Kegiatan : Program P2TPD Dinas Kesehatan Kab. Bulukumba Lokasi
Pekerjaan : Pembangunan Jaringan Perpipaan + Bangunan Pelengkap Tahun Anggaran
Volume : 5,500 m Kabupaten
JUMLAH HARGA SATUAN (Rp)
1 3 4
I PEK. PENDAHULUAN 12,324,167.40
II PEKERJAAN UTAMA
Pengadaan Pipa 277,796,740.00
Pengadaan Accessories 15,768,700.00
Pemasangan Pipa 72,565,305.48
Pemasangan Accessories 6,552,316.49
III PEKERJAAN BANGUNAN PELENGKAP
Pek. Hidrant Umum 25 7,370,984.14
Pek. Rangka Struktur Turbine 127,105,012.80
Pek. Pengadaan dan Pemasangan Turbin Angin 2,917,800,000.00 Pengadaan Dan Instalasi Listrik 10,739,421.69
IV Pekerjaan Pengeboran 2 141,992,126.09
Dr. Hj. Rusni Sufran Nip: 196212110 198303 1 021
Kab. Bulukumba
DIBULATKAN (B)
Terbilang :
PPn 10% (tidak dipungut)(10% x B = C) DIBULATKAN Jumlah (B + C)
Program P2TPD Dinas Kesehatan
Mengetahui / Meny
REKAPITULASI RENCANA ANGGARAN BIAYA PERPIPAAN + BANGUNAN PEL
NO URAIAN PEKERJAAN VOLUME
2
Jumlah (A)
Nip ; 19530103 1980 Pangkat : Pembina
Bulukumba, Pimpinan Kegiatan
Hasanuddin, SKM. M.Kes
Tiga Milyar Sembilan Ratus Delapan Juta Sembilan Ratus Sepuluh Ribu Rupiah
Kepala Dinas Kesehatan Kab.
: Kel. Mariorennu : 2010
: Bulukumba
5
12,324,167.40
277,796,740.00
15,768,700.00
72,565,305.48
6,552,316.49
184,274,603.40
127,105,012.80
2,917,800,000.00
10,739,421.69
283,984,252.18
3,908,910,519.44
3,908,910,000.00
390,891,000.00
4,299,801,000.00
4,299,801,000.00
an. M.Kes enyetujui
ELENGKAP
JUMLAH (Rp)
8011 2 001 a Tk.I
Februari 2010 ab. Bulukumba
Kegiatan : Program P2TPD Dinas Kesehatan Kab. Bulukumba Lokasi
Pekerjaan : Pembangunan Jaringan Perpipaan + Bangunan Pelengkap Tahun Anggaran
Volume : 5,500 m Kabupaten
HARGA SATUAN
1 4
A. PEK. PENDAHULUAN
1. 1 Pengukuran Jalur Pipa dan Pematokan 5,500.00 m1 926.95
2 Papan Nama Proyek 1.00 ls 350,000.00
3 Administrasi dan Dokumentasi 1.00 ls 1,000,000.00 4 Back Up Data dan As Built Drawing 1.00 ls 750,000.00 5 Direksikeet 3 x 3 meter 9.00 m2 458,435.55 6 Mobilisasi Peralatan dan Tenaga Kerja 1.00 ls 1,000,000.00
B. PEKERJAAN UTAMA 1. Pengadaan Pipa
Pipa PVC, Tekanan Nominal 10 kg/cm2 Termasuk Pengangkutan Ke Lokasi Pekerjaan
1 Pipa PVC Paralon std S - 12,5 RRJ 3" 4,580.00 m1 54,571.00 2 Pipa PVC Paralon std S - 12,5 RRJ 2" 920.00 m1 27,588.00 3 Pipa GIP 4" (pelintas) 30.00 m1 79,300.00 4 Pipa GIP 1" (pelintas) 8.00 m 12,700.00 J U M L A H 2. Pengadaan Accessories
1 Long Bend Ø 3" (raubber ring)
- Ø 3" 90o 6.00 bh 133,300.00
- Ø 3" 45o 4.00 bh 116,700.00
2 Bell Reducer Ø 3" x Ø 2" (raubber ring) 2.00 bh 74,600.00 3 TS TEE Ø 3" (raubber ring) 3.00 bh 50,000.00 4 TS TEE Ø 3" - 2"(raubber ring) 2.00 bh 65,000.00 5 Ventil Udara Ø 13 mm 2.00 bh 425,000.00 6 Clamp Sadlle Ø 2" x 0,5" 25.00 bh 24,400.00
7 DOP 3.00 bh 36,800.00
8 Stop Kran Ø 3" (Flange) 6.00 bh 500,000.00
9 WaterMeter 3/4 25.00 bh 350,000.00
10 Stop Kran Ø 3/4 " 25.00 bh 30,100.00 J U M L A H 3. Pemasangan Pipa
1 Pipa PVC Paralon std S - 12,5 RRJ 3" 4,580.00 m1 13,452.57 2 Pipa PVC Paralon std S - 12,5 RRJ 2" 920.00 m1 11,139.44 3 Pipa GIP 4" (pelintas) 30.00 m1 18,533.33 4 Pipa GIP 1" (pelintas) 8.00 m 18,533.33 J U M L A H 4. Pemasangan Accessories
1 Bell Bend Ø 3"
- Ø 3" 90o 6.00 bh 72,072.04
- Ø 3" 45o 4.00 bh 66,811.88
2 Bell Reducer Ø 3" x Ø 2" (raubber ring) 2.00 bh 79,878.06 3 TS TEE Ø 3" (raubber ring) 3.00 bh 76,660.08 4 TS TEE Ø 3" - 2"(raubber ring) 2.00 bh 76,660.08 5 Ventil Udara Ø 13 mm 2.00 bh 61,200.00 6 Clamp Sadlle Ø 2" x 0,5" 25.00 bh 61,200.00
7 DOP 3.00 bh 76,660.08
8 Stop Kran Ø 3" (Flange) 6.00 bh 61,200.00
9 WaterMeter 3/4 25.00 bh 61,200.00
10 Stop Kran Ø 3/4 " 25.00 bh 61,200.00 J U M L A H J U M L A H A
2 3
RENCANA ANGGARAN BIAYA
NO URAIAN PEKERJAAN VOL. /
SAT.
J U M L A H B
HARGA SATUAN
1 2 3 4
NO URAIAN PEKERJAAN VOL. /
SAT.
C. PEKERJAAN BANGUNAN PELENGKAP 1 Pek. Hidrant Umum
1 Galian Tanah 1.22 m3 13,900.00
2 Urugan Tanah 0.61 m3 161,687.50
3 Urugan Sirtu Bawah Lantai 2.10 m3 209,275.00 4 Pasangan Batu Kosong 1.43 m3 313,942.50 5 Pasangan Pondasi Batu Kali 1 : 4 2.78 m3 528,470.90 6 Pekerjaan Rabat Beton 1 : 3 : 5 Lantai
Dudukan 0.70 m3 624,977.00
7 Pekerjaan Rabat Beton 1 : 3 : 5 Tempat
Cuci 0.70 m3 624,977.00
8 Pekerjaan Plesteran Camp. 1 : 4 6.16 m2 26,724.90 9 Pekerjaan Acian dengan Semen 6.16 m2 5,557.50 10 Pekerjaan Pasangan Bak Penampungan 2
m3 1.00 unit 3,219,300.00
11 Pas.Pipa PVC 3/4" aw 12.00 m' 5,458.75 12 Kran Air 1/2" inc. install 6.00 Bh 73,000.00 13 Plampung Ø 3/4" inc. install 1.00 unit 101,200.00
J U M L A H C 2 Pek. Rangka Struktur Turbin
A Pondasi Rangka Struktur Turbin
1 Galian Tanah 36.36 m3 13,900.00
2 Urugan Tanah kembali 25.14 m3 6,662.50 3 Lantai kerja (rabat Beton 1:3;5) 3.30 m3 624,977.00 4 Beton Bertulang (1:2:3) 11.22 m3 2,623,207.50 B Fabrikasi Rangka Struktur
1 Pipa GIP Medium A Ø 3" 209.00 m 145,200.00 2 Pipa GIP Medium A Ø 1,5" 666.00 m 60,550.00 3 Plat Sepatu uk 30x30cm tebal 8mm 22.00 unit 64,616.26
4 Angkur 15mm 88.00 Bh 75,000.00
6 Pengecatan Rangka 135.58 m2 11,760.75
5 Biaya Fabrikasi dan instal rangka 875.00 m 16,740.68 J U M L A H 3 Pengadaan dan Instalsi Turbin Angin
1 Wind Turbine dia 1m (200 watt) 140.00 unit 18,200,000.00
2 Charge Controller 140.00 Bh 1,350,000.00
3 Inverter 5KW 6.00 Bh 19,800,000.00
4 Battery 100aH 20.00 Bh 1,850,000.00
5 Frame ukuran 3625x5790 (alum, t 2") 10.00 unit 2,500,000.00
J U M L A H D 4 Pengadaan Dan Instalasi Listrik
1 Pas. Kabel NFA2X 2x10mm 1,500.00 m 3,755.00 2 Tiang penyangga Gip Ø 1,5" 6 m inc
dudukan beton 20x20x60cm 30.00 btg 170,230.72
J U M L A H D
: Kel. Mariorennu : 2010
: Bulukumba
JUMLAH HARGA
5
5,098,247.45
350,000.00
1,000,000.00
750,000.00
4,125,919.95
1,000,000.00
12,324,167.40
249,935,180.00
25,380,960.00
2,379,000.00
101,600.00
277,796,740.00
799,800.00
466,800.00
149,200.00
150,000.00
130,000.00
850,000.00
610,000.00
110,400.00
3,000,000.00
8,750,000.00
752,500.00
15,768,700.00
61,612,750.56
10,248,288.25
556,000.00
148,266.67
72,565,305.48
432,432.21
267,247.51
159,756.12
229,980.24
153,320.16
122,400.00
1,530,000.00
229,980.24
367,200.00
1,530,000.00
1,530,000.00
6,552,316.49
372,683,061.97
JUMLAH HARGA
5
16,958.00
98,629.38
439,477.50
448,937.78
1,469,149.10
437,483.90
437,483.90
164,625.38
34,234.20
3,219,300.00
65,505.00
438,000.00
101,200.00
7,370,984.14
505,404.00
167,495.25
2,062,424.10
29,432,388.15
-
30,346,800.00
40,326,300.00
1,421,557.78
6,600,000.00
1,594,550.71
14,648,092.81
127,105,012.80
2,548,000,000.00
189,000,000.00
118,800,000.00
37,000,000.00
25,000,000.00
2,917,800,000.00
5,632,500.00
5,106,921.69
10,739,421.69
No Uraian Volume Satuan Harga Satuan
Harga Barang ( C ) 1.00 ea $ 1000
Harga Barang ( C ) $ 1000 ea Rp 11,000.00
Insurance ( I ) (2%) 2.00% Rp 11,000,000.00
Ongkos kirim ( F ) 20% 20.00% Rp 11,000,000.00
Bea Masuk MFN (Most Favourable Nations)
CIT * (10%) 10.00% Rp 13,420,000.00
PPN = (CIF + bea masuk) * 10% 10.00% Rp 14,762,000.00
PPh = (CIF + bea masuk) * 7.5% 7.50% Rp 14,762,000.00
Biaya kirim dari Jakarta ke Bulukumba / kg 10.00 kg 15,465.00 Biaya Instalasi (turbin ke rumah panel ,
diambil jarak rata rata 1.00 LS 350,000.00 Biaya Komisioning (pengetesan 48 Jam 1.00 LS 350,000.00
Note : $1 = Rp 11,000,-
Jumlah Material On Site dan Instalasi = A + B + C Total CIF (A)
ANALISA HARGA LUMSUM
ITEM PEKERJAAN PENGADAAN TURBIN ANGIN DAN INSTALASI
Jumlah Tagihan Pajak (B)
Jumlah Pekerjaan Lokal (C)
Total Harga 11,000,000.00 Rp
220,000.00 Rp
2,200,000.00 Rp
13,420,000.00 Rp
1,342,000.00 Rp
1,476,200.00 Rp
1,107,150.00 Rp
3,925,350.00 Rp
154,650.00 Rp
350,000.00 Rp
350,000.00 Rp
854,650.00 Rp
18,200,000.00 Rp
A. PEKERJAAN PATOK
Patok dibuat dari kayu 5/7 pjg : 50 cm dgn ujung diruncingkan : 1. 1 m2 Pengecatan : Dinding / kayu / Besi
0.2600
kg Cat Kayu / Besi @ Rp. 36,700.00 = Rp.
0.0025
oh Mandor @ Rp. 47,500.00 = Rp.
0.0700
oh Pekerja @ Rp. 30,000.00 = Rp.
Rp.
2. Biaya Pembuatan 100 Patok : 0.0250
m3 Kayu Kaso Kls. II @ Rp. 3,145,000.00 = Rp.
0.6500
m2 Pengecatan @ Rp. 11,760.75 = Rp.
0.1000
oh Mandor @ Rp. 47,500.00 = Rp.
1.0000
oh Tukang Kayu @ Rp. 45,000.00 = Rp.
1.0000
oh Pekerja @ Rp. 30,000.00 = Rp.
1.0000
ls Biaya Pemasangan @ Rp. 100,000.00 = Rp.
1.0000
ls Biaya Pengukuran @ Rp. 100,000.00 = Rp.
Rp.
Biaya Pembuatan 1 Patok : Rp.
3. Biaya Pengukuran 500 m Uiset Jalur Pipa : 1.0000
oh Mandor @ Rp. 47,500.00 = Rp.
5.0000
oh Pekerja @ Rp. 30,000.00 = Rp.
11.0000
bh Patok @ Rp. 1,452.46 = Rp.
1.0000
ls Alat Bantu @ Rp. 250,000.00 = Rp.
Biaya Pengukuran dan Pematokan Per Meter ( m1 ) : Rp.
B. PEKERJAAN PEMASANGAN PIPA
1. Pemasangan Per Batang Pipa PVC Dia. 3":
1.2600
m3 Galian Tanah Biasa @ Rp. 13,900.00 = Rp.
0.3150
m3 Urugan Pasir @ Rp. 145,915.00 = Rp.
1.0395
m3 Urugan Tanah dan Pemadatan @ Rp. 6,662.50 = Rp.
1.0000
Btg Penurunan dan Penyetelan Pipa @ Rp. 10,312.50 = Rp.
Biaya Pemas. Per meter Pipa PVC Dia. 3" : Rp.
2. Pemasangan Per Batang Pipa PVC Dia. 2" : 0.9000
m3 Galian Tanah Biasa @ Rp. 13,900.00 = Rp.
0.2700
m3 Urugan Pasir @ Rp. 145,915.00 = Rp.
0.6930
m3 Urugan Tanah dan Pemadatan @ Rp. 6,662.50 = Rp.
1.0000
Btg Penurunan dan Penyetelan Pipa @ Rp. 10,312.50 = Rp.
Biaya Pemas. Per meter Pipa PVC Dia. 2" : Rp.
C. PEMASANGAN TEE / DOP
1. Pemasangan Tee / Dop pada Pipa Dia. 100 mm dan < 100 mm : 1.0000
bh Penyetelan @ Rp. 61,200.00 = Rp.
0.0048
m3 Blok Beton @ Rp. 618,842.00 = Rp.
0.0400
m2 Bekisting Biasa @ Rp. 312,241.00 = Rp.
D. PEMASANGAN REDUCER
1. Pemasangan Reducer pada Pipa Dia. 100 mm dan < 100 mm : 1.0000
bh Penyetelan @ Rp. 61,200.00 = Rp.
0.0100
m3 Blok Beton @ Rp. 618,842.00 = Rp.
0.0400
m2 Bekisting Biasa @ Rp. 312,241.00 = Rp.
DAFTAR ANALISA HARGA SATUAN PERPIPAAN
DAFTAR ANALISA HARGA SATUAN PERPIPAAN
F. PEMASANGAN BEND 90o
1. Pemasangan Bend 90o pada Pipa Dia. 100 mm dan < 100 mm : 1.0000
bh Penyetelan @ Rp. 61,200.00 = Rp.
0.0100
m3 Blok Beton @ Rp. 618,842.00 = Rp.
0.0150
m2 Bekisting @ Rp. 312,241.00 = Rp.
G. PEMASANGAN BEND 45o ,22,5o , & 11./14o
1. Pemasangan Bend pada Pipa Dia. 100 mm dan < 100 mm : 1.0000
bh Penyetelan @ Rp. 61,200.00 = Rp.
0.0015
m3 Blok Beton @ Rp. 618,842.00 = Rp.
0.0150
m2 Bekisting @ Rp. 312,241.00 = Rp.
H PEKERJAAN PEMASANGAN, PENURUNAN DAN PENYETELAN PIPA 1. 1 BATANG ( 6 METER ) PIPA PVC
Pipa Dia. 100 mm dan < Dia. 100 mm 0.0150
oh Mandor @ Rp. 47,500.00 = Rp.
0.0800
oh Tukang Pipa @ Rp. 45,000.00 = Rp.
0.1500
oh Pekerja @ Rp. 30,000.00 = Rp.
1.0000
oh Peralatan @ Rp. 1,500.00 = Rp.
= Rp.
Biaya Pemasangan Pipa PVC dia 3/4"
1.1000
m' Pipa 3/4 @ Rp. 3,400.00 = Rp.
1.0000
Biaya penyetelan @ Rp. 1,718.75 = Rp.
PEKERJAAN PENURUNAN DAN PENYETELAN PIPA 2. 1 BATANG ( 6 METER ) PIPA GIP
Pipa Dia. 4''mm dan < Dia. 4"
0.0200
oh Mandor @ Rp. 47,500.00 = Rp.
0.7500
oh Tukang Pipa @ Rp. 45,000.00 = Rp.
2.5000
oh Pekerja @ Rp. 30,000.00 = Rp.
1.0000
oh Peralatan @ Rp. 1,500.00 = Rp.
= Rp.
I PEK. PENURUNAN / PENYAMBUNGAN FITTING (BEND/TEE/REDUCER/FLANGE SOCKET/FLANG GIL BOULT JOINT) DAN SEJENISNYA :
1. Pipa Dia. 100 mm dan < Dia. 100 mm 0.1200
oh Mandor @ Rp. 47,500.00 = Rp.
0.4000
oh Tukang Pipa @ Rp. 45,000.00 = Rp.
1.2000
oh Pekerja @ Rp. 30,000.00 = Rp.
1.0000
oh Peralatan @ Rp. 1,500.00 = Rp.
= Rp.
J
1. Pipa Dia. 100 mm dan < Dia. 100 mm 0.1200
oh Mandor @ Rp. 47,500.00 = Rp.
0.4000
oh Tukang Pipa @ Rp. 45,000.00 = Rp.
1.2000
oh Pekerja @ Rp. 30,000.00 = Rp.
1.0000
ls Peralatan @ Rp. 1,500.00 = Rp.
= Rp.
PEK. PENURUNAN / PENYAMBUNGAN FITTING (GATE VALVE /CHECK VALVE/WATER METER/BU DAN SEJENISNYA
Sehingga pekerjaanPenyetelan Pipa GIP uk < dia 100 mm untuk 1 Meter = Sehingga pekerjaan penyetelan Pipa PVC uk < dia 100 mm untuk 1 Meter =