Pekerjaan :

PEMBANGUNAN SPAM RAWAN AIR TERFASILITASI KWS. SAPTA MARGA, KAB. MALUKU TENGAH

Lokasi :

KWS. SAPTA MARGA, KAB. MALUKU TENGAH

DETAIL ENGINEERING DESIGN (DED)

Kepala Satuan Kerja Pengembangan Sistem Penyediaan Air Minum Provinsi Maluku

ANNIE L. LABOBAR, ST. MSi NIP. 19650402 199403 2 008

Lokasi :

KWS. SAPTA MARGA, KAB. MALUKU TENGAH

TAHUN ANGGARAN 2018

Disetujui Oleh :

(2)

PETA ORIENTASI SPAM BARU TA.2018

Pembangunan SPAM di Kawasan Rawan Air Kws. Sapta Marga, Kec. Tehoru

SATUAN KERJA SISTYM PENYEDIAAN AIR MINUM

PROVINSI MALUKU

SATUAN KERJA

PENGEMBANGAN SISTEM

PENYEDIAAN AIR MINUM

(3)

MESJID RENC.BRONCAPTERING KAP. 1,5 L/Det± 98 M'

AR AH TE HO RU AR AH YA PU TI

KU

KU KU KUKU

KUKUKU KUKU

SIT UA SI D ES A SA PT A M A RG A

= R EN C. B RO NC AP TE RIN G K E T E R A N G A N

= G IP Ø 10 0 m m = 2 .92 8 M ' = G IP Ø 50 m m = 1 .15 2 M ' 1 U NIT = K RA N U MU M

= G IP Ø 75 m m = 1.2 36 M ' 1 0 U NIT

ASI STE N P ER EN CA NA

LORDY. F. de Wanna, ST. MTNIP. 19730218 200801 1 008

KEPALA SATUAN KERJAPENGEMBANGAN SISTEMPENYEDIAAN AIR MINUM PROVINSIMALUKU

ANNIE . L . LABOBAR.ST,MSiNIP. 19650402 199403 2 008

P S P A M

(4)

: PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

KEGIATAN : PEMBANGUNAN SPAM DI KAWASAN RAWAN AIR KWS. SAPTA MARGA KAB. MALUKU TENGAH LOKASI : KWS. SAPTA MARGA, KAB. MALUKU TENGAH

T. ANGGARAN : 2018 NO

A. PEMBANGUNAN BRONCAPTERING = 1 UNIT Rp 100,559,848.48

B. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 50 mm = 1.152 M Rp 190,214,556.00 C. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 75 mm = 1.236 M Rp 330,990,510.48 D. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 100 mm = 2.928 M Rp 1,148,428,598.39

JUMLAH HARGA ( Rp ) URAIAN PEKERJAAN

REKAPITULASI

DETAIL ENGINEERING DESIGN (DED)

SATUAN KERJA

E. PEMBANGUNAN KRAN UMUM SISTIM CABANG = 10 UNIT Rp 47,988,510.72

Rp 1,818,182,024.07

Rp 181,818,202.41

Rp 2,000,000,226.48 Rp 2,000,000,000.00

Terbilang : Dua Milyar Rupiah,-

Harga-harga tersebut di atas sudah termasuk PPn, PPh dan Pajak-Pajak Lain sesuai ketentuan yang berlaku.

Ambon, 2017 KEPALA SATUAN KERJA

PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

ANNIE L. LABOBAR, ST. M.Si NIP. 19650420 199403 2 008 TOTAL

JUMLAH ( A + B + C + D + E ) DIBULATKAN JUMLAH PPN ( 10% )

(5)

: PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

KEGIATAN : PEMBANGUNAN SPAM DI KAWASAN RAWAN AIR KWS. SAPTA MARGA KAB. MALUKU TENGAH LOKASI : KWS. SAPTA MARGA, KAB. MALUKU TENGAH

T. ANGGARAN : 2018

HARGA JUMLAH

NO SAT VOL SATUAN HARGA

( Rp ) ( Rp )

A. PEMBANGUNAN BRONCAPTERING = 1 UNIT I. Pekerjaan Awal

1 Pembersihan Lokasi Brocaptering M2 22.50 19,406.25 436,640.63

2 Pengadaan Pemasangan Papan Nama Proyek Bh 1.00 639,328.13 639,328.13

3 Mobilisasi Demobilisasi Peralatan dan Bahan - bahan Yang Dibutuhkan Ls 1.00 35,000,000.00 35,000,000.00

4 Pengukuran dan Pemasangan Bowplak M2 4.50 458,467.63 2,063,104.31

38,139,073.06 II. Pekerjaan Tanah

1 Galian tanah keras untuk pondasi broncaptering M3 7.59 157,190.63 1,193,076.84

2 Timbunan kembali tanah bekas galian M3 1.90 62,876.25 119,307.68

3 Pas Batu Kosong M3 5.76 879,943.55 5,068,474.82

4 Urugan Kerikil Untuk Saringan ( Grafel ) M3 0.69 634,222.13 437,613.27

6,818,472.61 III. Pekerjaan pasangan Batu Kali, Plesteran dan Pengecatan

1 Pasangan pondasi batu kali camp 1 Pc : 4 Ps. M3 6.20 1,536,351.13 9,525,376.98

2 Plesteran dinding luar dan dalam broncaptering T = 15 mm camp 1 Pc : 2 Ps M2 40.16 95,838.13 3,848,859.10

3 Acian dinding luar dan dalam M2 34.95 28,577.50 998,783.63

4 Pengecetan dinding Bronkaptering M2 22.99 37,059.90 852,007.10

15,225,026.80 IV. Pekerjaan Beton

1 Pengecoran kopor Pondsi Broncaptering

- Bakesten untuk Pondasi M2 10.50 252,437.65 2,650,595.33

- Beton Mutu f'c = 7,4 Mpa (K100), Slump (12 ± 2) cm, w/c = 0,87 ( camp 1 : 2 : 3 ) M3 4.95 1,867,913.95 9,246,174.05 2 Beton tumbuk dibawah Lantai T = 5 cm

- Bakesten untuk Pondasi M2 0.38 252,437.65 95,926.31

- Beton Mutu f'c = 7,4 Mpa (K100), Slump (3-6) cm, w/c = 0,87 ( camp 1 : 3 : 5 ) M3 0.18 1,776,002.50 319,680.45 3 Pengecoran Plat lantai Broncaptering T= 20 cm

- Pembesian untuk Plat Lantai Kg 58.57 530,610.58 31,077,861.38

- Bakesten untuk Pondasi M2 1.52 252,437.65 383,705.23

- Beton Mutu f'c = 9,8 Mpa (K125), Slump (12 ± 2) cm, w/c = 0,78 ( camp 1 : 1,5 : 2,5 ) M3 0.72 1,944,618.95 1,400,125.64 URAIAN PEKERJAAN

RENCANA ANGGARAN BIAYA ( RAB )

SATUAN KERJA

- Beton Mutu f'c = 9,8 Mpa (K125), Slump (12 ± 2) cm, w/c = 0,78 ( camp 1 : 1,5 : 2,5 ) M3 0.72 1,944,618.95 1,400,125.64 4 Pengecoran Plat Dinding Broncaptering T= 15 cm

- Pembesian untuk Plat Dinding Kg 104.62 20,583.74 2,153,470.36

- Bakesten untuk Plat Dinding M2 10.80 471,816.83 5,095,621.71

- Beton Mutu f'c = 9,8 Mpa (K125), Slump (12 ± 2) cm, w/c = 0,78 ( camp 1 : 1,5 : 2,5 ) M3 0.99 1,944,618.95 1,925,172.76 5 Pengecoran Plat Penutup Broncaptering T= 10 cm

- Pembesian untuk Plat Penutup Kg 51.79 20,583.74 1,066,031.64

- Bakesten untuk Lantai M2 0.82 530,610.58 435,100.67

- Beton Mutu f'c = 7,4 Mpa (K100), Slump (12 ± 2) cm, w/c = 0,87 ( camp 1 : 2 : 3 ) M3 0.29 1,867,913.95 541,695.05 56,391,160.56 V. Pekerjaan Pengadaan / Pemasangan Pipa dan Accessories

1 Pengad / Pemas Pipa Outlet dia. 100 mm M 6.00 348,266.00 2,089,596.00

2 Pengad / Pemas Pipa Inlet dia. 100 mm M 6.00 348,266.00 2,089,596.00

3 Pengad / Pemas Pipa Overflow dia. 100 mm M 3.00 348,266.00 1,044,798.00

4 Pengad / Pemas Pipa Penguras dia. 100 mm M 3.00 348,266.00 1,044,798.00

5 Foor Valve dia. 100 mm Bh 1.00 145,000.00 145,000.00

6 Gate Valve flange dia 100 mm Bh 3.00 3,215,000.00 9,645,000.00

7 Flange Las dia.100 mm 10 K Bh 7.00 162,000.00 1,134,000.00

8 Bend Flange dia 100 mm x 90 drj Bh 1.00 295,000.00 295,000.00

9 Bend Flange dia 100 mm x 45 drj Bh 2.00 295,000.00 590,000.00

10 Karet paking dia 100 mm Bh 7.00 53,000.00 371,000.00

18,448,788.00 VI. Pekerjaan Lain -Lain

1 Pipa Vent dia. 50 mm Unit 1.00 420,000.00 420,000.00

2 Menhole Plat baja 60 X 60 Cm Unit 1.00 782,600.00 782,600.00

3 Gembok Bh 1.00 33,300.00 33,300.00

4 Baut 5/8 panjang 7 cm Bh 72.00 10,000.00 720,000.00

5 Ring Baut Bh 144.00 4,000.00 576,000.00

6 Biaya pengelasan Flange dia 100 mm Bh 7.00 135,400.00 947,800.00

3,479,700.00

A. PENGUMPULAN

I. Pekerjaan Awal Rp 38,139,073.06

II. Pekerjaan Tanah Rp 6,818,472.61

III. Pekerjaan pasangan Batu Kali, Plesteran dan Pengecatan Rp 15,225,026.80

IV. Pekerjaan Beton Rp 18,448,788.00

V. Pekerjaan Pengadaan / Pemasangan Pipa dan Accessories Rp 18,448,788.00

VI. Pekerjaan Lain -Lain Rp 3,479,700.00

Rp 100,559,848.48

JUMLAH

(6)

HARGA JUMLAH

NO SATUAN VOLUME SATUAN HARGA

( Rp ) ( Rp )

B. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 50 mm = 1.152 M I. Pekerjaan Pengadaan Pipa GIP dia 50 mm Dan Accessories

a

1 Pipa GIP Kls Medium Dia 50 mm M 1,152.00 97,300.00 112,089,600.00

b Pengadaan Accessories Pipa

1 Socket GIP dia 50 mm Bh 192.00 63,000.00 12,096,000.00

2 Bend Socket Gip dia 50 mm x 45 drj Bh 4.00 103,000.00 412,000.00

3 Bend Socket Gip dia 50 mm x 90 drj Bh 5.00 103,000.00 515,000.00

4 Tee Socket GIP dia 50 mm X 50 mm Bh 5.00 143,000.00 715,000.00

5 Nepel GIP dia 50 mm Bh 4.00 68,000.00 272,000.00

6 Water Mur GIP dia 50 mm Bh 6.00 126,000.00 756,000.00

7 Gate Valve Socket dia 50 mm Bh 2.00 1,142,000.00 2,284,000.00

8 Dop Socket GIP dia 50 mm Bh 14.00 78,000.00 1,092,000.00

9 CLamp Sadle GIP dia 50 mm x 20 mm Bh 14.00 98,000.00 1,372,000.00

10 StreBox dia 50 mm Bh 2.00 125,500.00 251,000.00

19,765,000.00 II. Pekerjaan Pemasangan Pipa dan Accessories

Pemasangan pipa lengkap dengan Accessories termasuk pengalian tanah, pengecatan serta perbaikan kembali semua kebocoran sesuai gambar spesifikasi teknis

1 Galian Tanah Biasa Untuk Pemasangan Pipa M3 100.80 70,798.66 7,136,504.68

2 Urugan Tanah Kembali M3 97.23 62,876.25 6,113,382.34

3 Pemasangan Pipa GIP Kls Medium Dia 50 mm ( Termasuk Galian Tanah ) M 1,152.00 38,950.50 44,870,976.00

4 Pengecoran StreBox dia 50 mm Camp 1 Pc : 2 Ps : 3 Kr M3 0.13 1,867,913.95 239,092.99

58,359,956.00

B. PENGUMPULAN

I. Pekerjaan Pengadaan Pipa GIP dia 50 mm Dan Accessories Rp 131,854,600.00

II. Pekerjaan Pemasangan Pipa dan Accessories Rp 58,359,956.00

RENCANA ANGGARAN BIAYA ( RAB )

URAIAN PEKERJAAN

Pengadaan Pipa

Rp 190,214,556.00

JUMLAH

(7)

HARGA JUMLAH

NO SATUAN VOLUME SATUAN HARGA

( Rp ) ( Rp )

C. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 75 mm = 1.236 M I. Pekerjaan Pengadaan Pipa GIP dia 75 mm Dan Accessories

a

1 Pipa GIP Kls Medium Dia 75 mm M 1,236.00 161,400.00 199,490,400.00

b Pengadaan Accessories Pipa

1 Socket GIP dia 75 mm Bh 206.00 90,000.00 18,540,000.00

2 Tee Socket GIP dia 75 mm X 75 mm Bh 1.00 169,000.00 169,000.00

3 Tee Socket GIP dia 75 mm X 50 mm Bh 4.00 159,000.00 636,000.00

4 Reducer Socket GIP dia 75 mm x 50 mm Bh 2.00 95,000.00 190,000.00

5 Gate Valve Flange dia 75 mm Bh 2.00 2,756,000.00 5,512,000.00

6 Flange Las dia.75 mm 10 K Bh 4.00 131,000.00 524,000.00

7 Baut 5/8 panjang 7 cm Bh 32.00 10,000.00 320,000.00

8 Ring Baut Bh 64.00 4,000.00 256,000.00

9 Karet Paking dia 75 mm Bh 4.00 50,000.00 200,000.00

10 Nepel GIP dia 75 mm Bh 3.00 87,000.00 261,000.00

11 Gilbaut Joing GIP dia 75 mm Bh 1.00 220,000.00 220,000.00

12 CLamp Sadle GIP dia 75 mm x 20 mm Bh 2.00 118,000.00 236,000.00

13 StreBox dia 75 mm Bh 2.00 145,500.00 291,000.00

27,355,000.00 II. Pekerjaan Pemasangan Pipa dan Accessories

Pemasangan pipa lengkap dengan Accessories termasuk pengalian tanah, pengecatan serta perbaikan kembali semua kebocoran sesuai gambar spesifikasi teknis

1 Galian Tanah Biasa Untuk Pemasangan Pipa M3 148.32 70,798.66 10,500,856.88

2 Urugan Tanah Kembali M3 140.41 62,876.25 8,828,429.11

3 Pemasangan Pipa GIP Kls Medium Dia 75 mm ( Termasuk Galian Tanah ) M 1,236.00 68,163.38 84,249,931.50

4 Biaya pengelasan Flange dia 75 mm Bh 4.00 81,700.00 326,800.00

5 Pengecoran StreBox dia 75 mm Camp 1 Pc : 2 Ps : 3 Kr M3 0.13 1,867,913.95 239,092.99

104,145,110.48

C. PENGUMPULAN

I. Pekerjaan Pengadaan Pipa GIP dia 75 mm Dan Accessories Rp 226,845,400.00

RENCANA ANGGARAN BIAYA ( RAB )

Pengadaan Pipa

URAIAN PEKERJAAN

I. Pekerjaan Pengadaan Pipa GIP dia 75 mm Dan Accessories Rp 226,845,400.00

II. Pekerjaan Pemasangan Pipa dan Accessories Rp 104,145,110.48

Rp 330,990,510.48

JUMLAH

(8)

HARGA JUMLAH

NO SAT VOL SATUAN HARGA

( Rp ) ( Rp )

D. PENGAD / PEMAS PIPA GIP SERTA ACCESSORIES DIA 100 mm = 2.928 M I. Pekerjaan Pengadaan Pipa GIP dia 100 mm Dan Accessories

a

1 Pipa GIP Kls Medium Dia 100 mm M 2,928.00 235,100.00 688,372,800.00

b Pengadaan Accessories Pipa

1 Flange Las dia 100 mm Bh 208.00 162,000.00 33,696,000.00

2 Socket Gip dia 100 mm Bh 388.00 101,000.00 39,188,000.00

3 Bend Flange dia 100 mm x 90 drj Bh 4.00 295,000.00 1,180,000.00

4 Bend Flange dia 100 mm x 45 drj Bh 12.00 295,000.00 3,540,000.00

5 Bend Flange dia 100 mm x 22,5 drj Bh 8.00 295,000.00 2,360,000.00

6 Bend Socket GIP dia 100 mm x 90 drj Bh 2.00 153,000.00 306,000.00

7 Bend Socket GIP dia 100 mm x 45 drj Bh 6.00 153,000.00 918,000.00

8 Bend Socket GIP dia 100 mm x 22.5 drj Bh 4.00 153,000.00 612,000.00

9 Tee Socket GIP dia 100 mm X 50 mm Bh 6.00 159,000.00 954,000.00

10 Tee Socket GIP dia 100 mm X 75 mm Bh 3.00 169,000.00 507,000.00

11 Tee Flange GIP dia 100 mm X 100 mm Bh 3.00 214,000.00 642,000.00

12 Gate Valve Flange dia 100 mm Bh 4.00 3,215,000.00 12,860,000.00

13 Gilbaut Joing GIP dia 100 mm Bh 2.00 276,000.00 552,000.00

14 Air Relief dia 20 mm Bh 2.00 249,000.00 498,000.00

15 CLamp Sadle GIP dia 100 mm x 20 mm Bh 2.00 139,000.00 278,000.00

16 Reducer Socket GIP dia 100 mm x 75 mm Bh 1.00 159,000.00 159,000.00

17 Baut 5/8 panjang 7 cm Bh 832.00 10,000.00 8,320,000.00

18 Ring Baut Bh 1,664.00 4,000.00 6,656,000.00

19 Karet Paking dia 100 mm Bh 104.00 53,000.00 5,512,000.00

20 StreBox dia 100 mm Bh 2.00 163,600.00 327,200.00

119,065,200.00 II. Pekerjaan Mobilisasi Pipa Transmisi

1 Biaya Pikul Pipa Dia 100 mm Sejauh 300 M - 1.002 M Staf 117.00 55,000.00 6,435,000.00

2 Biaya Pikul Pipa Dia 100 mm Sejauh 1.002 M - 2.004 M Staf 167.00 70,000.00 11,690,000.00

3 Biaya Pikul Pipa Dia 100 mm Sejauh 2.004 M - 2.886 M Staf 147.00 85,000.00 12,495,000.00

30,620,000.00

RENCANA ANGGARAN BIAYA ( RAB )

URAIAN PEKERJAAN

Pengadaan Pipa

30,620,000.00 III. Pekerjaan Pemasangan Pipa dan Accessories

Pemasangan pipa lengkap dengan Accessories termasuk pengecatan serta perbaikan kembali semua kebocoran sesuai gambar spesifikasi teknis

1 Galian Tanah Biasa Untuk Pemasangan Pipa M3 395.28 70,798.66 27,985,293.34

2 Urugan Tanah Kembali M3 367.46 62,876.25 23,104,758.33

3 Pemas Pipa GIP Kls Medium Dia 100 mm ( Termasuk Galian Tanah ) M 2,928.00 77,901.00 228,094,128.00

4 Biaya pengelasan Flange dia 100 mm Bh 208.00 135,400.00 28,163,200.00

5 Pekerjaan Beton untuk penyanga Pipa Camp. 1 Pc : 2 Ps : 3 Kr M3 1.49 1,867,913.95 2,784,125.74

6 Pengecoran StreBox dia 75 mm Camp 1 Pc : 2 Ps : 3 Kr M3 0.13 1,867,913.95 239,092.99

310,370,598.39

D. PENGUMPULAN

I. Pekerjaan Pengadaan Pipa GIP dia 100 mm Dan Accessories Rp 807,438,000.00

II. Pekerjaan Mobilisasi Pipa Transmisi Rp 30,620,000.00

III. Pekerjaan Pemasangan Pipa dan Accessories Rp 310,370,598.39

Rp 1,148,428,598.39 JUMLAH

(9)

HARGA JUMLAH

NO VOLUME SATUAN HARGA

( Rp ) ( Rp )

E. PEMBANGUNAN KRAN UMUM SISTIM CABANG = 10 UNIT I. Pekerjaan Persiapan

1 Pengukuran dan Pemasangan Bowplak M2 2.89 458,467.63 1,324,971.44

II. Pekerjaan Tanah

1 Galian Tanah Biasa M3 4.50 70,798.66 318,593.96

2 Timbunan Tanah Kembali M3 1.13 62,876.25 71,050.16

3 Urugan Pasir Dibawah Pondasi M3 0.75 556,502.25 417,376.69

807,020.81 III. Pekerjaan Pas Batu Kali, Beton, Plesteran dan Pengecatan

Pas Batu Kali Untuk Pondasi Kran Umum Camp 1 Pc : 4 Ps M3 6.00 1,536,351.13 9,218,106.75

1 Pengecoran Tiang Kran Umum

- Bakesten untuk Kolom M2 8.00 465,204.33 3,721,634.60

- Pembesian untuk Tiang Kran Umum Kg 21.00 20,583.74 432,258.44

- Pembesian untuk Behel Tiang Kran Umum Kg 7.89 20,583.74 162,405.67

- Beton Mutu f'c = 7,4 Mpa (K100), Slump (12 ± 2) cm, w/c = 0,87 ( camp 1 : 2 : 3 ) M3 1.60 1,867,913.95 2,988,662.32 2 Pengecoran Beton Untuk Saluran Air dan Rabat

- Bakesten untuk Pondasi M2 9.60 252,437.65 2,423,401.44

- Beton Mutu f'c = 7,4 Mpa (K100), Slump (12 ± 2) cm, w/c = 0,87 ( camp 1 : 2 : 3 ) M3 1.21 1,867,913.95 2,260,175.88

3 Plesteran Karan Umum Camp 1 Pc : 4 Ps M2 76.90 86,217.23 6,630,104.60

4 Pekerjaan Pengacian Tianga Kran Umum (1 lapis plamur / Aci) M2 1.60 28,577.50 45,724.00

5 Pengecetan Kran Umum M2 21.20 37,059.90 785,669.88

28,668,143.58 IV. Pekerjaan Pengadaan / Pemasangan Pipa dan Accessories

1 Pengadaan / Pemasangan Pipa GIP Medium A dia 20 mm M 120.00 57,886.46 6,946,374.90

2 Tee Socket GIP dia 20 mm Bh 10.00 38,700.00 387,000.00

3 Kney GIP dia 20 mm Bh 20.00 38,700.00 774,000.00

4 Nepel GIP dia 20 mm Bh 10.00 43,000.00 430,000.00

5 Water Mur GIP dia 20 mm Bh 10.00 40,800.00 408,000.00

6 Socket GIP 20 mm Bh 40.00 32,200.00 1,288,000.00

7 Reducer Socket GIP dia 20 mm x 13 mm Bh 20.00 35,000.00 700,000.00

8 Stop Kran Handel dia 13 mm ( merk Onda ) Bh 20.00 53,000.00 1,060,000.00

9 Gate Valve Socket dia 20 mm Bh 10.00 194,500.00 1,945,000.00

13,938,374.90 V. Pekerjaan Akhir ( Commisioning Test )

1 Uji Coba dan Perbaikan Kembali Ls 1.00 1,750,000.00 1,750,000.00

RENCANA ANGGARAN BIAYA ( RAB )

SATUAN URAIAN PEKERJAAN

1 Uji Coba dan Perbaikan Kembali Ls 1.00 1,750,000.00 1,750,000.00

2 Pembersihan akhir Ls 1.00 1,500,000.00 1,500,000.00

3,250,000.00

E. PENGUMPULAN

I. Pekerjaan Persiapan Rp 1,324,971.44

II. Pekerjaan Tanah Rp 807,020.81

III. Pekerjaan Pas Batu Kali, Beton, Plesteran dan Pengecatan Rp 28,668,143.58

IV. Pekerjaan Pengadaan / Pemasangan Pipa dan Accessories Rp 13,938,374.90

V. Pekerjaan Akhir ( Commisioning Test ) Rp 3,250,000.00

Rp 47,988,510.72

JUMLAH

Referensi

Dokumen terkait

Kepala Badan Layanan Umum Sistem Penyediaan Air Minum (BLU SPAM) adalah Kepala Badan Layanan Umum Sistem Penyediaan Air Minum Kabupaten Musi Rawas yang berada dibawah Bupati

Untuk mendukung pelaksanaan Pengembangan Sistem Penyediaan Air Minum (SPAM) seperti yang diharapkan, diperlukan suatu penyediaan/pembangunan jaringan air bersih/air

Pemasangan pipa lengkap dengan accessories,termasuk penggalian tanah, urugan pasir,timbunan kembali,perbaikan akibat galian,peyeberangan pipa pada,jalan/sungai,pengecatan

menghubungkan antara satu daerah tujuan wisata dengan daerah asal wisatawan, baik dalam bentuk sarana transportasi berjadwal (scheduled.. IV - 9 transport) ataupun

Pemasangan pipa lengkap dengan accessories,termasuk penggalian tanah, urugan pasir,timbunan kembali,perbaikan akibat galian,peyeberangan pipa pada,jalan/sungai,pengecatan

Pemasangan pipa lengkap dengan accessories,termasuk penggalian tanah, urugan pasir,timbunan kembali,perbaikan akibat galian,peyeberangan pipa pada,jalan/sungai,pengecatan

Pemasangan pipa lengkap dengan Accessories termasuk penggalian tanah urugan pasir, timbunan kembali,perbaikan akibat galian,penyeberangan pipa pada jalan/sungai,pengecatan dan