PERHITUNGAN VOLUME I. PEKERJAAN PERSIAPAN

1. Pembersihan Lahan Panjang lahan = 65 m Lebar lahan = 38 m Volume = 65 x 38

= 2470 m² 2. Pagar Keamanan

Keliling lapangan = ( 65 + 38 ) x 2 = 206 m

3. Direksi Kit

Luas = Panjang x lebar = 4 m x 4 m = 16 m² 4. Bauplank

Keliling bangunan = 126,28 m II. PEKERJAAN TANAH 1. Galian Tanah Pondasi Lajur

Panjang = 216 m

Luas = ( 1,66 + 0,80) x ½ x 1,6 = 1,986 m²

Volume = 1,986 x 216 = 425,088 m³

2. Galian Tanah Pondasi Foot Plat ( 40 Titik )

Panjang = 2,8 m 3. Galian Tanah Pondasi Rollag

 Rollag Trap

Panjang = 9 m

Luas = ( 0,85 + 1,2) x ½ x 1 = 1,025 m²

Volume = 1,025 x 9 = 9,225 m ³

 Rollag Pengikat

(2)

Luas = ( 0,2 + 0,3 ) x ½ x 0,3 = 0,075 m²

Volume = 0,075 x 84,8 = 6,36 m ³

TOTAL PEKERJAAN GALIAN TANAH = 425,088 +511,84 + 9,225 + 6,36 = 952,513 m ³

III. PEKERJAAN PASANGAN PONDASI 1. Urugan Pasir

 Pondasi Lajur

Panjang = 216 Luas = 0,8 x 0,1

= 0,08 m² Volume = 0,08 x 216

= 17,28 m³  Pondasi Foot Plat

Volume = 0,1 x 1,75 x 2,8 = 0,49 m ³

Volume tot = 0,49 x 40 = 19,6 m³  Pondasi Rollag Trap

Volume = 0,3 x 0,1 x 9 = 0,27 m³ Volume tot = 0,27 x 6

=1,62 m³  Pondasi Rollag Pengikat

Volume = 0,25 x 0,1 x 84,8 = 2,12 m³

 Urugan pasir bawah lantai Luas = 643,45 m² Volume = 643,45 x 0,1

= 64,345 m³

VOLUME TOTAL URUGAN PASIR = 17,28 + 19,6 + 1,62 + 2,12 + 64,345 = 104,965 m³

2. Pasangan Batu Belah

Panjang = 216 m

Luas = ( 0,25 + 0,8 ) x ½ x 0,9 = 0,47 m²

Volume = 0,47 x 216 = 102,06 m ³ 3. Pasangan Anstamping

(3)

IV. PEKERJAAN BETON BERTULANG 1. Foot Plat

 Type A ( 20 Bh)

Volume di bagi menjadi 2 bagian : V1 = 1,65 x 1,62 x 0,3 Pembesian

D 19 – 15. 2 = 2x ( 100/15 x 2,230 x 1,65 x 1,62 ) = 79,47 kg / unit

Berat / m = 79,47 / 1,08

= 73,58 kg / m³ ~ 74 kg / m ³  Type B ( 6 Bh )

V1 = 1,65x1,62x0,3 = 0,80 m

V1 = 1,65x1,62x0,3 = 0,80

(4)
(5)

= 44,516 kg / m Berat / m = 44,516 / 0,15

= 296,77 kg / m  Type S2

TUMPUAN

Panjang = 58,2 m

Volume = 58,2 x 0,4 x 0,25 = 5,82 m

Pembesian

4 D 22 x 2 = 4 x 2,980 x 2 = 23,84 kg / m

2 Ø 12 = 2 x 0,888 = 1,776 kg / m

Ø 10 – 10 = 100 / 10 x 0,617 x 1,3 = 8,021 kg / m = 33,63 kg / m Berat / m = 33,63 / 0,1

=336,37 kg / m LAPANGAN

Panjang =87,3 m

Volume = 87,3 x 0,4 x 0,25 = 8,73 m

Pembesian

4 D 22 x 2 = 4 x 2,980 x 2 = 23,84 kg / m

2 Ø 12 = 2 x 0,888 = 1,776 kg / m

Ø 10 – 15 = 100 / 15 x 0,617 x 1,3 = 5,34 kg / m = 30,96 kg / m Berat / m = 30,96 / 0,1

= 309,6 kg

Bekisting = ( 2 x 0,4 ) + 0,25 = 1,05 m

Luas / m = 1,05 / 0,1 = 10,5 m / m  Type S3

TUMPUAN

Panjang = 16,8 m

Volume = 16,8 x 0,3 x 0,6 = 3,024 m

Pembesian

6 D 22 x 2 = 6 x 2,980 x 2 = 35,76 kg / m

2 Ø 12 = 2 x 0,888 = 1,776 kg / m

Ø 10 – 10 = 100 / 10 x 0,617 x 1,8 = 11,1 kg / m = 48,64 kg / m Berat / m = 48,64 / 0,18

= 270,2 kg /m LAPANGAN

Panjang = 25,2

(6)

= 4,536 m Pembesian

6 D 22 x 2 = 6 x 2,980 x 2 = 35,76 kg / m

2 Ø 12 = 2 x 0,888 = 1,776 kg / m

Ø 10 – 15 = 100 / 15 x 0,617 x 1,8 = 7,40 kg / m = 44,9 kg / m Berat / m = 44,9 / 0,18

= 249 , 4 kg / m Bekisting = ( 2 x 0,6 ) + 0,3

= 1,5 m Luas /m = 1,5 / 0,18

= 8,33 m / m

3. Kolom  K1

Tinggi = 7,4 m Jumlah= 20 bh

Vol = 7,4 x 3,14 x 0,25 x 0,25 x 20 = 29,04 m

Pembesian

15 Ø19 = 15x2,230 = 33, 45 kg / m

Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,5) = 6,2 kg / m = 39,65 kg / m Berat / m = 39,65 / 0,195

= 202,29 kg / m Bekisting = ( 3,14 x 0,5) x 1

= 1,57 m

Luas / m = 1,57 / ( 3,14 x 0,25 x 0,25 = 8,26 m / m

 K2

Tinggi = 4,2 m Jumlah = 4 bh

Vol = 4,2 x 3,14 x 0,2 x 0,2 x 4 = 2,1 m

Pembesian

10 Ø19= 10 x2,230 = 22,3 kg / m

Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,4) = 4,96 kg / m = 27,26 kg / m Berat / m = 27,26 / 0,125

= 218,08 kg / m Bekisting = ( 3,14 x 0,4) x 1

= 1,26 m Luas / m = 1,26 / 0,125

(7)

Tinggi = 4,2 m Jumlah = 2 bh

Vol = 4,2 x 3,14 x 0,15 x 0,15 x 2 = 0,593 m

Pembesian

8 Ø19 = 8 x2,230 = 17,84 kg / m

Ø 8 – 10 =100 / 10 x 0,395 ( 3,14 x 0,3) = 3,72 kg / m = 21,56 kg / m Berat / m = 21,56 / 0,07

= 308 kg / m Bekisting = ( 3,14 x 0,3 ) x 1

= 0,942 m Luas / m = 0,942 / 0,07

= 13,45 m / m  K4

Tinggi = 7,4 m Jumlah = 6 bh

Vol = 7,4 x 0,4 x 0,4 x 6 = 7,104 m

Pembesian

16 Ø19 = 16 x2,230 = 35,68 kg / m

Ø 8 – 10 =100 / 10 x 0,395 { ( 0,4 + 0,4) x2) = 6,32 kg / m = 42 kg / m Berat / m = 42 / 0,16

= 262,5 kg / m

Bekisting = ( 2 x ( 0,4 x 0,4 ) ) x 1 = 1,6 m

Luas / m = 1,6 / 0,16 = 10 m / m  K5

Tinggi = 7,4 m Jumlah = 8 bh

Vol = 7,4 x 0,3 x 0,3 x 8 = 5,328 m

Pembesian

8 Ø19 = 8 x2,230 = 17,84 kg / m

Ø 8 – 10 =100 / 10 x 0,395 { ( 0,3 + 0,3) x2) = 4,74 kg / m = 22,58 kg / m Berat / m = 22,58 / 0,09

= 250 kg / m

Bekisting = ( 2 x ( 0,3 x 0,3 ) ) x 1 = 1,2 m

(8)

4. Balok  B1 TUMPUAN Panjang = 4,8 m

Volume = 4,8 x 0,8 x 0,4 = 1,536 m Pembesian

2x 10 Ø19 = 10 x2,230 = 44,6 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 2,4 = 9,48 kg / m = 54,08 kg / m Berat / m = 54,08 / ( 0,8 x 0,4 )

= 169 kg / m Bekisting = ( 0,8 x 2 ) + 0,4

= 2 m

Luas / m = 2 / ( 0,8 x 0,4 ) = 6,25 m / m LAPANGAN

Panjang = 7,2 m

Volume = 7,2 x 0,8 x 0,4 = 2,304 m Pembesian

10 Ø19 = 10 x2,230 = 22,3 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 2,4 = 6,31 kg / m

7 Ø19 = 7 x 2,230 = 15,61 kg / m

4 Ø19 = 4 x 2,230 = 8,92 kg / m

=53, 14kg / m Berat / m = 53,14 / ( 0,8 x 0,4 )

= 166 kg / m  B2-1

TUMPUAN Panjang = 14,4 m

Volume = 7,2 x 0,7 x 0,3 = 3,024 m Pembesian

8 Ø19 = 8 x2,230 = 17,84 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 2 = 7,9 kg / m

4 Ø19 = 4 x 2,230 = 8,92 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=35,45 kg / m Berat / m = 35,45 / 0,21

=168,8 kg / m LAPANGAN

Panjang = 21,6 m

(9)

Pembesian

4 Ø19 x 2 = 4 x2,230 x 2 = 17,84 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 2 = 5,26 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=23,89 kg / m Berat / m = 23,89 / 0,21

=113,79 kg / m Bekisting = ( 0,7 x 2 ) + 0,3

= 1,7 m

Luas / m = 1,7 / ( 0,7 x 0,3 ) = 8,09 m / m  B2 -2

TUMPUAN

Panjang = 6 m

Volume = 6 x 0,7 x 0,3 = 1,26 m Pembesian

7 Ø19 = 7 x2,230 = 15,61 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 2 = 7,9 kg / m

3 Ø19 = 3 x 2,230 = 6,69 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=30,99 kg / m Berat / m = 30,99 / 0,21

= 147,57 kg / m Bekisting = ( 0,7 x 2 ) + 0,3

= 1,7 Luas / m = 1,7 / 0,21

= 8,09 m /m LAPANGAN

Panjang = 9 m

Volume = 9 x 0,7x 0,3 = 1,89 m Pembesian

4 Ø19 = 4 x2,230 = 8,920 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 2 = 5,26 kg / m

5 Ø19 = 5 x 2,230 = 11,15 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=26,12 kg / m Berat / m = 26,12 / 0,21

= 124,38 kg / m  B3-1

TUMPUAN

Panjang = 56 m

(10)

Pembesian

6 Ø19 = 6 x2,230 = 13,38 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,5 = 5,925 kg / m

3 Ø19 = 3 x 2,230 = 6,69 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=26,78 kg / m Berat / m = 26,78 / 0,5 x 0,25

= 214,24 kg / m Bekisting = ( 0,5 x 2 ) + 0,25

= 1,25 m

Luas / m = 1,25 / 0,5 x 0,25 = 10 m / m

LAPANGAN

Panjang = 96 m

Volume = 96 x 0,5 x 0,25 = 12 m

Pembesian

3 Ø19 = 3 x2,230 = 6,69 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,5 = 3,94 kg / m

4 Ø19 = 4 x 2,230 = 8,92 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=16,79 kg / m Berat / m = 16 ,79 / 0,5x 0,25

= 134,32 kg / m  B3-2

TUMPUAN

Panjang = 12 m

Volume = 12 x 0,5 x 0,25 = 1,5 m

Pembesian

5 Ø19 = 5 x2,230 = 11,15 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,5 = 5,925 kg / m

2 Ø19 = 2 x 2,230 = 4,46 kg / m

2 Ø8 = 2 x 0,395 = 0,79 kg / m

=22,325 kg / m Berat / m = 22,325 / 0,5x0,25

= 178,6 kg / m LAPANGAN

Panjang = 18 m

Volume = 18 x 0,5 x 0,25 = 2,25 m Pembesian

2 Ø19 = 2 x2,230 = 4,46 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,5 = 3,94 kg / m

3 Ø19 = 2 x 2,230 = 6,69 kg / m

(11)

=15,88 kg / m Berat / m = 15,88/ 0,5 x 0,25

= 127,04 kg / m  B4-1

TUMPUAN

Panjang = 70,8 m

Volume = 70,8 x 0,4 x 0,25 = 7,08

Pembesian

5 Ø19 = 5 x2,230 = 11,15 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 3,42 kg / m

2 Ø19 = 2 x 2,230 = 4,46 kg / m

=19,38 kg / m Berat / m = 19,38 / 0,4x0,25

=193,8 kg / m Bekisting = ( 0,4 x 2 ) + 0,25

= 1,05

Luas / m = 1,05 / 0,4 x 0,25 = 1,05 m / m LAPANGAN

Panjang = 106,2 m

Volume = 106,2 x 0,4 x 0,25 = 10,62 m

Pembesian

2 Ø19 = 2 x2,230 = 4,46 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m

3 Ø19 = 2 x 2,230 = 6,69 kg / m

=14,57 kg / m Berat / m = 14,57/ 0,4x0,25

= 145,7 kg / m  B4-2

TUMPUAN

Panjang = 27,6 m

Volume = 27,6 x 0,4 x 0,25 = 2,76 m

Pembesian

4 Ø19 = 4 x2,230 = 8,920 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 3,42 kg / m

2 Ø19 = 2 x 2,230 = 4,46 kg / m

=16,8 kg / m Berat / m = 16,8 / 0,4 x 0,25

= 168 kg / m LAPANGAN

Panjang = 41,4 m

Volume = 41,4 x 0,4 x 0,25 = 4,14 m

(12)

2 Ø19 = 2 x2,230 = 4,46 kg / m Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m

3 Ø19 = 2 x 2,230 = 6,69 kg / m

=14,57 kg / m Berat / m = 14,57/ 0,4x0,25

= 145,7 kg / m  B5-1

TUMPUAN

Panjang = 16,8 m

Volume = 16,8 x 0,4 x 0,2 = 1,344 m

Pembesian

5 Ø16 = 5 x1,58 = 7,9 kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,2 = 4,74 kg / m

2 Ø16 = 2 x 1,58 = 3,16 kg / m

=15,8 kg / m Berat / m = 15,8 / 0,08

= 197,5 kg / m Bekisting = ( 0,4 x 2 ) + 0,2

= 1 Luas / m = 1 / 0,08

= 12,5 m / m LAPANGAN

Panjang = 25,2 m

Volume = 25,2 x 0,4 x 0,2 = 2,016

Pembesian

3 Ø16 = 3 x1,58 = 4,74kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,2 = 3,15 kg / m

4 Ø16 =4 x 1,58 = 6,32 kg / m

=14,21 kg / m Berat / m = 14,21 / 0,08

= 177,625 kg / m  B5-2

TUMPUAN

Panjang = 3,6 m

Volume = 3,6 x 0,4 x 0,2 = 0,288 m Pembesian

4 Ø16 = 4 x1,58 = 6,32kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,2 = 4,74 kg / m

2 Ø16 = 2 x 1,58 = 3,16 kg / m

=14,2 kg / m Berat / m = 14,2 / 0,08

(13)

LAPANGAN

Panjang = 5,4 m

Volume = 5,4 x 0,4 x 0,2 = 0,432 m Pembesian

3 Ø16 = 3 x1,58 = 4,74kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,2 = 3,15 kg / m

2 Ø16 = 2 x 1,58 = 3,16 kg / m

=11,05 kg / m Berat / m = 11,05 / 0,08

= 138,125 kg / m  B6

TUMPUAN

Panjang = 9,6 m

Volume = 9,6 x 0,3 x 0,25 = 0,72 m

Pembesian

3 Ø14 = 3 x1,23 = 3,69 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,1 = 2,89 kg / m

2 Ø14 = 2 x 1,23 = 2,46 kg / m

=9,04 kg / m Berat / m = 9,04 / 0,075

= 120,53 kg / m LAPANGAN

Panjang = 14,4

Volume = 14,4 x 0,3 x 0,25 = 1,08 m

Pembesian

3 Ø16 = 3 x1,58 = 4,74 kg / m

Ø 8 – 20 =100 / 20 x 0,395 x 1,1 = 2,17 kg / m

2 Ø14 = 2 x 1,23 = 2,46 kg / m

=9,37 kg / m Berat / m = 9,37 / 0,075

= 124,9 kg / m Bekisting = ( 0,3 x 2 ) + 0,25

= 0,85 m Luas / m = 0,85 / 0,075

= 11,3 m / m  B7

TUMPUAN

Panjang = 4,8 m

Volume = 4,8 x 0,6 x 0,25 = 0,72 m

Pembesian

(14)

Ø 8 – 10 =100 / 10 x 0,395 x 1,7 = 6,715 kg / m

3 Ø19 =3 x 2,230 = 6,69kg / m

2 Ø8 = 2 x 0,395 = 0,79kg / m

=27,57 kg / m Berat / m = 27,57 / 0,15 = 183,8 kg /m

LAPANGAN

Panjang = 7,2 m

Volume = 7,2 x 0,6 x 0,25 Pembesian

4 Ø19 = 4 x2,230 = 8,92kg / m

Ø 8 – 10 =100 / 15 x 0,395 x 1,7 = 4,47 kg / m

3 Ø19 =3 x 2,230 = 6,69kg / m

2 Ø8 = 2 x 0,395 = 0,79kg / m

=20,87 kg / m Berat / m = 20,87 / 0,15

= 139,17 kg /m Bekisting = ( 0,6 x2 ) + 0,25

= 1,45 Luas /m = 1,45 / 0,15

=9,66 m /m 5. RING BALK TUMPUAN

Panjang = 75,8 m

Volume = 75,8 x 0,4 x 0,25 = 7,58 m

Pembesian

4 Ø19 = 4 x2,230 = 8,92kg / m

Ø 8 – 10 =100 / 10 x 0,395 x 1,3 = 5,135 kg / m

2 Ø19 =2 x 2,230 = 4,46 kg / m

=18,515 kg / m Berat / m = 18,515 / 0,1

= 185,15 kg /m Bekisting = ( 0,4 x 2 ) + 0,25

= 1,05 Luas / m = 1,05 / 0,1

= 10,5 m / m LAPANGAN

Panjang = 96,1 m

Volume = 96,1 x 0,4 x 0,25 = 9,61 m

Pembesian

3 Ø19 = 3 x2,230 = 6,69 kg / m

Ø 8 – 15 =100 / 15 x 0,395 x 1,3 = 3,42 kg / m

2 Ø19 =2 x 2,230 = 4,46 kg / m

(15)

Berat / m = 14,57 / 0,1 = 145,7 kg /m 6. PLAT LANTAI

Luas lantai = 573 m Tebal = 0,12

Volume = 0,12 x 474,1 = 67,772 m Pembesian

Ø 10 – 40 = 1,48 kg Berat / m = 1,48 / 0,12 x 1

= 12,34 kg / m 7. TANGGA

V. PEKERJAAN PASANGAN DINDING 1. Pasangan Batu Trasram 1 : 3

 Dinding lantai 1

Panjang = 157,75 – 50,69 = 107,06 m

Volume = 107,06 x 0,3 x 0,15 = 4,8117 m

 Trasram KM / WC LT 1 dan Lt 2 Tinggi trasram = 1,5 m Panjang = 50,4 – 8,2

= 42,2 m

Volume = 42,2 x 1,5 x 0,15 = 9,495 m

2. Pasangan Batu bata 1 : 3 : 10

 Dinding Lantai 1

Tinggi dinding = 3,7 m Panjang = 157,75 m

Luas = ( panjang dinding x tinggi ) – bukaan = ( 157,75 x 3,7 ) – 142,69

= 583,675 – 142,69 = 440,985 m Volume = 440,985 x 0,15

= 66,14 m  Dinding Km / Wc lantai 1

Tinggi dinding = 2,25 m Panjang = 27 m

Luas = ( 27 x 2,25 ) – 23,066 = 60,75 – 23,066 = 37,684 m Volume = 37,684 x 0,15

= 5,65 m  Dinding Lantai 2

Tinggi = 3,2 m

Panjang = 153,75

(16)

= 492 – 116,25 = 375,75 m Volume = 375,75 x 0,15

= 56,36 m  Dinding Km Lt 2

Tinggi = 1,45 m

Panjang = 26,6

Luas = ( 26,2 x 1,45 ) – 5,28 = 33,29 m

Volume = 33,29 x 0,15 = 4,99 m VI. PEKERJAAN PLESTERAN

1. Dinding trasram ( 1 : 8 ) tebal 15 mm  Dinding LT 1

Panjang = 107,06

Tinggi = 0,3

Volume = 107,06 x 0,3 x 2 = 64,23 m

 Dinding Km / Wc

Panjang = 42,2

Tinggi = 1,75

Volume = 42,2 x 1,75 x 2 = 147,7 m 2. Dinding ½ bata ( 1: 3 ) tebal 15 mm

 Dinding Lt 1

Volume = 440,985 x 2 = 881,97 m  Dinding KM / wc Lt1

Volume = 37,684 x 2 = 75,368 m  Dinding Lt 2

Volume = 375,75 x 2 = 751 ,5 m  Dinding Km / Wc Lt2 Volume = 33,29 x 2

= 66,58 VII. PEKERJAAN KUSEN

1. Type PJ1 ( 1 Bh )

 Kusen = Alumunium 6 / 10 Panjang = 29,61 m

 Kaca Mati

Volume =12,284 m 2. Type PJ2 ( 1 bh )

 Kusen = Alumunium

Panjang = 21,29 m  Pintu Panil Kyu

Luas = 3,15 m

 Jendela Berbingkai

(17)

 Kaca Mati Luas = 1,135 m 3. Type PJ3 ( 2 Bh )

 Kusen = Alumunium

Panjang = 15,55 x 2 = 31,1 m  Pintu Panil Kyu

Luas = 1,68 m Volume = 1,68 x 2

= 3,36 m

 Jendela Berbingkai

Luas = 1,43 m Volume = 1,43 x 2

= 2,86 m 4. Type PTS ( 1 Bh )

 Kusen = Alumunium

Panjang = 16,5 m  Pintu Panil Kyu

Luas = 1,68 m  Kaca Mati

Luas = 2,62 m

5. Type P1 ( 4 Bh )

 Kusen = Alumunium

Panjang = 9,05 m Volume = 9,05 x 4

= 36,2 m  Pintu Panil Kayu

Luas = 2,73 m Volume = 2,73 x 4

= 10,92 m  Kaca Mati

Luas = 3,65 m Volume = 3,65 x 4

= 14,6 m 6. Type P2 ( 7 Bh )

 Kusen = Alumunium

Panjang = 7,5 m Volume = 7,5 x 7

= 52,5 m  Pintu Panil Kayu

Luas = 1,68 m Volume = 1,68 x 7

= 11,76 m  Kaca Mati

(18)

Volume = 0,52 x 7 = 3,64 m 7. Type P3 ( 2 Bh )

 Kusen = Alumunium

Panjang = 10,4 m Volume = 10,4 x 2

= 20,8 m  Pintu Kaca

Luas = 2,28 m Volume = 2,28 x 2

= 4,56 m  Kaca Mati

Luas = 1,1 m Volume = 1,1 x 2

= 2,2 m 8. Type P4 ( 10 Bh )

 Kusen = Alumunium

Panjang = 5,12 m Volume = 5,12 x 10

= 51,2 m  Pintu PVC

Luas = 1,57 m Volume = 1,57 x 10

= 15,7 m 9. Type J1 ( 10 Bh )

 Kusen = Alumunium

Panjang = 17,2 m Volume = 17,2 x 10

= 172 m  Daun Jendela

Luas = 2,37 m Volume = 2,37 x 10

= 23,7 m  Kaca Mati

Luas = 1,7 m Volume = 1,7 x 10

= 17 m 10. Type J2 ( 19 Bh )

 Kusen = Alumunium

Panjang = 11,8 m Volume = 11,8 x 19

= 224,2 m  Daun Jendela

Luas = 2,37 m Volume = 2,37 x 19

= 45,03 m  Kaca Mati

(19)

Volume = 0,85 x 19 = 16,15 m 11. Type J3 ( 4 Bh )

 Kusen = Alumunium 6 / 10 Panjang = 14,08 m

Volume = 14,08 x 4 = 56,32 m  Kaca Mati

Luas = 3,852 m Volume = 3,85 x 4

= 15,4 m 12. Type J4 ( 2 Bh )

 Kusen = Alumunium

Panjang = 9,9 m Volume = 9,9 x 2

= 19,8 m  Daun Jendela

Luas = 1,18 m Volume = 1,18 x 2

= 2,37 m  Kaca Mati

Luas = 0,85m Volume = 0,85 x 2

= 1,7 m 13. Type J5 ( 2 Bh )

 Kusen = Alumunium 6 / 10 Panjang = 13,14 m

Volume = 13,14 x 2 = 26,28 m  Kaca Mati

Luas = 2,772m Volume = 2,772 x 2

= 5,54 m 14. Type J6 ( 1 Bh )

 Kusen = Alumunium 6 / 10 Panjang = 20,6 m

 Kaca Mati

Luas = 3,68 m 15. Type V1 (2 Bh )

 Kusen = Alumunium

Panjang = 5,35 m Volume = 5,35 x 2

= 10,7 m  Daun Jendela

(20)

= 1,82 m 16. Type V2 ( 9 Bh )

 Kusen = Alumunium

Panjang = 3,1 m Volume = 3,1 x 9

= 27,9 m  Daun Jendela

Luas = 0,455 m Volume = 0,455 x 9

= 4,095 m VIII. PEKERJAAN LANTAI

1. Garaito 40 x 40 ( Polos )

Luas = 157,5 + 13,5 + 9 + 4,25 = 184,25 m

Volume = 184,25 – 4,8 = 179,45 m 2. Keramik Glasur 40 x 40

Luas = 24,4 m

3. Keramik 30 x 30 ( Putih ) Luas = 684,5 m 4. Keramik 30 x 30 ( abu – abu )

Luas = 323,23 m 5. Keramik 20 x 20

Luas = 38 m

6. Keramik Dinding 20 x 25 Panjang =51,9 Tinggi = 1,5 m Luas = 51,9 x 1,5

= 77,85 m IX. PEKERJAAN LANGIT – LANGIT

1. Pemasanga Rangka Metal Furring Luas = 1542,34 m 2. Pemesangan gypsum Board Luas = 723,09 m 3. Pemasangan Kalsiboard

Luas = 819,25 m

X. PEKERJAAN ATAP

1. Pekerjaan Kuda – Kuda Baja  Kuda – Kuda 1

Profile 60.60 . 6 Panjang = 55,22 m Berat kg / m = 5,42 Berat total = 55,22 x 5,42

= 299,2 Profile 80.80.8 Panjang = 51,24 m Barat kg / m = 8,72 Berat total = 51,24 x 8,72

= 446,8

(21)

= 746,01  Kuda – Kuda 2

Profile 60.60.6 Panjang = 73,69

Berat Total = 73,69 x 5,42 = 399,41 Profile 80.80.8 Panjang = 28,44 m Berat total = 28,44 x 8,72

= 247,4

BERAT KUDA – KUDA TYPE 2 = 399,41 + 247,4 = 646,838

 Kuda – Kuda 3 Profile 60.60.6 Panjang = 18,16 m Berat total = 18,16 x 5,42

= 98,42 Profile 80.80.8 Panjang = 25,78 m Berat total = 25,78 x 8,72

= 224,8

BERAT KUDA – KUDA TYPE 3 = 98,42 + 224 ,8 = 323,22

2. Gording 8 / 12

Panjang = 633,33 m

Volume = 0,08 x x 633,33 = 50,6 m 3. Usuk dan reng

Luas atap = 870,454 m 4. Nok

Panjang = 48,75 m 5. Bubungan

Panjang = 48,75 m XI. PEKERJAAN SANITASI

1. Jumlah Kloset Duduk = 7 bh 2. Jumlah Wastafel = 9 bh 3. Jumlah floor drain = 8 bh 4. Jumlah kran = 9 bh

5. Pasang Bak cuci stainlestil = 1 bh 6. Pasang bak mandi = 7 bh

7. Panjang Pipa air kotor padat = 29,73 m 8. Panjang pipa air kotor cair = 48,63 m 9. Pasang pipa beton = 195,65 m 10. Pasang pipa air bersih = 99,13 m XII. PEKERJAAN ISTALASI LISTRIK

(22)

Referensi

Dokumen terkait

Sensor Ultrasonik dapat mengukur ketinggian untuk perhitungan volume air dengan media penampungan air mini menggunakan pelampung berfungsi dan hasil pengukuran dengan sensor

menggunakan prisma, penelitian ini mencoba melakukan per- bandingan standar deviasi dari selisih elevasi hasil pengukuran Total Station Foif prisma dan nonprisma

Dari Gambar A.4 dapat dilihat semakin jauh jarak sliding maka semakin besar diameter kontak keausan yang terjadi pada pin.. Pin pada disc C memiliki diameter kontak

Jalan lokal dan -alan lingkungan yang dapat dilalui kendaraan 0ermotor termasuk muatan dengan ukuran le0ar tidak mele0ii 2.166 milimeter, ukuran pan-ang tidak

Pondasi menggunakan pondasi batu kali mengelili panjang bangunan (menerus). Volume gallian tanah dihitung dengan satuan m3. Urugan tanah kembali bawah pondasi setebal 10 cm. Setelah

Prinsip perhitungan metode ini mirip dengan metode koordinat dari segi bentuk yang diasumsikan, yaitu trapesium.. Gambar 3.Mencari Luasan Metode Trapezoidal’s Rule dengan

Sedangkan pada hasil perhitungan volume dengan data desain perencanaan, nilai acuan ketinggian untuk melakukan galian atau timbunan, menggunakan nilai elevasi kontur yang didapatkan

VALIDASI PERHITUNGAN LINGKUP VOLUME GLASSWARE LABU UKUR Koreksi Volume : 10 mL Massa = Massa isi- Massa kosong