DETAIL ENGINEERING DESIGN (DED)

N/A
N/A
Protected

Academic year: 2021

Membagikan "DETAIL ENGINEERING DESIGN (DED)"

Copied!
9
0
0

Teks penuh

(1)

`

DETAIL ENGINEERING DESIGN (DED)

Pekerjaan :

PEMBANGUNAN SPAM KAWASAN RAWAN AIR KWS. TIHUANA KAB. MALUKU TENGAH

Lokasi :

KWS. TIHUANA KAB. MALUKU TENGAH

Disetujui Oleh :

Kepala Satuan Kerja Pengembangan Sistem

Penyediaan Air Minum Provinsi Maluku

ANNIE L. LABOBAR, ST. MSi

NIP. 19650402 199403 2 008

KWS. TIHUANA KAB. MALUKU TENGAH

(2)

PETA ORIENTASI SPAM BARU TA.2018

Pemb. SPAM Di Kawasan Rawan Air Kws. Tihuana, Kec. Seram Utara Timur Seti

SATUAN KERJA SISTYM

PENYEDIAAN AIR MINUM

PROVINSI MALUKU

SATUAN KERJA SISTEM

PENYEDIAAN AIR MINUM

(3)

BR O N CA PT ER IN G K AP .5 L /D ET EL V ± 1 20 m ' K ET ER A N GA N = R EN C. B RO N CA PT ER IN G = R ES EV O IR K AP . 1 00 m 3 1 U N IT 1 U N IT = G IP ∅ 1 00 m m = 2 .4 00 M ' = G IP ∅ 1 50 m m = 1 .2 00 M ' 1 U N IT R ES EV O IR K AP . 1 00 m 3 = G IP ∅ 7 5 m m = 2 .5 32 M ' AS IS TE N P ER EN CA NA L O R D Y . F . d e W a n n a , S T . M T N IP . 1 9 7 3 0 2 1 8 2 0 0 8 0 1 1 0 0 8 K E P A L A S A T U A N K E R J A P E N G E M B A N G A N S IS T E M P E N Y E D IA A N A IR M IN U M P R O V IN S I M A L U K U A N N IE . L . L A B O B A R .S T ,M S i N IP . 1 9 6 5 0 4 0 2 1 9 9 4 0 3 2 0 0 8

P

SPA

M

(4)

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

PEKERJAAN : PEMBANGUNAN SPAM DI KAWASAN RAWAN AIR KWS. TIHUANA, KAB. MALUKU TENGAH LOKASI : KWS. TIHUANA, KAB. MALUKU TENGAH

TAHUN ANGG. : 2016

JUMLAH HARGA ( Rp. ) I. PEMBANGUNAN BRONCAPTERING KAP. 5 L/Det = 1 UNIT Rp. 121,559,072.94 II. PEMBANGUNAN RESERVOIR KAP. 100 M3 - 1 Unit Rp. 322,400,043.24 III. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 150 MM Sep. 1.200 M' Rp. 1,398,475,154.37 IV. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 100 MM Sep. = 2.400 M' Rp. 1,217,642,861.24

REKAPITULASI

DETAIL ENGINEERING DESIGN (DED)

NO URAIAN PEKERJAAN

V. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 75 MM Sep. = 2.532 M' Rp. 1,030,832,586.73 4,090,909,718.52 409,090,971.85 Rp. 4,500,000,690.38 Rp. 4,500,000,000.00

Harga-harga tersebut di atas sudah termasuk PPn, PPh dan Pajak-Pajak Lain sesuai ketentuan yang berlaku.

Ambon, 2017

KEPALA SATUAN KERJA

PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

ANNIE L. LABOBAR, ST. M.Si

NIP. 19650420 199403 2 008

TERBILANG : EMPAT MILYAR LIMA RATUS JUTA RUPIAH,-JUMLAH

JUMLAH PPN 10% DIBULATKAN

(5)

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROVINSI MALUKU

PEKERJAAN : PEMBANGUNAN SPAM DI KAWASAN RAWAN AIR KWS. TIHUANA, KAB. MALUKU TENGAH

LOKASI : KWS. TIHUANA, KAB. MALUKU TENGAH

TAHUN ANGG. : 2016

HARGA JUMLAH

SATUAN HARGA

( Rp.) ( Rp.)

I. PEMBANGUNAN BRONCAPTERING KAP. 5 L/Det = 1 UNIT

1 Pekerjaan Persiapan

1 Pembersihan Seluruh Lokasi Pekerjaan LS 1.00 2,000,000.00 2,000,000.00

2 Pengukuran dan Pemasangan Bouwplak LS 1.00 750,000.00 750,000.00

3 Mobilisasi dan Demobilisasi Peralatan dan Bahan LS 1.00 36,579,000.00 36,579,000.00

39,329,000.00

2 Pekerjaan Tanah

1 Galian Tanah M3 10.36 25,920.00 268,531.20

2 Timbunan Tanah Kembali M3 2.09 12,426.00 25,970.34

3 Timbunan Pasir diBawah Pondasi M3 2.80 529,560.00 1,482,768.00

1,777,269.54

3 Pek. Pasangan Batu Kali, Beton Plesteran dan Pengecatan

1 Pasangan Batu Kosong M3 4.00 486,000.00 1,944,000.00

2 Pasang Batu Kali camp. 1pc : 4ps M3 8.37 980,849.00 8,209,706.13

3 Pengecoran Slof, Kolom dan Rring balok Camp 1 : 1,5 : 2,5 ( 110 kg/M3 ) M3 0.90 7,098,675.26 6,388,807.73

4 Pengecoran Dinding Camp, 1 : 1,5 : 2,5 ( 110 Kg / M3 ) M3 3.11 7,098,675.26 22,083,978.73

5 Pengecoran Lantai Camp 1 : 1,5 : 2,5 ( 85 kg/M3 ) M3 1.76 5,981,225.26 10,513,199.64

6 Pengecoran Plat Penutup Camp 1 : 2 : 3 ( 85 kg/M3 ) M3 1.16 5,981,225.26 6,938,221.30

7 Beton Rabat camp 1pc : 3ps : 5kr M3 0.78 1,452,846.00 1,133,219.88

8 Plesteran Dinding Camp : 1pc : 3ps M2 119.00 31,512.90 3,750,035.10

9 Acian Dinding luar dan dalam bak M2 72.69 14,845.00 1,079,083.05

10 Pengecatan Broncatering M2 33.12 33,702.00 1,116,210.24

63,156,461.81

4 Pek. Pengadaan Pemasangan Pipa dan Accessories

1 Pipa Inlet dan Outlet GIP Medium dia 150 MM M 6.00 533,577.51 3,201,465.05

VOL

RENCANA ANGGARAN BIAYA (RAB)

No. URAIAN PEKERJAAN SAT

4 Pek. Pengadaan Pemasangan Pipa dan Accessories

1 Pipa Inlet dan Outlet GIP Medium dia 150 MM M 6.00 533,577.51 3,201,465.05

2 Pipa Penguras dan Overflow GIP dia 100 mm M 6.00 377,479.42 2,264,876.54

3 Bend Flange GIP dia 100 mm x 90 drj Bh 2.00 210,000.00 420,000.00

4 Bend Flange GIP dia 100 mm x 45 drj Bh 2.00 210,000.00 420,000.00

5 Flange Las GIP dia 100 mm Bh 4.00 180,000.00 720,000.00

6 Gate Valve Flange dia 150 mm Bh 2.00 4,500,000.00 9,000,000.00

7 Paking Karet dia 150 mm Bh 2.00 45,000.00 90,000.00

8 Baut dan Moer dia 5/8" Bh 80.00 6,000.00 480,000.00

16,596,341.60

5 Pekerjaan Lain - lain

1 Manhole Plat = 3 mm 60 x 60 cm Unit 1.00 500,000.00 500,000.00

3 Pipa Vent dia 50 mm Unit 1.00 200,000.00 200,000.00

700,000.00

I. PENGUMPULAN

PEMBANGUNAN BRONCAPTERING KAP. 5 L/Det = 1 UNIT

1 Pekerjaan Persiapan Rp. 39,329,000.00

2 Pekerjaan Tanah Rp. 1,777,269.54

3 Pek. Pasangan Batu Kali, Beton Plesteran dan Pengecatan Rp. 63,156,461.81

4 Pek. Pengadaan Pemasangan Pipa dan Accessories Rp. 16,596,341.60

5 Pekerjaan Lain - lain Rp. 700,000.00

(6)

HARGA JUMLAH

SATUAN HARGA

( Rp.) ( Rp.)

II. PEMBANGUNAN RESERVOIR KAP. 100 M3 - 1 Unit

1 Pekerjaan Persiapan

1 Pengukuran dan Pemasangan Bouwplank LS 1.00 750,000.00 750,000.00

750,000.00

2 Pekerjaan Tanah

1 Galian Tanah Pond, Reservoir & Rumah Pengaman Gate Valve M3 23.51 25,000.00 587,650.00

2 Urugan Tanah Kembali M3 6.58 11,985.00 78,861.30

3 Urugan Pasir Dibawah Lantai Pondasi M3 4.79 407,250.00 1,949,558.48

2,616,069.78

3 Pekerjaan Pasangan Batu Kali / Karang & Batu Bata

1 Pas, Pondasi Batu Kali/Karang camp : 1pc : 4ps M3 25.66 740,871.00 19,012,231.60

2 Pas, Batu Bata Pengaman Rumah Gate Valve camp : 1pc : 4ps M3 2.20 740,871.00 1,628,434.46

3 Pas, Ventilasi Batu Angin 25 x 25 Cm Camp : 1pc : 4ps Bh 11.20 25,000.00 280,000.00

20,920,666.06

4 Pekerjaan Beton

1 Beton Tumbuk dibawah Lantai Reservoir, Rumah Pengaman Camp : 1 : 3 : 5 M3 12.00 1,127,354.00 13,528,248.00

2 Slof , Ring Balok dan Kolom Reservoir Camp : 1 : 1.5 : 2.5 ( 168 Kg/M3 ) M3 3.20 9,317,262.16 29,815,238.91

3 Pengecoran Plat Lantai Reservoir Camp : 1 : 1.5 : 2.5 ( 97 Kg/M3 ) M3 6.20 6,179,914.16 38,315,467.79

4 Pengecoran Plat Dinding Reservoir Camp : 1 : 1.5 : 2. 5 ( 120 Kg/M3 ) M3 14.06 7,196,238.16 101,172,631.92

5 Pengecoran Plat Penutup Reservoir Camp : 1 : 2 : 3 (168 kg/M3 ) M3 7.84 9,317,262.16 73,000,749.02

255,832,335.64

5 Pekerjaan Plesteran, Acian dan Pengecatan

1 Plesteran Dinding Luar, Dalam, Lantai & Plat Penutup Camp : 1pc : 3ps M2 304.57 20,990.50 6,393,076.59

2 Acian dinding Luar dan Dalam Reservoir M2 287.63 14,455.00 4,157,691.65

3 Pengecetan Diding Luar Reservoir dengan cat Auaprof 2x M2 207.49 32,915.00 6,829,665.01

17,380,433.25

6 Pekerjaan Pengadaan Pemasangan Pipa GIP dan Accesories

1 Pipa Inlet dia 100 MM M 6.00 398,967.57 2,393,805.43

2 Pipa Overflow & Penguras dia 100 MM M 6.00 377,479.42 2,264,876.54

3 Pipa Outlet dia 100 mm M 6.00 377,479.42 2,264,876.54

4 Tee GIP dia 100 mm x 100 mm Bh 1.00 195,000.00 195,000.00

No. URAIAN PEKERJAAN SAT VOL

3 Pipa Outlet dia 100 mm M 6.00 377,479.42 2,264,876.54

4 Tee GIP dia 100 mm x 100 mm Bh 1.00 195,000.00 195,000.00

5 Gate Valve Flange dia 100 mm Bh 2.00 3,000,000.00 6,000,000.00

6 Flange Las dia 100 mm Bh 4.00 180,000.00 720,000.00

7 Bend Socket Gip dia 100 mm x 90 drj Bh 2.00 210,000.00 420,000.00

8 Bend Socket Gip dia 100 mm x 45 drj Bh 2.00 210,000.00 420,000.00

9 Pipa vent dia 50 mm Unit 1.00 200,000.00 200,000.00

10 Kunci Gembok Bh 1.00 35,000.00 35,000.00

11 Pembuatan tangga kontrol Cor Besi Beton dia 22 mm Unit 1.00 1,000,000.00 1,000,000.00

12 Pembuatan manhole 60 cm x 60 cm Unit 4.00 500,000.00 2,000,000.00

17,913,558.51

7 Pekerjaan Kayu dan Pengecatan

1 Kusen Pintu Kayu Kls I Uk. 6 / 12 M3 0.16 4,750,000.00 760,000.00

2 Pintu Lapis Teakwood 3 mm M2 11.90 385,000.00 4,581,500.00

3 Kunci Tanam Dua Slag Bh 2.00 134,000.00 268,000.00

4 Enges Pintu 4" Psng 6.00 23,500.00 141,000.00

5 Pegecatan Kusen Pintu, Daun Pintu M2 11.04 112,000.00 1,236,480.00

6,986,980.00

1 PENGUMPULAN

PEMBANGUNAN RESERVOIR KAP. 100 M3 - 1 Unit

1 Pekerjaan Persiapan RP. 750,000.00

2 Pekerjaan Tanah RP. 2,616,069.78

3 Pekerjaan Pasangan Batu Kali / Karang & Batu Bata RP. 20,920,666.06

4 Pekerjaan Beton RP. 255,832,335.64

5 Pekerjaan Plesteran, Acian dan Pengecatan RP. 17,380,433.25

6 Pekerjaan Pengadaan Pemasangan Pipa GIP dan Accesories RP. 17,913,558.51

7 Pekerjaan Kayu dan Pengecatan RP. 6,986,980.00

JUMLAH : RP. 322,400,043.24

(7)

HARGA JUMLAH

SATUAN HARGA

( Rp.) ( Rp.)

III. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 150 MM Sep. 1.200 M'

1 PENGADAAN PIPA GIP DIA 150 MM DAN ACCESSORIES 1,102,821,300.00

a PENGADAAN PIPA

- Pipa GIP Medium A Dia. 150 mm M' 2,160.00 432,000.00 933,120,000.00

933,120,000.00

b PENGADAAN ACCESSORIES

- Klemp saddle GIP dia. 150 x 20 mm Ut. Air Valve Bh 3.00 137,100.00 411,300.00

- Flange Las dia. 150 mm Bh 720.00 176,000.00 126,720,000.00

- Ring Baut Ukuran 5/8" 150 mm Bh 3,600.00 7,500.00 27,000,000.00

- Karet Paking dia 150 mm Bh 360.00 37,000.00 13,320,000.00

- Reducer GIP dia. 150 x 100 mm Bh 2.00 450,000.00 900,000.00

- Bend Flanges Gip dia 150 mm x 90 drj Bh 2.00 225,000.00 450,000.00

- Bend Flanges Gip dia 150 mm x 45 drj Bh 2.00 225,000.00 450,000.00

- Bend Flanges Gip dia 150 mm x 22.5 drj Bh 2.00 225,000.00 450,000.00

169,701,300.00

2 PEMASANGAN PIPA DAN ACCESSORIES

Pemasangan pipa lengkap dengan Accessories termasuk penggalian tanah urugan pasir, timbunan kembali,perbaikan akibat galian,penyeberangan pipa pada jalan/sungai,pengecatan dan serta perbaikan kembali

semua kebocoran sesuai gambar spesifikasi teknis .

- Pemasangan Pipa GIP dia. 150 mm M' 2,160.00 101,577.51 219,407,419.44

219,407,419.44

3 PEKERJAAN LAIN - LAIN

- Pek Box Pengaman Gate Valve Beton Tumbuk camp. 1:2:3 M3 3.81 1,114,901.00 4,246,434.93

- Biaya Pengelasan Flangs dia. 150 mm Bh 720.00 100,000.00 72,000,000.00

76,246,434.93

III. PENGUMPULAN

PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 150 MM Sep. 1.200 M'

1,102,821,300.00 VOL

No. URAIAN PEKERJAAN SAT

1 PENGADAAN PIPA GIP DIA 150 MM DAN ACCESSORIES Rp.

2 PEMASANGAN PIPA DAN ACCESSORIES Rp.

3 PEKERJAAN LAIN - LAIN Rp.

JUMLAH : Rp. PEMBULATAN : Rp. 1,102,821,300.00 219,407,419.44 76,246,434.93 1,398,475,154.37 1,398,475,000.00

(8)

HARGA JUMLAH

SATUAN HARGA

( Rp.) ( Rp.)

IV. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 100 MM Sep. = 2.400 M'

1 PENGADAAN PIPA GIP DIA 100 MM DAN ACCES 960,449,500.00

a - Pipa GIP Medium A Dia. 100 mm M 2,790.00 310,000.00 864,900,000.00

864,900,000.00

b PENGADAAN ACCESSORIES

- Socket GIP dia. 100 mm Bh 465.00 93,000.00 43,245,000.00

- Gate Valve Flanges dia. 100 mm Bh 10.00 3,000,000.00 30,000,000.00

- Bend GIP dia 100 mm X 90 drt Bh 20.00 203,250.00 4,065,000.00

- Bend GIP dia 100 mm X 45 drt Bh 20.00 203,250.00 4,065,000.00

- Bend GIP dia 100 mm X 22.5 drt Bh 20.00 203,250.00 4,065,000.00

- Reduser Socket GIP dia. 100 X 75 mm Bh 15.00 195,700.00 2,935,500.00

- Watermur GIP dia. 100 mm Bh 15.00 167,000.00 2,505,000.00

- Gilbout Joint GIP dia. 100 mm Bh 8.00 173,000.00 1,384,000.00

- Clem Sadle 100 mm x 3/4" Bh 6.00 152,500.00 915,000.00

- Air Valve 100 mm x 3/4" Bh 6.00 225,000.00 1,350,000.00

- Nipple GIP dia. 100 mm Bh 6.00 170,000.00 1,020,000.00

95,549,500.00

2 PEMASANGAN PIPA DAN ACCESSORIES

Pemasangan pipa lengkap dengan Accessories termasuk penggalian tanah urugan pasir, timbunan kembali,perbaikan akibat galian,penyeberangan pipa pada jalan/sungai,pengecatan dan serta perbaikan kembali

semua kebocoran sesuai gambar spesifikasi teknis .

- Pemasangan Pipa GIP dia. 100 mm

M 2,790.00 88,967.57 248,219,523.09

248,219,523.09

3 PEKERJAAN LAIN - LAIN

- Pek Beton Penyangga Pipa camp. 1:2:3 M3 8.05 1,114,901.00 8,973,838.15

8,973,838.15

SAT VOL

No. URAIAN PEKERJAAN

8,973,838.15

IV. PENGUMPULAN

PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 100 MM Sep. = 2.400 M'

1 PENGADAAN PIPA GIP DIA 100 MM DAN ACCES Rp.

2 PEMASANGAN PIPA DAN ACCESSORIES Rp.

3 PEKERJAAN LAIN - LAIN Rp.

JUMLAH : Rp.

8,973,838.15 960,449,500.00 248,219,523.09

(9)

HARGA JUMLAH

SATUAN HARGA

( Rp.) ( Rp.)

V. PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 75 MM Sep. = 2.532 M'

1 PENGADAAN PIPA GIP DIA 75 MM DAN ACCESSORIES 759,348,800.00

a PENGADAAN PIPA

- Pipa GIP dia.75 mm M 3,630.00 194,500.00 706,035,000.00

706,035,000.00

b PENGADAAN ACCESSORIES

- Socket Gip dia 75 mm Bh 605.00 75,000.00 45,375,000.00

- Gate Valve GIP dia. 75 mm Bh 2.00 2,000,000.00 4,000,000.00

- Reducer GIP dia.75 mm x 50 mm Bh 4.00 102,500.00 410,000.00

- Bend GIP dia.75 mm x 90 drj Bh 8.00 130,000.00 1,040,000.00

- Bend GIP dia.75 mm x 45 drj Bh 8.00 130,000.00 1,040,000.00

- Tee GIP dia.75 x 75 mm Bh 4.00 150,200.00 600,800.00

- Water Moer 75 mm Bh 4.00 99,500.00 398,000.00

- Gilbaut Joint 75 mm Bh 4.00 112,500.00 450,000.00

53,313,800.00

2 PEMASANGAN PIPA DAN ACCESSORIES

Pemasangan pipa lengkap dengan Accessories termasuk penggalian tanah urugan pasir, timbunan kembali,perbaikan akibat galian,penyeberangan pipa pada jalan/sungai,pengecatan dan serta perbaikan kembali

semua kebocoran sesuai gambar spesifikasi teknis .

- Pipa GIP dia.75 mm M 3,630.00 74,614.16 270,849,408.06

270,849,408.06

3 PEKERJAAN LAIN - LAIN

- Box Pengaman Gate Valve camp. 1:2:3 M3 0.57 1,114,901.00 634,378.67

634,378.67

V. PENGUMPULAN

PENGAD./PEMAS. PIPA DAN ACCESSORIES GIP dia. 75 MM Sep. = 2.532 M'

1 PENGADAAN PIPA GIP DIA 75 MM DAN ACCESSORIES Rp.

2 PEMASANGAN PIPA DAN ACCESSORIES Rp. 270,849,408.06

634,378.67 VOL

URAIAN PEKERJAAN SAT

759,348,800.00 No.

2 PEMASANGAN PIPA DAN ACCESSORIES Rp.

3 PEKERJAAN LAIN - LAIN Rp.

JUMLAH : Rp.

270,849,408.06 634,378.67 1,030,832,586.73

Referensi

Dokumen terkait

Kepala Satuan Kerja Pengembangan Sistem Penyediaan Air Minum Provinsi Maluku... PETA ORIENTASI SPAM

Kepala Satuan Kerja Pengembangan Sistem Penyediaan Air Minum Provinsi Maluku..

Kepala Satuan Kerja Pengembangan Sistem Penyediaan Air Minum Provinsi Maluku... PETA ORIENTASI SPAM

menghubungkan antara satu daerah tujuan wisata dengan daerah asal wisatawan, baik dalam bentuk sarana transportasi berjadwal (scheduled.. IV - 9 transport) ataupun

Pengadaan dan pemasangan Pipa Refrigerant bahan pipa Tembaga berisolasi, lengkap terpasang dengan alat bantu dan Accessories yang diperlukan sesuai dengan gambar perencanaan

: PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM PROPINSI MALUKU PEKERJAAN : PEMBANGUNAN SPAM DI KAWASAN RAWAN AIR KWS.. PEMBUATAN TOWER

Desain hybrid dapat dilakukan untuk meningkatkan performansi reaktor terhadap limbah cair spesifik.[3] Keuntungan ABR dibandingkan sistem pengolahan limbah lainnya adalah waktu retensi

Raya Padalarang-Cisarua KM 2,Mekarsari Ngamprah 40552 DETAIL ENGINEERING DESIGN DED KEGIATAN: PEMBANGUNAN PRASARANA PERTANIAN SUB KEGIATAN: PEMBANGUNAN, REHABILITASI DAN