PERHITUNGAN VOLUME I. PEKERJAAN PERSIAPAN
1. Pembersihan Lahan Panjang lahan = 65 m Lebar lahan = 38 m Volume = 65 x 38
= 2470 m² 2. Pagar Keamanan
Keliling lapangan = ( 65 + 38 ) x 2 = 206 m
3. Direksi Kit
Luas = Panjang x lebar = 4 m x 4 m = 16 m² 4. Bauplank
Keliling bangunan = 126,28 m II. PEKERJAAN TANAH 1. Galian Tanah Pondasi Lajur
Panjang = 216 m
Luas = ( 1,66 + 0,80) x ½ x 1,6 = 1,986 m²
Volume = 1,986 x 216 = 425,088 m³
2. Galian Tanah Pondasi Foot Plat ( 40 Titik )
Panjang = 2,8 m 3. Galian Tanah Pondasi Rollag
Rollag Trap
Panjang = 9 m
Luas = ( 0,85 + 1,2) x ½ x 1 = 1,025 m²
Volume = 1,025 x 9 = 9,225 m ³
Rollag Pengikat
Luas = ( 0,2 + 0,3 ) x ½ x 0,3 = 0,075 m²
Volume = 0,075 x 84,8 = 6,36 m ³
TOTAL PEKERJAAN GALIAN TANAH = 425,088 +511,84 + 9,225 + 6,36 = 952,513 m ³
III. PEKERJAAN PASANGAN PONDASI 1. Urugan Pasir
Pondasi Lajur
Panjang = 216 Luas = 0,8 x 0,1
= 0,08 m² Volume = 0,08 x 216
= 17,28 m³ Pondasi Foot Plat
Volume = 0,1 x 1,75 x 2,8 = 0,49 m ³
Volume tot = 0,49 x 40 = 19,6 m³ Pondasi Rollag Trap
Volume = 0,3 x 0,1 x 9 = 0,27 m³ Volume tot = 0,27 x 6
=1,62 m³ Pondasi Rollag Pengikat
Volume = 0,25 x 0,1 x 84,8 = 2,12 m³
Urugan pasir bawah lantai Luas = 643,45 m² Volume = 643,45 x 0,1
= 64,345 m³
VOLUME TOTAL URUGAN PASIR = 17,28 + 19,6 + 1,62 + 2,12 + 64,345 = 104,965 m³
2. Pasangan Batu Belah
Panjang = 216 m
Luas = ( 0,25 + 0,8 ) x ½ x 0,9 = 0,47 m²
Volume = 0,47 x 216 = 102,06 m ³ 3. Pasangan Anstamping
IV. PEKERJAAN BETON BERTULANG 1. Foot Plat
Type A ( 20 Bh)
Volume di bagi menjadi 2 bagian : V1 = 1,65 x 1,62 x 0,3 Pembesian
D 19 – 15. 2 = 2x ( 100/15 x 2,230 x 1,65 x 1,62 ) = 79,47 kg / unit
Berat / m = 79,47 / 1,08
= 73,58 kg / m³ ~ 74 kg / m ³ Type B ( 6 Bh )
V1 = 1,65x1,62x0,3 = 0,80 m
V1 = 1,65x1,62x0,3 = 0,80
= 44,516 kg / m Berat / m = 44,516 / 0,15
= 296,77 kg / m Type S2
TUMPUAN
Panjang = 58,2 m
Volume = 58,2 x 0,4 x 0,25 = 5,82 m
Pembesian
4 D 22 x 2 = 4 x 2,980 x 2 = 23,84 kg / m
2 Ø 12 = 2 x 0,888 = 1,776 kg / m
Ø 10 – 10 = 100 / 10 x 0,617 x 1,3 = 8,021 kg / m = 33,63 kg / m Berat / m = 33,63 / 0,1
=336,37 kg / m LAPANGAN
Panjang =87,3 m
Volume = 87,3 x 0,4 x 0,25 = 8,73 m
Pembesian
4 D 22 x 2 = 4 x 2,980 x 2 = 23,84 kg / m
2 Ø 12 = 2 x 0,888 = 1,776 kg / m
Ø 10 – 15 = 100 / 15 x 0,617 x 1,3 = 5,34 kg / m = 30,96 kg / m Berat / m = 30,96 / 0,1
= 309,6 kg
Bekisting = ( 2 x 0,4 ) + 0,25 = 1,05 m
Luas / m = 1,05 / 0,1 = 10,5 m / m Type S3
TUMPUAN
Panjang = 16,8 m
Volume = 16,8 x 0,3 x 0,6 = 3,024 m
Pembesian
6 D 22 x 2 = 6 x 2,980 x 2 = 35,76 kg / m
2 Ø 12 = 2 x 0,888 = 1,776 kg / m
Ø 10 – 10 = 100 / 10 x 0,617 x 1,8 = 11,1 kg / m = 48,64 kg / m Berat / m = 48,64 / 0,18
= 270,2 kg /m LAPANGAN
Panjang = 25,2
= 4,536 m Pembesian
6 D 22 x 2 = 6 x 2,980 x 2 = 35,76 kg / m
2 Ø 12 = 2 x 0,888 = 1,776 kg / m
Ø 10 – 15 = 100 / 15 x 0,617 x 1,8 = 7,40 kg / m = 44,9 kg / m Berat / m = 44,9 / 0,18
= 249 , 4 kg / m Bekisting = ( 2 x 0,6 ) + 0,3
= 1,5 m Luas /m = 1,5 / 0,18
= 8,33 m / m
3. Kolom K1
Tinggi = 7,4 m Jumlah= 20 bh
Vol = 7,4 x 3,14 x 0,25 x 0,25 x 20 = 29,04 m
Pembesian
15 Ø19 = 15x2,230 = 33, 45 kg / m
Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,5) = 6,2 kg / m = 39,65 kg / m Berat / m = 39,65 / 0,195
= 202,29 kg / m Bekisting = ( 3,14 x 0,5) x 1
= 1,57 m
Luas / m = 1,57 / ( 3,14 x 0,25 x 0,25 = 8,26 m / m
K2
Tinggi = 4,2 m Jumlah = 4 bh
Vol = 4,2 x 3,14 x 0,2 x 0,2 x 4 = 2,1 m
Pembesian
10 Ø19= 10 x2,230 = 22,3 kg / m
Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,4) = 4,96 kg / m = 27,26 kg / m Berat / m = 27,26 / 0,125
= 218,08 kg / m Bekisting = ( 3,14 x 0,4) x 1
= 1,26 m Luas / m = 1,26 / 0,125
Tinggi = 4,2 m Jumlah = 2 bh
Vol = 4,2 x 3,14 x 0,15 x 0,15 x 2 = 0,593 m
Pembesian
8 Ø19 = 8 x2,230 = 17,84 kg / m
Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,3) = 3,72 kg / m = 21,56 kg / m Berat / m = 21,56 / 0,07
= 308 kg / m Bekisting = ( 3,14 x 0,3 ) x 1
= 0,942 m Luas / m = 0,942 / 0,07
= 13,45 m / m K4
Tinggi = 7,4 m Jumlah = 6 bh
Vol = 7,4 x 0,4 x 0,4 x 6 = 7,104 m
Pembesian
16 Ø19 = 16 x2,230 = 35,68 kg / m
Ø 8 – 10 =100 / 10 x 0,395 { ( 0,4 + 0,4) x2) = 6,32 kg / m = 42 kg / m Berat / m = 42 / 0,16
= 262,5 kg / m
Bekisting = ( 2 x ( 0,4 x 0,4 ) ) x 1 = 1,6 m
Luas / m = 1,6 / 0,16 = 10 m / m K5
Tinggi = 7,4 m Jumlah = 8 bh
Vol = 7,4 x 0,3 x 0,3 x 8 = 5,328 m
Pembesian
8 Ø19 = 8 x2,230 = 17,84 kg / m
Ø 8 – 10 =100 / 10 x 0,395 { ( 0,3 + 0,3) x2) = 4,74 kg / m = 22,58 kg / m Berat / m = 22,58 / 0,09
= 250 kg / m
Bekisting = ( 2 x ( 0,3 x 0,3 ) ) x 1 = 1,2 m
4. Balok B1 TUMPUAN Panjang = 4,8 m
Volume = 4,8 x 0,8 x 0,4 = 1,536 m Pembesian
2x 10 Ø19 = 10 x2,230 = 44,6 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 2,4 = 9,48 kg / m = 54,08 kg / m Berat / m = 54,08 / ( 0,8 x 0,4 )
= 169 kg / m Bekisting = ( 0,8 x 2 ) + 0,4
= 2 m
Luas / m = 2 / ( 0,8 x 0,4 ) = 6,25 m / m LAPANGAN
Panjang = 7,2 m
Volume = 7,2 x 0,8 x 0,4 = 2,304 m Pembesian
10 Ø19 = 10 x2,230 = 22,3 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 2,4 = 6,31 kg / m
7 Ø19 = 7 x 2,230 = 15,61 kg / m
4 Ø19 = 4 x 2,230 = 8,92 kg / m
=53, 14kg / m Berat / m = 53,14 / ( 0,8 x 0,4 )
= 166 kg / m B2-1
TUMPUAN Panjang = 14,4 m
Volume = 7,2 x 0,7 x 0,3 = 3,024 m Pembesian
8 Ø19 = 8 x2,230 = 17,84 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 2 = 7,9 kg / m
4 Ø19 = 4 x 2,230 = 8,92 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=35,45 kg / m Berat / m = 35,45 / 0,21
=168,8 kg / m LAPANGAN
Panjang = 21,6 m
Pembesian
4 Ø19 x 2 = 4 x2,230 x 2 = 17,84 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 2 = 5,26 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=23,89 kg / m Berat / m = 23,89 / 0,21
=113,79 kg / m Bekisting = ( 0,7 x 2 ) + 0,3
= 1,7 m
Luas / m = 1,7 / ( 0,7 x 0,3 ) = 8,09 m / m B2 -2
TUMPUAN
Panjang = 6 m
Volume = 6 x 0,7 x 0,3 = 1,26 m Pembesian
7 Ø19 = 7 x2,230 = 15,61 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 2 = 7,9 kg / m
3 Ø19 = 3 x 2,230 = 6,69 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=30,99 kg / m Berat / m = 30,99 / 0,21
= 147,57 kg / m Bekisting = ( 0,7 x 2 ) + 0,3
= 1,7 Luas / m = 1,7 / 0,21
= 8,09 m /m LAPANGAN
Panjang = 9 m
Volume = 9 x 0,7x 0,3 = 1,89 m Pembesian
4 Ø19 = 4 x2,230 = 8,920 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 2 = 5,26 kg / m
5 Ø19 = 5 x 2,230 = 11,15 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=26,12 kg / m Berat / m = 26,12 / 0,21
= 124,38 kg / m B3-1
TUMPUAN
Panjang = 56 m
Pembesian
6 Ø19 = 6 x2,230 = 13,38 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,5 = 5,925 kg / m
3 Ø19 = 3 x 2,230 = 6,69 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=26,78 kg / m Berat / m = 26,78 / 0,5 x 0,25
= 214,24 kg / m Bekisting = ( 0,5 x 2 ) + 0,25
= 1,25 m
Luas / m = 1,25 / 0,5 x 0,25 = 10 m / m
LAPANGAN
Panjang = 96 m
Volume = 96 x 0,5 x 0,25 = 12 m
Pembesian
3 Ø19 = 3 x2,230 = 6,69 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,5 = 3,94 kg / m
4 Ø19 = 4 x 2,230 = 8,92 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=16,79 kg / m Berat / m = 16 ,79 / 0,5x 0,25
= 134,32 kg / m B3-2
TUMPUAN
Panjang = 12 m
Volume = 12 x 0,5 x 0,25 = 1,5 m
Pembesian
5 Ø19 = 5 x2,230 = 11,15 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,5 = 5,925 kg / m
2 Ø19 = 2 x 2,230 = 4,46 kg / m
2 Ø8 = 2 x 0,395 = 0,79 kg / m
=22,325 kg / m Berat / m = 22,325 / 0,5x0,25
= 178,6 kg / m LAPANGAN
Panjang = 18 m
Volume = 18 x 0,5 x 0,25 = 2,25 m Pembesian
2 Ø19 = 2 x2,230 = 4,46 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,5 = 3,94 kg / m
3 Ø19 = 2 x 2,230 = 6,69 kg / m
=15,88 kg / m Berat / m = 15,88/ 0,5 x 0,25
= 127,04 kg / m B4-1
TUMPUAN
Panjang = 70,8 m
Volume = 70,8 x 0,4 x 0,25 = 7,08
Pembesian
5 Ø19 = 5 x2,230 = 11,15 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 3,42 kg / m
2 Ø19 = 2 x 2,230 = 4,46 kg / m
=19,38 kg / m Berat / m = 19,38 / 0,4x0,25
=193,8 kg / m Bekisting = ( 0,4 x 2 ) + 0,25
= 1,05
Luas / m = 1,05 / 0,4 x 0,25 = 1,05 m / m LAPANGAN
Panjang = 106,2 m
Volume = 106,2 x 0,4 x 0,25 = 10,62 m
Pembesian
2 Ø19 = 2 x2,230 = 4,46 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m
3 Ø19 = 2 x 2,230 = 6,69 kg / m
=14,57 kg / m Berat / m = 14,57/ 0,4x0,25
= 145,7 kg / m B4-2
TUMPUAN
Panjang = 27,6 m
Volume = 27,6 x 0,4 x 0,25 = 2,76 m
Pembesian
4 Ø19 = 4 x2,230 = 8,920 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 3,42 kg / m
2 Ø19 = 2 x 2,230 = 4,46 kg / m
=16,8 kg / m Berat / m = 16,8 / 0,4 x 0,25
= 168 kg / m LAPANGAN
Panjang = 41,4 m
Volume = 41,4 x 0,4 x 0,25 = 4,14 m
2 Ø19 = 2 x2,230 = 4,46 kg / m Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m
3 Ø19 = 2 x 2,230 = 6,69 kg / m
=14,57 kg / m Berat / m = 14,57/ 0,4x0,25
= 145,7 kg / m B5-1
TUMPUAN
Panjang = 16,8 m
Volume = 16,8 x 0,4 x 0,2 = 1,344 m
Pembesian
5 Ø16 = 5 x1,58 = 7,9 kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,2 = 4,74 kg / m
2 Ø16 = 2 x 1,58 = 3,16 kg / m
=15,8 kg / m Berat / m = 15,8 / 0,08
= 197,5 kg / m Bekisting = ( 0,4 x 2 ) + 0,2
= 1 Luas / m = 1 / 0,08
= 12,5 m / m LAPANGAN
Panjang = 25,2 m
Volume = 25,2 x 0,4 x 0,2 = 2,016
Pembesian
3 Ø16 = 3 x1,58 = 4,74kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,2 = 3,15 kg / m
4 Ø16 =4 x 1,58 = 6,32 kg / m
=14,21 kg / m Berat / m = 14,21 / 0,08
= 177,625 kg / m B5-2
TUMPUAN
Panjang = 3,6 m
Volume = 3,6 x 0,4 x 0,2 = 0,288 m Pembesian
4 Ø16 = 4 x1,58 = 6,32kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,2 = 4,74 kg / m
2 Ø16 = 2 x 1,58 = 3,16 kg / m
=14,2 kg / m Berat / m = 14,2 / 0,08
LAPANGAN
Panjang = 5,4 m
Volume = 5,4 x 0,4 x 0,2 = 0,432 m Pembesian
3 Ø16 = 3 x1,58 = 4,74kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,2 = 3,15 kg / m
2 Ø16 = 2 x 1,58 = 3,16 kg / m
=11,05 kg / m Berat / m = 11,05 / 0,08
= 138,125 kg / m B6
TUMPUAN
Panjang = 9,6 m
Volume = 9,6 x 0,3 x 0,25 = 0,72 m
Pembesian
3 Ø14 = 3 x1,23 = 3,69 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,1 = 2,89 kg / m
2 Ø14 = 2 x 1,23 = 2,46 kg / m
=9,04 kg / m Berat / m = 9,04 / 0,075
= 120,53 kg / m LAPANGAN
Panjang = 14,4
Volume = 14,4 x 0,3 x 0,25 = 1,08 m
Pembesian
3 Ø16 = 3 x1,58 = 4,74 kg / m
Ø 8 – 20 =100 / 20 x 0,395 x 1,1 = 2,17 kg / m
2 Ø14 = 2 x 1,23 = 2,46 kg / m
=9,37 kg / m Berat / m = 9,37 / 0,075
= 124,9 kg / m Bekisting = ( 0,3 x 2 ) + 0,25
= 0,85 m Luas / m = 0,85 / 0,075
= 11,3 m / m B7
TUMPUAN
Panjang = 4,8 m
Volume = 4,8 x 0,6 x 0,25 = 0,72 m
Pembesian
Ø 8 – 10 =100 / 10 x 0,395 x 1,7 = 6,715 kg / m
3 Ø19 =3 x 2,230 = 6,69kg / m
2 Ø8 = 2 x 0,395 = 0,79kg / m
=27,57 kg / m Berat / m = 27,57 / 0,15 = 183,8 kg /m
LAPANGAN
Panjang = 7,2 m
Volume = 7,2 x 0,6 x 0,25 Pembesian
4 Ø19 = 4 x2,230 = 8,92kg / m
Ø 8 – 10 =100 / 15 x 0,395 x 1,7 = 4,47 kg / m
3 Ø19 =3 x 2,230 = 6,69kg / m
2 Ø8 = 2 x 0,395 = 0,79kg / m
=20,87 kg / m Berat / m = 20,87 / 0,15
= 139,17 kg /m Bekisting = ( 0,6 x2 ) + 0,25
= 1,45 Luas /m = 1,45 / 0,15
=9,66 m /m 5. RING BALK TUMPUAN
Panjang = 75,8 m
Volume = 75,8 x 0,4 x 0,25 = 7,58 m
Pembesian
4 Ø19 = 4 x2,230 = 8,92kg / m
Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 5,135 kg / m
2 Ø19 =2 x 2,230 = 4,46 kg / m
=18,515 kg / m Berat / m = 18,515 / 0,1
= 185,15 kg /m Bekisting = ( 0,4 x 2 ) + 0,25
= 1,05 Luas / m = 1,05 / 0,1
= 10,5 m / m LAPANGAN
Panjang = 96,1 m
Volume = 96,1 x 0,4 x 0,25 = 9,61 m
Pembesian
3 Ø19 = 3 x2,230 = 6,69 kg / m
Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m
2 Ø19 =2 x 2,230 = 4,46 kg / m
Berat / m = 14,57 / 0,1 = 145,7 kg /m 6. PLAT LANTAI
Luas lantai = 573 m Tebal = 0,12
Volume = 0,12 x 474,1 = 67,772 m Pembesian
Ø 10 – 40 = 1,48 kg Berat / m = 1,48 / 0,12 x 1
= 12,34 kg / m 7. TANGGA
V. PEKERJAAN PASANGAN DINDING 1. Pasangan Batu Trasram 1 : 3
Dinding lantai 1
Panjang = 157,75 – 50,69 = 107,06 m
Volume = 107,06 x 0,3 x 0,15 = 4,8117 m
Trasram KM / WC LT 1 dan Lt 2 Tinggi trasram = 1,5 m Panjang = 50,4 – 8,2
= 42,2 m
Volume = 42,2 x 1,5 x 0,15 = 9,495 m
2. Pasangan Batu bata 1 : 3 : 10
Dinding Lantai 1
Tinggi dinding = 3,7 m Panjang = 157,75 m
Luas = ( panjang dinding x tinggi ) – bukaan = ( 157,75 x 3,7 ) – 142,69
= 583,675 – 142,69 = 440,985 m Volume = 440,985 x 0,15
= 66,14 m Dinding Km / Wc lantai 1
Tinggi dinding = 2,25 m Panjang = 27 m
Luas = ( 27 x 2,25 ) – 23,066 = 60,75 – 23,066 = 37,684 m Volume = 37,684 x 0,15
= 5,65 m Dinding Lantai 2
Tinggi = 3,2 m
Panjang = 153,75
= 492 – 116,25 = 375,75 m Volume = 375,75 x 0,15
= 56,36 m Dinding Km Lt 2
Tinggi = 1,45 m
Panjang = 26,6
Luas = ( 26,2 x 1,45 ) – 5,28 = 33,29 m
Volume = 33,29 x 0,15 = 4,99 m VI. PEKERJAAN PLESTERAN
1. Dinding trasram ( 1 : 8 ) tebal 15 mm Dinding LT 1
Panjang = 107,06
Tinggi = 0,3
Volume = 107,06 x 0,3 x 2 = 64,23 m
Dinding Km / Wc
Panjang = 42,2
Tinggi = 1,75
Volume = 42,2 x 1,75 x 2 = 147,7 m 2. Dinding ½ bata ( 1: 3 ) tebal 15 mm
Dinding Lt 1
Volume = 440,985 x 2 = 881,97 m Dinding KM / wc Lt1
Volume = 37,684 x 2 = 75,368 m Dinding Lt 2
Volume = 375,75 x 2 = 751 ,5 m Dinding Km / Wc Lt2 Volume = 33,29 x 2
= 66,58 VII. PEKERJAAN KUSEN
1. Type PJ1 ( 1 Bh )
Kusen = Alumunium 6 / 10 Panjang = 29,61 m
Kaca Mati
Volume =12,284 m 2. Type PJ2 ( 1 bh )
Kusen = Alumunium
Panjang = 21,29 m Pintu Panil Kyu
Luas = 3,15 m
Jendela Berbingkai
Kaca Mati Luas = 1,135 m 3. Type PJ3 ( 2 Bh )
Kusen = Alumunium
Panjang = 15,55 x 2 = 31,1 m Pintu Panil Kyu
Luas = 1,68 m Volume = 1,68 x 2
= 3,36 m
Jendela Berbingkai
Luas = 1,43 m Volume = 1,43 x 2
= 2,86 m 4. Type PTS ( 1 Bh )
Kusen = Alumunium
Panjang = 16,5 m Pintu Panil Kyu
Luas = 1,68 m Kaca Mati
Luas = 2,62 m
5. Type P1 ( 4 Bh )
Kusen = Alumunium
Panjang = 9,05 m Volume = 9,05 x 4
= 36,2 m Pintu Panil Kayu
Luas = 2,73 m Volume = 2,73 x 4
= 10,92 m Kaca Mati
Luas = 3,65 m Volume = 3,65 x 4
= 14,6 m 6. Type P2 ( 7 Bh )
Kusen = Alumunium
Panjang = 7,5 m Volume = 7,5 x 7
= 52,5 m Pintu Panil Kayu
Luas = 1,68 m Volume = 1,68 x 7
= 11,76 m Kaca Mati
Volume = 0,52 x 7 = 3,64 m 7. Type P3 ( 2 Bh )
Kusen = Alumunium
Panjang = 10,4 m Volume = 10,4 x 2
= 20,8 m Pintu Kaca
Luas = 2,28 m Volume = 2,28 x 2
= 4,56 m Kaca Mati
Luas = 1,1 m Volume = 1,1 x 2
= 2,2 m 8. Type P4 ( 10 Bh )
Kusen = Alumunium
Panjang = 5,12 m Volume = 5,12 x 10
= 51,2 m Pintu PVC
Luas = 1,57 m Volume = 1,57 x 10
= 15,7 m 9. Type J1 ( 10 Bh )
Kusen = Alumunium
Panjang = 17,2 m Volume = 17,2 x 10
= 172 m Daun Jendela
Luas = 2,37 m Volume = 2,37 x 10
= 23,7 m Kaca Mati
Luas = 1,7 m Volume = 1,7 x 10
= 17 m 10. Type J2 ( 19 Bh )
Kusen = Alumunium
Panjang = 11,8 m Volume = 11,8 x 19
= 224,2 m Daun Jendela
Luas = 2,37 m Volume = 2,37 x 19
= 45,03 m Kaca Mati
Volume = 0,85 x 19 = 16,15 m 11. Type J3 ( 4 Bh )
Kusen = Alumunium 6 / 10 Panjang = 14,08 m
Volume = 14,08 x 4 = 56,32 m Kaca Mati
Luas = 3,852 m Volume = 3,85 x 4
= 15,4 m 12. Type J4 ( 2 Bh )
Kusen = Alumunium
Panjang = 9,9 m Volume = 9,9 x 2
= 19,8 m Daun Jendela
Luas = 1,18 m Volume = 1,18 x 2
= 2,37 m Kaca Mati
Luas = 0,85m Volume = 0,85 x 2
= 1,7 m 13. Type J5 ( 2 Bh )
Kusen = Alumunium 6 / 10 Panjang = 13,14 m
Volume = 13,14 x 2 = 26,28 m Kaca Mati
Luas = 2,772m Volume = 2,772 x 2
= 5,54 m 14. Type J6 ( 1 Bh )
Kusen = Alumunium 6 / 10 Panjang = 20,6 m
Kaca Mati
Luas = 3,68 m 15. Type V1 (2 Bh )
Kusen = Alumunium
Panjang = 5,35 m Volume = 5,35 x 2
= 10,7 m Daun Jendela
= 1,82 m 16. Type V2 ( 9 Bh )
Kusen = Alumunium
Panjang = 3,1 m Volume = 3,1 x 9
= 27,9 m Daun Jendela
Luas = 0,455 m Volume = 0,455 x 9
= 4,095 m VIII. PEKERJAAN LANTAI
1. Garaito 40 x 40 ( Polos )
Luas = 157,5 + 13,5 + 9 + 4,25 = 184,25 m
Volume = 184,25 – 4,8 = 179,45 m 2. Keramik Glasur 40 x 40
Luas = 24,4 m
3. Keramik 30 x 30 ( Putih ) Luas = 684,5 m 4. Keramik 30 x 30 ( abu – abu )
Luas = 323,23 m 5. Keramik 20 x 20
Luas = 38 m
6. Keramik Dinding 20 x 25 Panjang =51,9 Tinggi = 1,5 m Luas = 51,9 x 1,5
= 77,85 m IX. PEKERJAAN LANGIT – LANGIT
1. Pemasanga Rangka Metal Furring Luas = 1542,34 m 2. Pemesangan gypsum Board Luas = 723,09 m 3. Pemasangan Kalsiboard
Luas = 819,25 m
X. PEKERJAAN ATAP
1. Pekerjaan Kuda – Kuda Baja Kuda – Kuda 1
Profile 60.60 . 6 Panjang = 55,22 m Berat kg / m = 5,42 Berat total = 55,22 x 5,42
= 299,2 Profile 80.80.8 Panjang = 51,24 m Barat kg / m = 8,72 Berat total = 51,24 x 8,72
= 446,8
= 746,01 Kuda – Kuda 2
Profile 60.60.6 Panjang = 73,69
Berat Total = 73,69 x 5,42 = 399,41 Profile 80.80.8 Panjang = 28,44 m Berat total = 28,44 x 8,72
= 247,4
BERAT KUDA – KUDA TYPE 2 = 399,41 + 247,4 = 646,838
Kuda – Kuda 3 Profile 60.60.6 Panjang = 18,16 m Berat total = 18,16 x 5,42
= 98,42 Profile 80.80.8 Panjang = 25,78 m Berat total = 25,78 x 8,72
= 224,8
BERAT KUDA – KUDA TYPE 3 = 98,42 + 224 ,8 = 323,22
2. Gording 8 / 12
Panjang = 633,33 m
Volume = 0,08 x x 633,33 = 50,6 m 3. Usuk dan reng
Luas atap = 870,454 m 4. Nok
Panjang = 48,75 m 5. Bubungan
Panjang = 48,75 m XI. PEKERJAAN SANITASI
1. Jumlah Kloset Duduk = 7 bh 2. Jumlah Wastafel = 9 bh 3. Jumlah floor drain = 8 bh 4. Jumlah kran = 9 bh
5. Pasang Bak cuci stainlestil = 1 bh 6. Pasang bak mandi = 7 bh
7. Panjang Pipa air kotor padat = 29,73 m 8. Panjang pipa air kotor cair = 48,63 m 9. Pasang pipa beton = 195,65 m 10. Pasang pipa air bersih = 99,13 m XII. PEKERJAAN ISTALASI LISTRIK