BIDS AND AWARDS COMMITTEE 

Supplemental Bid Bulletin No. 1  November 9, 2015 

Department of Finance – 7

th

 Floor Office Renovation    

  This  Supplemental  Bid  Bulletin  No.  1  is  issued  to  modify  or  amend  the  item  in  the  Bid  Documents.  This shall form an integral part of the Bid Documents. 

 

REFERENCE 

 

AMENDMENT/CHANGE/CLARIFICATION  Section I. Invitation to Bid 

Item No. 8 

ACTIVITIES  SCHEDULE 

Advertisement/Posting  of Invitation to Bid 

October 23, 2015  

Issuance and Availability  of Bid Documents 

October 23, 2015 

Pre‐Bid Conference  October  30,  2015,  10:00 a.m. 

Request for Clarification  November  1,  2015  (thru Email)  

Issuance  of 

Supplemental  Bid  Bulletin 

November 4, 2015 

Deadline for Submission  of Bids 

November 11, 2015  8:45 a.m. 

Opening of Bids  November 11, 2015  10:00 a.m. 

   

Section I. Invitation to Bid  Item No. 8 

ACTIVITIES  SCHEDULE 

Advertisement/Posting  of Invitation to Bid 

October 23, 2015  

Issuance and Availability  of Bid Documents 

October 23, 2015 

Pre‐Bid Conference  October  30,  2015,  10:00 a.m. 

Request for Clarification  November  2,  2015  (thru Email)  

Issuance  of 

Supplemental  Bid  Bulletin 

November 9, 2015 

Deadline  for 

Submission of Bids 

November 16, 2015  9:45 a.m. 

Opening of Bids  November 16, 2015  11:30 a.m. 

Note:  All statements and formats referring to this  clause should be amended/corrected accordingly.

 

Section V. Special Conditions   

6.5 The Contractor shall employ the following Key  Personnel: 

 

1. Civil Engineer  2. Architect 

Section V. Special Conditions   

6.1.5 The Contractor shall employ the following key  personnel named in the scheduled of Key Personnel  with reference to 12.1 (b) Technical Documents, item  (ii.1) and (ii.2) Project Requirements : 

 

1. Project Manager/Architect  2. Civil Engineer 

(2)

3. Mechanical Engineer 

4. Plumbing Engineer/Master Plumber  5. Electrical Engineer 

6. Foremen   

The name, designation, license, background  employment record, and  experience of each key  personnel to be assigned to the project should be  presented in the attached  a. Key Personnel’s 

Certificate of Employment, and b. Contractor’s Letter‐

Certificate to the Department of Finance  format shown  as attached herewith and  must be submitted as part of  the technical documents. 

 

Note:  All statements and formats referring to this  clause should be amended/corrected accordingly.

Section VIII. Bill of Quantities   

2.3.1 Supply and installation of 600mm x 600mm acoustical ceiling tiles on metal tee runners and hanger rods

 

3.2.1 Troffer lights

3.3.1 One Gang Switch (Panasonic Wide Series)

3.3.2 Two Gang Switch (Panasonic Wide Series)

3.3.3 Three Gang Switch (Panasonic Wide Series)

3.3.4 Single Receptacle Outlet (Panasonic Wide Series)

3.3.5 Duplex Receptacle Outlet (Panasonic Wide Series)

3.3.6 Floor Outlet (Panasonic DU81831HTC)

         

4.1 Rehabilitation and relocation of existing ducting as required by the new layout and design

4.2.1 Flexible Duct (200mm x 3000mm) - l.m.

4.2.2 New Diffusers (4 way-400mm x 400mm) - sets

4.2.3 Plenum Box Collars - sets

4.5 Supply and installation of variable drives for all existing AHU’s including all necessary accessories

  5.1  

 

Relocation of existing sprinkler heads 

Section VIII. Bill of Quantities   

 

2.3.1 Supply and installation of 600mm x 1200mm acoustical ceiling tiles on metal tee runners and hanger rods 

 

3.2.1 Troffer lights ( See specifications indicated in the Plan Fumaco or

approved equal)

3.3.1 One Gang Switch (Panasonic Wide Series or approved equal)   

3.3.2 Two Gang Switch (Panasonic Wide Series or approved equal)   

3.3.3 Three Gang Switch (Panasonic Wide Series or approved  equal) 

 

3.3.4 Single Receptacle Outlet (Panasonic Wide Series or approved  equal) 

3.3.5 Duplex Receptacle Outlet (Panasonic Wide Series or approved  equal) 

3.3.6 Floor Outlet (Panasonic DU81831HTC or approved equal)   

     

4.1 Rehabilitation and relocation of existing ducting as required by the new layout and design ( Please refer to Plan on actual quantities) 

 

4.2.1 Flexible Duct 250mm dia x 3000mm (cost included in item 4.1) 

4.2.2 New Diffusers 4 way-400mm x 400mm (cost included in item 4.1)

4.2.3 Plenum Box Collars (cost included in item 4.1)   

4.5 Supply and installation of variable drives for 18.5KW/25HP Motor 62A, 3-Phase, 380-480V, 50-60Hz, UL Listed for the existing

(3)

3   

and lines as may be    affected by the  new layout and design  

5.2.1 25mm dia B.I. Pipe S-40 - l.m.

5.2.2 12mm dia Sprinkler Head - pcs.

 

6.1 Relocation of existing smoke detectors and supply and installation of new lines as required by the new layout and design

6.2.1 New smoke detectors (addressable) - sets 6.2.2 Relocate existing smoke detectors - sets

 

7.1

7.2.1

Supply and installation of structured cabling lines using CAT 6 wires for all offices and work stations

Fabricated Cable Tray - l.m.

7.2.2 Information Outlet (Cat6) - sets

7.2.3 Face Plates - sets

   

2 units AHU’s 68TR Capacity including all necessary accessories (submit material specification for approval)

 

5.1       Relocation of existing sprinkler heads and lines as may be     affected by the new layout and design ( Please refer to Plan on actual quantities)

 

5.2.1 25mm dia B.I. Pipe S-40 (cost included in item 5.1) 5.2.2 12mm dia Sprinkler Head (cost included in item 5.1)   

6.1 Relocation of existing smoke detectors and supply and installation of new lines as required by the new layout and design ( Please refer to Plan on actual quantities)

 

6.2.1 New smoke detectors addressable (cost included in item 6.1)

6.2.2 Relocate existing smoke detectors (cost included in item 6.1)

 

7.1 Supply and installation of structured cabling lines using CAT 6 wires for all offices and work stations ( Please refer to Plan on actual quantities)

7.2.1 Fabricated Cable Tray (cost included in item 7.1) 7.2.2 Information Outlet Cat6 (cost included in item 7.1) 7.2.3 Face Plates (cost included in item 7.1)

See attached: 

 

 Contractor’s Letter‐Certificate to the Department  of Finance 

 Key Personnel’s Certificate of Employment 

 General Notes 

 Riser Diagram 

 Load Schedule 

 Power Layout (Corrected) 

 Lighting Layout 

 Sprinkler Layout 

 Structured Cabling Layout 

 

 

 

For guidance and information of all concerned. 

     

                  GIL S. BELTRAN 

Undersecretary and    BAC Member   

     

(4)

Key Personnel’s Certificate of Employment   

Issuance Date   

Name of the Head of the Procuring Entity  Position of the Head of the Procuring Entity  Department of Finance 

Office of the Secretary, Department of Finance 

DOF Building, Roxas Blvd., corner P. Ocampo Sr. St., Manila   

Dear Sir/Madame: 

   

  I am (Name of Nominee) a Licensed ___________ Engineer with Professional License  No. _________ issued on (date of issuance) at (place of issuance). 

 

  I hereby  certify  that (Name  of Bidder) has engaged my services  as  (Designation)  for  (Name of Contract), if awarded to it. 

 

  As  (Designation),  I  supervised  the  following  completed  projects  similar  to  the  contract under bidding): 

 

NAME OF PROJECT  OWNER  COST  DATE COMPLETED 

       

       

       

 

  At present, I am supervising the following projects: 

 

NAME OF PROJECT  OWNER  COST  DATE COMPLETED 

       

       

       

 

  In  case  of  my  separation  for  any  reason  whatsoever  from  the  above‐mentioned  Contractor, I shall notify the Department of Finance at least twenty one (21) days before the  effective date of my separation. 

 

  As (Designation), I know I will have to stay in the job site all the time to supervise and  manage  the  Contract  works  to  the  best  of  my  ability,  and  aware  that  I  am  authorized  to  handle only one (1) contract at a time. 

 

  I do not allow the use of my name for the purpose of enabling the above‐mentioned 

Contractor to qualify for the  Contract without any firm commitment on my part to assume 

the post of (Designation) therefore, if the contract is awarded to him since I understand that 

to  do  so  will  be  a  sufficient  ground  for  my  disqualification  as  (Designation)  in  any  future 

Department of Finance bidding or employment with any Contractor doing business with the 

Department of Finance. 

(5)

     

 

DRY SEAL   

  IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month] 

[year] at [place of execution]. 

     

             

(Signature of Engineer) 

           Affiant 

 

  SUBSCRIED AND SWORN to before me this ___ day of [month] [year] at [place of execution],  Philippines. Affiant/s is/are personally known to me and was/were identified by me through 

competent evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No. 02‐8‐13‐

SC). Affiant/s exhibited to me his/her [insert type of government identification card used], with  his/her photograph and signature appearing thereon, with no. ____ and his/her [name of  identification card]  issued on ____ at  ____. 

  Witness my hand and seal this ___ day of [month] [year]. 

 

        NAME OF NOTARY PUBLIC 

        Serial No. of Commission ________ 

        Notary Public for _____ until _____ 

        Roll of Attorneys No. _______ 

        PTR No. ____, [date issued], [place issued] 

        IBP No. ____, [date issued] [place issued] 

    Doc. No. ____ 

Page No. ____ 

Book No. ____ 

Series of_____ 

 

(6)

Contractor’s Letter‐Certificate to the Department of Finance  Date: ____________________ 

 

Name of the Head of the Procuring Entity  Position of the Head of the Procuring Entity  Department of Finance 

Office of the Secretary, Department of Finance 

DOF Building, Roxas Blvd., corner P. Ocampo Sr. St., Manila   

Dear Sir/Madame: 

 

Supplementing our Organizational Chart for the Contract, we have the honor to submit herewith,  and to certify as true and correct, the following pertinent information: 

 

1.  That I/we have engaged the services of (Name of Employee), to be the (Designation) of the 

(Name of Contract), who is a (Profession) with Professional License Certificate No. _______ 

issued on _____________ and who has performed the duties in the construction of the  Contracts enumerated in the duly filled Form       . 

 

2. The said Engineer shall be designated by us as our (Designation) to personally perform the  duties of the said position in the above‐mentioned Project, if and when the same is awarded  in our favor. 

 

3. That said Engineer shall employ the best care, skill and ability in performing his duties in  accordance with the Contract Agreement, Conditions of Contract, Plans, Specifications,  Special Provisions, and other provisions embodied in the proposed contract. 

 

4. That said Engineer shall be personally present at the jobsite to supervise the phase of the  construction work pertaining to this assignment as (Designation), all the time. 

 

5. That, in order to guarantee that said Engineer shall perform his duties properly and be  personally present in the Job Site, he is hereby required to secure a certificate of appearance  for the Department of Finance representative/consultant at the end of every month. 

 

That, in the event that I/we elect or choose to replace said (Designation) with another  Engineer, the Department of Finance (DOF) will be accordingly notified by us in writing at  least twenty one (21) days before making the replacement.  We will submit to the DOF, for  prior approval, the name of the proposed new (Designation), his qualifications, experience,  list of projects undertaken and other relevant information. 

 

6. That any willful violation on my/our part of the herein conditions may prejudice my/our  standing as a reliable contractor in future bidding of the Department of Finance. 

  Very truly yours, 

_______________________________ 

(Authorized Representative of Bidder)   

CONCURRED IN: 

_______________________________ 

  (Name of Engineer) 

_______________________________ 

  (Address)   

Referensi

Dokumen terkait

*Frosted glass sticker supply, delivery and installation cost shall be incorporated in the corresponding glass works bid cost.. For guidance and information of all

Republic of the Philippines DEPARTMENT OF FINANCE Roxas Boulevard Corner Pablo Ocampo, Sr.. Street Manila 1004 BIDS AND AWARDS COMMITTEE Supplemental Bid Bulletin

3 September 24, 2021 Procurement of Various Food Items for the Department of Finance ITB No.. 3 is issued to modify or amend the item in the Bid

Audited financial statements, stamped “received” by the Bureau of Internal Revenue BIR or its duly accredited and authorized institutions, for the preceding calendar year, which should

Special Conditions of Contract GCC Clause 1 The DOF reserves the right to increase or reduce the number of shuttle service for any given period on the duration of the contract..

6:am-3:pm Elevator/Hallway/Driver Lounge/Fire Exit 6:am-3:pm Parking Area /segregate/dispose garbage 6:am-3:pm PMT/Cash/Clinic 11:am-8:pm Entrance/Guard Office/CR Male& Female

The schedule of bidding activities is as follows: ACTIVITIES DATES Issuance and Availability of Bidding Documents March 6, 2015 Friday Pre-Bid Conference March 19, 2015

REFERENCE AMENDMENT/CHANGE/CLARIFICATION Page 26 Schedule of Requirements Item Number Description Quantity Delivered, Weeks / Months 1 One 1 Unit Manage Service Cisco