Bidder – Refers to a contractor, manufacturer, supplier, distributor and/or consultant who submits a bid in response to the requirements of the Bidding Documents. Bidding Documents – The documents issued by the procuring entity as a basis for bids, which provide all the information necessary for a potential bidder to prepare a bid for the goods, infrastructure projects and/or consultancy services required by the procuring entity. Contract – Refers to the agreement entered into between the procuring entity and the supplier, manufacturer, distributor or service provider for the purchase of goods and services;

A procurement project must be described, detailed and planned in the project procurement management plan prepared by the agency and which will be consolidated in the annual procurement plan of the procuring entity.

Invitation to Bid

Improvement of the existing and installation of a new pump house with motor for the field at the PhilRice. The Philippine Rice Research Institute now invites contractors with a PCAB license of at least Category C & D/Small B for the above-mentioned tender project. The bids will be opened in the presence of the bidders' representatives (a limited number only) who choose to be present at the address below.

The opening of the bids will take place at the schedule given below and the bids will be opened in the presence of the representatives of the bidders who choose to participate in the activity.

Instructions to Bidders

  • Scope of Bid
  • Funding Information
  • Bidding Requirements
  • Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices
  • Eligible Bidders
  • Origin of Associated Goods
  • Subcontracts
  • Pre-Bid Conference
  • Clarification and Amendment of Bidding Documents
  • Documents Comprising the Bid: Eligibility and Technical Components
  • Documents Comprising the Bid: Financial Component
  • Alternative Bids
  • Bid Prices
  • Bid and Payment Currencies
  • Bid Security
  • Sealing and Marking of Bids
  • Deadline for Submission of Bids
  • Opening and Preliminary Examination of Bids
  • Detailed Evaluation and Comparison of Bids
  • Post Qualification
  • Signing of the Contract

Bidders must meet the eligibility criteria in accordance with Section 23.4.2 of IRR 2016 no. RA. Any bid exceeding the ABC stated in paragraph 1 of the IB will not be accepted. The customer may request additional printed and/or electronic copies of the offer.

The preliminary review of offers will be regulated by Article 30 of the revised IRR in 2016 of RSH No.

Bid Data Sheet

Key Personnel General Experience Relevant Experience Project Manager Project Management 5 years Project Engineer General Construction 5 years Materials Engineer Materials Testing 5 years In-house Health & Occupational Health. The amount of not less than Php Insert two percent (2%) of ABC] if the bid security is cash, cashier's/manager's check, banker's check/guarantee or irrevocable letter of credit;. 21 Additional contract documents relevant to the project that may be required by existing laws and/or the procuring entity, such as construction plan and S-curve, manpower plan, construction methods, equipment usage schedule, construction safety and health program approved by DOLE , and other acceptable tools for project planning.

General Conditions of Contract

  • Scope of Contract
  • Sectional Completion of Works
  • Possession of Site
  • The Contractor’s Obligations
  • Performance Security
  • Site Investigation Reports
  • Warranty
  • Liability of the Contractor
  • Termination for Other Causes
  • Dayworks
  • Program of Work
  • Instructions, Inspections and Audits
  • Advance Payment
  • Progress Payments
  • Operating and Maintenance Manuals

The contracting authority will transfer the entire construction site or parts thereof to the contractor on the basis of the delivery schedule indicated in the VCA, which corresponds to the execution of the works. If possession of a share is not given before the above date, the contracting authority is deemed to have postponed the start of the relevant activities. By entering into the contract with the contracting authority, the contractor acknowledges the right of the contracting authority to take action in accordance with RA No.

Pursuant to the Change Order Guidelines in Appendix “E” of the Revised IRR of 2016 RA No.

Special Conditions of Contract

7.2 [In the case of permanent structures, such as Type 4 and 5 buildings as classified under the National Building Code of the Philippines and other structures made of steel, iron or concrete that comply with relevant structural codes (e.g. DPWH Standard Specifications) , such as, but not limited to, steel/concrete bridges, flyovers, aircraft movement areas, harbors, dams, tunnels, filtration and treatment plants, sewage systems, power plants, transmission and communication towers, railway systems and other similar permanent structures :] Fifteen (15) years. In the case of semi-permanent structures such as Type 1, 2 and 3 buildings as classified under the National Building Code of the Philippines, concrete/asphalt roads, concrete flood control, drainage, irrigation canals, river landing, deep wells, rock bridge, footbridge and other similar semi-permanent structures:] Five (5) years. In the case of other structures such as bailey and wooden bridges, shallow wells, spring developments and other similar structures:] Two (2) years.

13 The advance amount is not more than 15% of the total contract price. 14 Materials and equipment delivered to the site but not fully installed will not be included in the payment. Work Progress Photographs (in print and on CD for electronic copy) Refer to Section VI for full details of the Closed Report.

Specifications

The cost of the samples together with the transport, delivery and any other costs shall be borne by the Contractor. Lighting Fixtures: Lighting points, unless otherwise specified, shall be provided and installed by the Contractor.

Drawings

Bill of Quantities

Pursuant to your invitation to bid for the above project, we - (or I) propose to supply, deliver, place and complete all necessary materials, labor, plant, tools, appliances and equipment, supplies, supplies, transportation, supervision, supervision and other facilities in connection therewith subject to all conditions and requirements thereto, and to perform all operations necessary to complete the project within CALENDAR DAYS (____ CD) at our (my) expense, for the following lump sum Bid Price, in Philippine currency . We (or I) make this proposal knowing that all provisions of the general specifications applicable to the work, unless otherwise stated, and to the extent that they do not conflict with the provisions of the contract drawing, shall form an essential part of this proposal . We (or I) make this proposal with full knowledge of the nature, quantity and quality of articles and services required, and if this proposal is accepted, we (or I) after receiving notice of acceptance will contract with PHILRICE with good and sufficient security for faithful performance thereof.

We (or I) will not request any extension of time due to delay in procurement of materials needed in construction. We (or I) understand that the proposed amount submitted herein contained provisions for the payment of all applicable taxes (contractor's and other taxes) with the stipulation, however, that should there be any exemption from the payment of those taxes, shall such exemptions be credited to PHILRICE. We (or I) hereby certify that we (or I) have prepared and/or checked and reviewed the construction procedures and prices in this proposal; and under complete supervision said construction procedures, schedule and prices are sufficient for the proper execution and successful prosecution of the work required herein.

PROJECT: Improvement of existing and installation of new pump houses with engine for the research field. PROJECTS : IMPROVEMENT OF EXISTING AND INSTALLATION OF NEW PUMP HOUSES WITH ENGINES FOR THE RESEARCH FIELD. Concrete drip inlet with control plate (Portland cement, 40 kg/bag, type 1 (quick set), washed sand; S-1 and 3/4 crushed gravel).

Checklist of Technical and Financial Documents

2005, as finally reviewed and approved by And the Bureau of Internal Revenue (BIR). f) Statement by the potential bidder on all its ongoing public and private contracts, including any awarded but not yet commenced, whether or not they are comparable in nature and complexity to the contract to be awarded; And. g) Declaration of the bidder's Single Largest Completed Contract (SLCC), similar to the contract to be bid for, except under the conditions specified in the rules; h) and license from the Philippine Contractors Accreditation Board (PCAB); Special PCAB license in case of joint ventures; and registration of the type and costs of the contract to be awarded; And. i) Original copy of Bid Security. Each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information contained therein are true and correct;

Bidder's name] authorizes the head of the client or his duly authorized representative to verify all submitted documents;. If Sole Proprietor:] The Owner or Sole Proprietor is not related to the Head of the Client, Members of the Bidding and Award Committee (BAC), Technical Working Groups and the BAC Secretariat, Head of the Project Management Office. or end-user unit and project consultants by consanguinity or consanguinity up to the third civil degree;. If a company or joint venture:] None of the officers, directors and controlling shareholders of [bidder's name] are related to the head of the procuring entity, the members of the Bids and Awards Committee (BAC), the technical working groups, and the BAC secretariat, the head of the project management office or units for end users and project consultants by consanguinity or consanguinity up to the third civil degree;.

Making an assessment of the facilities available and required for the contract bid, if any; and. Bidder's Name] has not given or paid, directly or indirectly, any commission, sum, fee or any form of compensation, cash or otherwise, to any person or government official, personnel or representative in connection with any project or procurement activity. . I/we agree that: (a) I/we shall be automatically disqualified from bidding on any procurement contract with any procuring entity for a period of two (2) years after receipt of your blacklisting order; and, (b) I/we will pay the applicable penalty provided for in Section 6 of the Instructions for the Use of the Bid Security Statement within fifteen (15) days of receipt of the written request from the procuring entity to perform the actions that result in the implementation of the bid security declaration according to article 23.1(b and 69.1), with the exception of 69.1(f), of the IRR of RSH No.

Upon expiry of the validity period of the bid, or any extension thereof in terms of your request;. I/we understand that, according to your conditions, in order to guarantee the faithful performance by the supplier/distributor/manufacturer/contractor/consultant of its obligations under the Contract, I/we will issue a Performance Assurance Statement within a maximum period of ten ( 10) calendar days from the receipt of the Notice of Award prior to the signing of the Contract.

Forms

Referensi

Dokumen terkait

The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the site, determined the general characteristics of the contracted Works and the conditions for this

The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the site, determined the general characteristics of the contracted Works and the conditions for this