data Pendaftaran Siswa Baru, Data Penyeleksian Siswa Baru,

memenuhi kualifikasi harus melakukan pengujian beton segar di lokasi konstruksi, menyiapkan contoh-contoh uji silinder yang diperlukan untuk mencatat suhu beton segar pada

Buku Siswa diarahkan agar siswa lebih aktif dalam mengikuti proses pembelajaran melalui kegiatan mengamati, menanya, menalar, mencoba, berdiskusi serta

Dari penelitian awal yang penulis lakukan dengan cara melakukan interview (wawancara) pada beberapa orang terkait penilaiannya selama 5 tahun kebelakang terhadap kinerja

Tujuan penelitian ini adalah untuk mengetahui faktor-faktor yang berpengaruh terhadap jumlah kasus penderita campak dengan menggunakan metode Regresi Nonparametrik

Moleong (2007:157), sumber data utama penelitian kualitatif adalah kata-kata dan tindakan, sehingga selebihnya adalah data tambahan berupa dokumen dan lain-lain. kata-kata