QUARTERLY REPORT
For the Fourth (4
th
) Quarter of the Year 2016
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Table Of Contents
1 Executive Summary ... 1
1.1 Current Implementation Situation ... 1
1.1.1 Civil Works... 1
1.1.2 Consultancy Services ... 4
1.2
Current Status of Loan... 5
1.3
Current Problems and Action Required ... 5
2
General... 6
2.1
Reporting Requirements ... 6
2.2
Loan Status
... 7
2.3
Financial Management ... 7
2.4
Project Cost Monitoring ... 8
2.5
World Bank Implementation Review Mission and Site Visit ... 8
2.6
Project Steering Committee Meeting ... 9
3
Project Management and Implementation... 10
3.1
Procurement Status ... 10
3.2
Implementation Status
Civil Works... 11
3.3
Variation Order Details ... 19
3.4
Consultancy Services... 21
3.5
Implementation of the Anti-Corruption A c t i o n Plan ... 23
3.6
Implementation of the Environmental Management Plan and LARAP... 24
4
Road Safety Audit ... 26
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
APPENDICES
Appendix S-1
:
Summary of Studies and Reports (Environmental Activity)
Appendix S-2
:
Summary of Studies and Reports (Social Activity)
Appendix S-3
:
Community Development Activity Reports
Appendix S-4
:
Community Representative Observers (CRO) Reports
Appendix 1
:
Disbursement and Expenditures Status
Appendix 2
:
Report At The End of The Quarter (December 2016)
Appendix 3
:
Detailed Summary of the Project Cost Monitoring
Appendix 4
:
Procurement Management of Civil Works
Appendix 5
:
Procurement Plan for Consulting Services
Appendix 6
:
List of Names of Community Representative Observers (CRO)
Appendix 7
:
Anti Corruption Action Plan (ACAP)
Activity Progress of Community Representative Observers (CRO)
Appendix 8
:
List of Appointed Third Party Monitors (TPM)
Appendix 9
:
Progress of Third Party Monitoring (TPM) Activities
Appendix 10
:
Complaints Handling Mechanism System (CHS)
Appendix 11
:
Work Activities On Publication/Disclosure
Appendix 12
:
Environmental Safeguards
Appendix 13
:
Environmental Management Plan (EMP) Compliance
Appendix 14
:
Status of Monitoring of Environmental Mitigation
Appendix 15
:
Overall Land Acquisition Status as of End of December 2016
Appendix 16
:
Status of Road Safety Audits
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
ANNEXES
Annex P-1
:
Package No. 1 (Biha
Krui)
Annex P-2
:
Package No. 2 (Pd. Sawah
Sp. Empat)
Annex P-3
:
Package No. 3 (Manggopoh
Pd. Sawah)
Annex P-4
:
Package No. 4 (Ipuh
Bantal)
Annex P-5
:
Package No. 5 (Sp. Rampa
Poriaha)
Annex P-6
:
Package No. 6 (Ps. Pedati
Kerkap)
Annex P-7
:
Package No. 7 (Indrapura
Tapan)
Annex P-8
:
Package No. 8 (Bts. Kota Pariaman - Manggopoh)
Annex P-11
:
Package No. 11 (Bantal
Mukomuko)
Annex P-12
:
Package No. 12 (Kambang - Indrapura)
Annex P-13
:
Package No. 13 (Sp. Rukis
Tj. Kemuning)
Annex P-14
:
Package No. 14 (Painan - Kambang)
Annex P-15
:
Package No. 15 (Sibolga
Bts. Tapsel)
Annex P-16
:
Package No. 16 (Seblat
Ipuh)
Annex P-17
:
Package No. 17 (Sp. Gunung Kemala
Pugung Tampak)
Annex P-19
:
Package No. 19 (Lais
Bintunan)
Annex P-20
:
Package No. 20 (Lubuk Alung - Sicincin)
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
1
1 Executive Summary
1.1 Current Implementation Situation
1.1.1 Civil Works
Implementation of the WINRIP Project is scheduled to be implemented into three (3)
Annual Work Programs (AWP's). The implementation starts with the preparation of
tender documents (detailed design drawings including associated bidding documents),
tendering stage (procurement of works) and the actual civil works construction
implementation.
The original implementation schedules of the three (3) Annual Work Programs (AWPs)
are scheduled in three (3) phases, namely ; AWP-1 to start in mid-2011 and to be
completed on the last quarter of 2014, AWP-2 is expected to begin in mid 2012 with
target date of completion by mid-2016 and AWP-3 is expected to start during the early
part of 2013 and to be completed during the middle part of 2017.
However, due to some unavoidable circumstances the original implementation
schedules did not materialized.
Based on the present status of the program implementation progress, a revised
implementation schedule, the Project Implementation Timeline (as shown on
Page 2
) is
to be implemented in order to accommodate the originally delayed schedule into the
remaining time frame of the WINRIP Program until the expiry date of the loan
agreement by the end of
December 2017
. Shown on
Page 3
is the current construction
status of the implementation relative to the Project Implementation Timeline.
Table 1
[image:6.595.134.555.479.745.2]shows the present status.
Table 1 - Implementation Status as of End of the 4
th
Quarter on December 31, 2016
Pack
Package Name
Contract
Under
Under Defect Liability
Period
No.
Sign
Construct
1
Krui - Biha
√
Completed
√
2
Padang Sawah - Sp.Empat
√
Completed
√
3
Manggopoh - Padang Sawah
√
Completed
√
4
Ipuh - Bantal
√
Completed
√
5
Sp. Rampa - Poriaha
√
√
6
Ps. Pedati - Kerkap
√
√
7
Indrapura - Tapan
√
√
8
Bts.Pariaman - Manggopoh
√
√
11
Bantal - Mukomuko
√
√
12
Kambang - Indrapura
√
√
13
Sp. Rukis - Tj.Kemuning
√
√
14
Painan - Kambang
√
√
15
Sibolga - Bts.Tap Sel
√
√
16
Seblat - Ipuh
√
√
17
Sp.Gn.Kemala - Pg.Tampak
√
√
19
Lais - Bintunan
√
Completed
√
20
Lubuk Alung - Sicincin
√
√
21
Lubuk Alung - Kuraijati
√
√
T O T A L :
18
13
5
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
2
Project Implementation Timeline
Length
C'ti on
Km
Peri od
J
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
1
Krui - Biha
25,00
21 mth
2
Padang Sawah - Sp.Em pat
40,90
24 mth
3
Manggopoh - Padang Sawah
32,00
24 mth
4
Ipuh - Bantal
42,40
24 mth
5
SI MPANG RAMPA - PORI AHA
11,10
18 mth
11
BANTAL - MUKOMUKO
50,10
24 mth
13
SP RUKIS - TJ KEMUNING
56,30
24 mth
17
Sp.Gn.KEMALA - Pg. TAMPAK
36,80
24 mth
6
PS. PEDATI - KERKAP
25,00
15 mth
19
LAI S - BI NTUNAN
11,60
10 mth
15
SI BOLGA - BATAS TAPSEL
36,00
27 mth
7
I NDRAPURA - TAPAN
19,50
21 mth
8
BTS.Kt PARI AMAN-MANGGOPOH
46,80
24 mth
10
SI MPANG EMPAT - SP.AI R BALAM
61,70
24 mth
12
KAMBANG - I NDRAPURA
55,20
24 mth
14
PAI NAN KAMBANG
31,50
21 mth
16
SEBLAT I PUH
34,50
21 mth
20
LUBUK ALUNG SI CI NCI N
14,60
18 mth
21
LUBUK ALUNG KURAI TAJI
16,80
18 mth
9
RANTAU TI JANG-KOTA AGUNG
42,00
The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
18
MUKOMUKO-BTS SUMBAR
25,80
The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
Original target :
715,60
km
ENVIRONMENT & SOCIAL SAFEGUARD
Revised target :
640,00 km
Prequalification
Detail Eng Design
LARAP Study
Road Safety
Owner's Estimate
Appraisal & Public Consultation
Procurement & Sign Contr
Bid Document
LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
CONSTRUCTION
CONSTRUCTION
Rev-DED RS
DED
COW
PROC
COW
CONSTRUCTION
OE & BD
DED
Rev-DED RS
OE & BD
OE & BD
DED
OE & BD
COW
CONSTRUCTION
SBD & OE + BD
SBD & OE + BD
PQ
PROC
PROC
CONSTRUCTION
DED
RSA & REVISED DED
CONSTRUCTION
PQ
RS
Proc
COW
SBD
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
DED
RSA & REVISED DED
OE & BD
DED
RSA & REVISED DED
OE & BD
OE
BD
DED
SBD & OE + BD
Rev-DED RS
DED
Rev-DED RS
OE & BD
DED
RSA & REVISED DED
OE & BD
CONSTRUCTION
PROC
COW
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS
PQ
CONSTRUCTION
Review DED & RS
PQ
PROC
COW
Review DED & RS
PQ
COW
CONSTRUCTION
PROC
Pack
#
PACKAGE NAME
2012
2013
2014
2015
2016
2017
2018
PROC
COW
PROC
COW
PROC
COW
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
COW
PROC
COW
PROC
COW
PROC
CONSTRUCTION
CONSTRUCTION
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
3
Actual Implementation Timeline of WINRIP
Length
C'ti on
Km
Peri od
J N D
J
F M A M J
J A S O N D
J
F M A M J
J A S O N D
J
F M A M J
J A S O N D
J
F M A M J
J A S O N D
J
F M A M J
J A S O N D
J
F M A M J
J A S O N D
Core Team Consultant (CTC)
40 mth
IMPLEMENTATION
Time extension for sevices
Design & Supervision Cslt (DSC)
42 mth
IMPLEMENTATION
Time extension for sevices
TA for Dev.of Sl ope Sta bi l i za ti on, Desi gn & M a na gement
1
Krui - Biha
25,00
21 mth
8 Jan'14
2
Padang Sawah - Sp.Empat
40,90
24 mth
6 Jan'14
3
M anggopoh - Padang Sawah
32,00
24 mth
6 Jan'14
4
Ipuh - Bantal
42,40
24 mth
10 Jan'14
5
SIMPANG RAMPA - PORIAHA
11,10
18 mth
18 Jun'15
20 Jul'17
11
BANTAL - MUKOMUKO
50,10
24 mth
23 Feb'15
11 Feb'17
13
SP RUKIS - TJ KEMUNING
56,30
24 mth
11 Feb'17
17
Sp.Gn.KEMALA - Pg. TAMPAK
36,80
24 mth
04 Sep'15
23 Agt'17
6
PS. PEDATI - KERKAP
25,00
15 mth
11 Mar'15
19
LAIS - BINTUNAN
11,60
10 mth
11 Mar'15
CONSTRUCTION 300+125+53 days
30 Jun '16
15
SIBOLGA - BATAS TAPSEL
36,00
27 mth
20 Nov'15
7
INDRAPURA - TAPAN
19,50
21 mth
10 Dec'15
30 Agt'17
8
BTS.Kt PARIAMAN-MANGGOPOH
46,80
24 mth
PROC
23 Mar'16
10
SIMPANG EMPAT - SP.AIR BALAM
61,70
24 mth
12
KAMBANG - INDRAPURA
55,20
24 mth
14
PAINAN KAMBANG
31,50
21 mth
PROC
13 Aug'16
16
SEBLAT IPUH
34,50
21 mth
8 Nov'16
CONSTRUCTION
20
LUBUK ALUNG SICINCIN
14,60
18 mth
1 Sep'16
21
LUBUK ALUNG KURAITAJI
16,80
18 mth
1 Sep'16
Original target :
715,60
km
ENVIRONMENT & SOCIAL SAFEGUARD
1st Revised target :
640,00 km
Prequalification
Detail Eng Design
LARAP Study
Road Safety
Owner's Estimate
Appraisal & Public Consultation
Procurement & Sign Contr
Bid Document
LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
28 Jan'17
30-Des-17
30-Des-17
PROC
PROC
to be canceled
CONSTRUCTION 720 - 71 days
Rev-DED RS
Rev-DED RS
Rev-DED RS
31-Des-17
30-Des-17
PROCUREMENT
IMPLEMENTATION
31-Des-17
31-Des-17
31-Des-17
CONSTRUCTION 450 + 240 days
31-Des-17
CONSTRUCTION 540 - 53 days
31-Des-17
CONSTRUCTION 540 - 53 days
CONSTRUCTION 630 - 114 days
6-Nov-12
19-Jun-13
PROC
PROC
DED
Rev-DED RS
ICB
ICB
NCB
NCB
DED
PROC
CONSTRUCTION 720 days
ICB
ICB
ICB
ICB
PROC
CONSTRUCTION 810 - 37 days
DED
CONSTRUCTION 630 days
23-Mei-16
CONSTRUCTION 720 - 132 days
NCB
NCB
NCB
Review DED & RS
Review DED & RS
SBD & OE + BD
RSA & REVISED DED
OE & BD
DED
RSA & REVISED DED
OE & BD
SBD & OE + BD
DED
RSA & REVISED DED
OE & BD
DED
ICB
RSA & REVISED DED
OE & BD
Review DED & RS
SBD & OE + BD
PQ
RS
Proc
COW
SBD
DED
OE
BD
DED
NCB
NCB
DED
Pack
#
PACKAGE NAME
2012
2013
2014
2015
2016
2017
2018
ICB
ICB
ICB
ICB
ICB
#########
CONSTRUCTION 640 + 93 days
14-Apr-16
PROC
17-Mar-16
CONSTRUCTION 540 + 224 days
CONSTRUCTION 730 + 105 days
CONSTRUCTION 730 + 75 days
CONSTRUCTION 730 + 90 days
31-Mei-16
Review DED & RS
PQ
Review DED & RS
PQ
PQ
Review DED & RS
Review DED & RS
PROC
CONSTRUCTION 720 days
CONSTRUCTION 720 days
22-Jul-15
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
4
1.1.2 Consultancy Services
TA Consultant
Planned
Mobilization
Contract
Signed
Actual
Mobilization
CTC
Jul 2012
5 Nov 2012
12 Nov 2012
DSC
Jul 2012
11 Jun 2013
19 Jun 2013
Capacity Building for Disaster
Risks Reduction
Cancelled
Development of Slope
Stabilization, Design and
Management
January 2017
Capacity Building for
Environmental Management
Cancelled
Capacity Building for
Road Safety
Cancelled
The technical assistance for consultancy of Capacity Building For Disaster Risk
Reduction has been deleted, but replaced by
Technical Assistance for
Development of Slope Stabilization, Design and Management .
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
5
1.2
Current Status of Loan
At the end of this quarter on December 31, 2016 some 40.47% or USD 101.18 million of the
available loan had been disbursed, which is 7.85% over the revised forecasted expenditures
of 26.00% (USD 65.00 million) at the end of the quarter.
Total disbursements during this Quarter amounted to USD 26.79 million covering the
payments for "Statement of Work Accomplished' (MC) to civil works Contractors of the
on-going construction packages and advance payments to Contractors of newly started
contract packages. Details of the Disbursements and Expenditures Status are presented
in
Appendix 1
.
A more detailed and updated status of the loan are fully described and presented in
sixtenth (16
th
) Quarterly Financial Report covering the 4
th
Quarter
(October-November-December) of the Year 2016 which is under preparation and will be submitted separately.
1.3
Current Problems and Action Required
Program
Activity
Responsibility
AWP-1
4 Nos. Completed and provisionally handed over. Under defects
liability period for seven hundred and thirty (730) days.
Contractor, PPK and
DSC
AWP-2 & AWP-3
13Nos.Four (4) packages out of the thirteen (13) packages
under construction are way behind schedule with huge
percentages
of
negative
progress
slippages.
Contractors of the problematic packages shall resolve
immediately the current problems. PPK and DSC shall
closely monitor the activities of the Contractor.
1 No. Completed and provisionally handed over. Under defects
liability period for seven hundred and thirty (730) days.
2 Nos. Cancelled.
1 Nos. Proposal to be Cancelled.
Contractor and
PPK and DSC
Contractor, PPK and DSC.
Capacity Building for
Disaster Risks Reduction
Cancelled
Technical Assistance for
Development of Slope
Stabilization, Design and
Management
Still in selection process.
POKJA, Sub-Directorate of
Geotechnical and Slope
Management, Directorate of
Road Construction, DGH,
MPWH
Capacity Building for
Environmental
Management
Cancelled
Capacity Building for
-2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
6
2
General
2.1
Reporting Requirements
Quarterly Progress Reports
:
This is twelfth (12
th
) Quarterly Progress Report as
required and stipulated in CTC's consultancy contract and the Loan Agreement. Prior
to the production of this report, Monthly Progress Reports have been prepared and
have dealt with all aspects of the works. This report attempts to bring the situation up
to date by covering overall progress up to the end of fourth (4
th
) Quarter of the Year
2016.
Financial Monitoring Reports
:
These have been prepared for each quarter since the
beginning of 2013 with the first Report, issued in May 2013, covering the period
January
March 2013. Since that date quarterly reports have been prepared and
submitted regularly.
Report
Period Covered
Date Issued
Financial Monitoring Report No. 1
January 2013
March 2013
May 15, 2013
Financial Monitoring Report No. 2
April 2013
June 2013
August 15, 2013
Financial Monitoring Report No. 3
July 2013
September 2013
November 15, 2013
Financial Monitoring Report No. 4
October 2013
December 2013
February 15, 2014
Financial Monitoring Report No. 5
January 2014
March 2014
May 15, 2014
Financial Monitoring Report No. 6
April 2014
June 2014
August 15, 2014
Financial Monitoring Report No. 7
July 2014
September 2014
November 15, 2014
Financial Monitoring Report No. 8
October 2014
December 2014
April 7, 2015
Financial Monitoring Report No. 9
January 2015
March 2015
August 31, 2015
Financial Monitoring Report No. 10
April 2015
June 2015
October 2, 2015
Financial Monitoring Report No. 11
July 2015
September 2015
December 16, 2015
Financial Monitoring Report No. 12
October 2015
December 2015
February 10, 2016
Financial Monitoring Report No. 13
January 2016
March 2016
June 8, 2016
Financial Monitoring Report No. 14
April 2016
June 2016
August 25, 2016
Financial Monitoring Report No. 15
July 2016
September 2016
December 2, 2016
Financial Monitoring Report No. 16
October 2016
December 2016
Under Preparation
CTC Monthly Progress Reports
:
These report have been prepared covering each full
month since January 2013. Subsequent reports have been submitted on a regular
monthly basis.
Environmental Studies and Activity Reports
:
These report have been continuously
updated and submitted to PMU for submission to World Bank for Bank's issuance of No
Objection Letter (NOL).
Appendix S-1
shows the summary of submitted of Reports
covering each contract package since inception of the Project.
Social Impact Studies and Activity Reports
:
These report which mainly dealt with the
implementation of "Land Acquisition Resettlement Action Plan" (LARAP) have been
continuously submitted to PMU for submission to World Bank for Bank's issuance of
No Objection Letter (NOL).
Appendix S-2
indicates the updated summary of all
submitted Reports.
Anti-Corruption Action Plan (ACAP) : Community Development Activity Reports
:
These Reports have been prepared and continuously submitted to the Client.
Appendix S-3
shows the summary of submitted Reports from the very first (1
st
)
submittal up to latest report before the Quarter ended.
Community Representative Observers (CRO) and Third Party Monitoring (TPM)
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
7
submitted by the appointed CRO's and TPMs of the respective contract package.
Their reports were based on their actual observations and monitoring during pre
-bid meetings, site visit and -bid openings of every contract package under procurement.
Appendix S-4
shows the updated summary of all reports which were forwarded to PMU.
2.2
Loan Status
The agreed allocation of loan funds from the original loan agreement together with the %
disbursed by the World Bank to the end of the quarter date (September 30, 2016) is
[image:12.595.99.558.526.738.2]presented in
Table 2
Table 2
Category
Description
Loan Restructuring
Amount US$
Total Disbursement
for the 3
rd
Quarter of
2016
Previous
Disbursement
Total Disbursed by
WB to End December
31, 2016 in US$
% Disbursed
1
Part 1
Betterment and
Capacity Expansion of National
Roads.
220,400,000.00
19,454,368.91
74,935,762.23
94,390,131.14
42.83
2
Part 2
Implementation Support
17,000,000.00
0
6,790,105.83
6,790,105.83
39.94
3
Part 3
Road Sector Institutional
Development
0
0
0
0
0
4
Part 4
Contingency for Disaster Risk
Response
0
0
0
0
0
Unallocated
12,600,000.00
0
0
0
0
Original Loan
Amount
250,000,000.00
19,454,368.91
81,725,868.06
101,180,236.97
40.47
2.3
Financial Management
S-Curve for Financial Progress
A report at the end of the quarter (Decmber 31, 2016) is presented in
Appendix 2
#REF!
1.25
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Month
%
Co
m
pl
et
e
Actual Expenditure USD
101.18 mil (40.47 %)
WINRIP ACTUAL PROGRESS UP TO DECEMBER 2016 AND FORECAST UP TO JUNE 2018
ACTUAL Dec 2016
Original Forecast
Forecast Expenditure Rev
USD
65.00 mil
(26.00%)
Forecast Dec 2016
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
8
2.4
Project Cost Monitoring
A detailed summary of the project cost monitoring in tabular format is presented as
Appendix 3
at the end of this report.
2.5
World Bank Implementation Review Mission and Site Visit
During this 4
th
quarter, there was no mission from the World Bank.
The Technical and Financial Audit Consultant (TFAC) mission took place on 4, October 2016
until 6, October 2016 and 22, November 2016 until 24, November 2016 with site visit
inspection on Packages No.17, 7 respectively.
The Workshop meeting conducted by TFAC was held on 21, November 2016 for Packages
No.7, 12, 14, 16, 20.
An "Agreed Key Action Plans" for progress compliance monitoring of the status of the
works on monthly interval is shown in
Table 3
.
Table 3 Agreed Key Action and Plans
Status as of end of 4
th
Quarter (December 2016)
No.
Action
By Whom
New Deadline (s)
1.
Inform the WB if the Contractor can finish the package 16
within 2017.
PPK through
PMU and CTC.
January 30, 2017.
2.
Send to the WB informally the proposed contract
modification for package 03.
PMU and CTC.
December 14, 2016.
3.
Issue a NOL to the contract modification for time extension
for package 05.
WB.
December 23, 2016.
4.
Inform the WB about the contract modification to include the
additional drainage and accesses to houses in package 06
(contact finishes on January 28, 2017).
PPK through
PMU and CTC.
December 30, 2016.
5.
Inform the WB if the Contractor of package 13 was able to
comply with 400 m3 of quarry material production per day.
PMU and CTC.
January 16, 2017.
6.
Inform the WB if the Contractor of package 15 was able to
achieve 20% of cumulative progress by the end of 2016.
PMU and CTC.
January 16, 2017.
7.
Inform the WB after completion of field engineering if
package 20 can be completed within 2017; and what Bina
Marga will do considering that this package is in good
condition.
PMU and CTC.
January 10, 2017.
8.
Submit to the WB the proposal evaluation report for the
slope stabilization, design, and management.
PMU and CTC.
January 11, 2017.
9.
Send to the WB the #2 DSC contract modification for price
escalation.
PMU and CTC.
January 30, 2017.
10.
Send to the WB formally the request for NOL to CTC contract
amendment No. 5.
PMU and CTC.
December 15, 2016.
11.
Send to the WB the environmental management and
monitoring plans (RKPPLs) for packages 07, 14, and 20 to the
Bank.
PMU and CTC.
•
RKPPLs for
packages 07,
14, and 20:
December
30, 2016.
•
RKPPL Training
for package 16:
First week of
January 2017.
12.
Cary out HIV/AIDS workshops.
PMU/CTC/ DSC.
February 2017 for
packages
16, 20, and 21.
Send to the WB the final LARAP document for package 05
[image:13.595.72.542.332.786.2]2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
9
No.
Action
By Whom
New Deadline (s)
13.
comparison between the amount paid to affected people and
the amount due to them according to the appraisal, as well as a
list of remedial actions.
PMU and CTC.
December 15, 2016.
14.
Send to the WB the necessary clarification about the right of
use permission from the Forestry Department for the existing
road at package 05.
PMU and CTC.
January 16, 2017.
15.
Carry out remedial actions for the LARAP implementation of
package 05.
PMU.
March, 2017.
16.
Send to the WB the monitoring report of LARAP
implementation of package 05.
PMU.
March, 2017.
17.
Submit to the WB LARAP monitoring reports for packages 07,
08, 15, 20, and 21.
PMU.
•
Packages 07, 08,
and 21:
December 30,
2016.
•
Packages 15,
and 20:
January 30,
2016.
18.
Completely follow up on the FY2015 audit findings, and
report to the WB.
PMU and CTC.
December 30, 2016.
19.
Submit to the WB the quarterly IFR for the period October to
December, 2016.
PMU.
February 15, 2016.
20.
Send to the WB the TFAC response for packages 03, 05, 06,
07, 11, 13, 15, and 17.
PMU/DSC/
CTC.
•
Package 03:
January 10,
2017.
•
Package 05:
January 10,
2017.
•
Package 06:
December
16, 2016.
•
Package 07:
January 23,
2017
•
Package 11:
January 04,
2017.
•
Package 13:
January 10,
2017.
•
Package 15:
January 10,
2017.
•
Package 17:
January 24,
2017.
21.
Upload the mid-term review report on WINRIP website
(please send link to the Bank).
PMU/CTC.
January 31, 2017.
22.
Submit to the WB the 2015 IRMS traffic data for the 19 road
packages.
PMU/CTC.
December 30, 2016.
23.
Submit regularly to the WB the quarterly progress reports.
PMU.
This activity must be
carried out every
calendar quarter.
24.
Update the newsletter quarterly, including the list of
contracts, implementation progress, project related
workshops, and number, typology and status of complaints.
PMU.
This activity must be
carried out every
calendar quarter.
2.6
Project Steering Committee Meeting
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
10
3
Project Management and Implementation
3.1
Procurement Status
(A) Civil Works
Civil Works are now being implemented in Annual Work Programs (AWP) which have
been numbered AWP-1, AWP-2, and AWP-3.
All Contract Agreements for the four (4) AWP-1 contract packages were signed by the
end of 2013 with actual work commencement on January 2014.
[image:15.595.137.525.343.736.2]Under the other two (2) implementation programs, AWP-2 and AWP-3, fourteen (14)
packages were already procured.
Table 4
Shows the actual pre-construction and procurement status under the
implementation schedules AWP-2 and AWP-3
Table 4
Package
No.
Package Name
Status
AWP-2
5
Sp. Rampa - Poriaha
Procured. Under construction since the issuance
of Notice To Proceed (NTP) on June 18, 2015
6
Ps. Pedati - Kerkap
Procured. Under construction since the issuance
of Notice To Proceed (NTP) on March 11, 2015
7
Indrapura
Tapan
Procured. Under construction since the
issuance of Notice To Proceed (NTP) on
December 10, 2015
8
Bts. Pariaman
Manggopoh
Procured.
Under
construction
since
the
issuance of Notice To Proceed (NTP) on March
23, 2016
10
Sp. Empat
Sp. Air Balam
Cancelled . The road is still in relatively in good
condition and widening is not needed
immediately.
11
Bantal - Mukomuko
Procured. Under construction since the issuance
of Notice To Proceed (NTP) on February 23,
2015
12
Kambang
Indrapura
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
11
Package
No.
Package Name
Status
13
Sp. Rukis
Tj. Kemuning
Procured. Under construction since the
issuance of Notice To Proceed on July 22,
2015
AWP-3
14
Painan
Kambang
Procured. Under construction since the issuance
of Notice To Proceed on August 3, 2016
15
Sibolga
Bts. Tapsel
Procured. Under construction since the issuance
of Notice To Proceed (NTP) on November 20,
2015
16
Seblat - Ipuh
Procured. Under construction since the issuance
of Notice To Proceed on November 8, 2016.
17
Sp.Gn.Kemala
Pg. Tampak
Procured. Under construction since the issuance
of Notice To Proceed (NTP)on September 4,
2015.
19
Lais
Bintunan
Procured. Construction completed. Under
Defect Notification period for 730 days.
20
Lubuk Alung
Sicincin
Procured. Under construction since the issuance
of Notice To Proceed on September 1, 2016.
21
Lubuk Alung - Kuraitaji
Procured. Under construction since the issuance
of Notice To Proceed on September 1, 2016.
Note : Packages No.9 and No.18 are cancelled from the program.
Presented in
Appendix 4
is the current status of procurement management.
(B) Services
The Core Team (CTC), Design & Supervision Consultant (DSC), and the others Capacity
Building Consultancy status are discussed in Section 3.4.
3.2
Implementation Status
Civil Works
As of end of this reporting quarter (December 2016), five (5) of contract packages were
already completed and currently under defects liability period for seven hundred and thirty
(730) days effective on the day the TOCs were issued.
Thirteen (13) packages are on-going construction. Details of each contract package are
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
[image:17.842.56.813.100.518.2]Western I ndonesia National Roads I mprovement Project
12
Table 5
Program
Contract
Package
#
Contractor
Name of Road
Province
Contract
Signed
Commence
ment of
Work
Original
Time
Extension
Revised
Contract
Amount
Contract
Time
Completion
Date
Contract Amount
Contract
Time
Completion
Date
AWP-1
1
PT. Jaya Konstruksi
Manggala Pratama Tbk
Biha - Krui
Lampung
Nov 25,
2013
Jan 8, 2014
134,909,211,000
640 CD
Oct 9, 2015
93 CD
140,255,020,000
733 CD
Jan 20, 2016
2
PT.Jaya Konstruksi Manggala
Pratama Tbk
Padang Sawah
Sp. Empat including
Air Gadang
West
Sumatera
Dec 6, 2013
Jan 6, 2014
197,936,699,000
730 CD
Jan 5, 2016
105 CD
249,348,931,000
835 CD
Apr 14,
2016
3
PT. Jaya Konstruksi
Manggala Pratama Tbk
Manggopoh
Padang Sawah
West
Sumatera
Dec 6, 2013
Jan 6, 2014
143,688,963,000
730 CD
Jan 5, 2016
75 CD
183,940,872,000
805 CD
Mar 17,
2016
4
PT. Waskita Karya and PT.
Mulya Turangga (JO)
Ipuh - Bantal
Bengkulu
Nov 14,
2013
Jan 13, 2014
186,936,750,000
730 CD
Jan 12, 2016
90 CD
194,902,179,000
820 CD
May 31,
2016
AWP-2
5
PT. Nusa Konstruksi
Enjiniring Tbk.
Sp. Rampa
-Poriaha
North
Sumatera
March 17,
2015
June 18,
2015
107,321,260,310
540 CD
Dec 8, 2016
-
107,321,260,310
764 CD
Jul 20, 2016
6
PT. Waskita Karya (Persero)
Tbk.
Ps. Pedati - Kerkap
Bengkulu
Feb 27,
2015
Mar 11,
2015
86,517,470,000
450 CD
Jun 2, 2016
240 CD
118,444,156,000
690 CD
Jan 28, 2017
7
PT. Adhi Karya
Indrapura
Tapan
West
Sumatera
Nov 26,
2015
Dec 10,
2015
129,699,900,000
630 CD
Aug 30,
2017
-
-
-8
PT. PP/PT. Statika Mitra
Sarana J.O
Bts. Kota Pariaman
- Manggopoh
West
Sumatera
Jan 28, 2016
Mar 23,
2016
355,500,000,000
720 CD
Mar 12,
2018
- 71 CD
649 CD
Dec 31,
2017
11
PT. Hutama Karya/PT. Daya
Mulya J.O.
Bantal
Mukomuko
Bengkulu
Dec 18,
2014
Feb 23,
2015
228,899,717,000
720 CD
Feb 11,
2017
-262,611,303,000
-
-12
PT. Lancar Jaya/PT. Cahaya
T.A. J.O
Kambang
Indrapura
West
Sumatera
Jan 28, 2016
May 23,
2016
358,650,400,000
720 CD
May 12,
2018
-116 CD
604 CD
Jan 16, 2018
13
PT. Waskita Karya (Persero)
Tbk.
Sp. Rukis
TJ.
Kemuning
Bengkulu
Dec 18,
2014
July 22,
2015
292,700,000,000
720 CD
July 10,
2017
-
-
-AWP-3
14
PT. Yasa Patria
Perkasa/Conbloc, JO
Painan
Kambang
West
Sumatera
Jun 1, 2016
Aug 3, 2016
214,327,429,680
630CD
Apr 12,
2018
-114 CD
-
516 CD
Dec 31,
2017
15
PT. Pembangunan
Perumahan (Persero)
Sibolga
Bts.
Tapsel
North
Sumatera
July 13,
2015
Nov 20,
2015
260,100,000,000
810 CD
Feb 6, 2018
- 37 CD
773 CD
Dec 31,
2017
16
KSO PT Yasa PP-Multi
Structure
Ipuh - seblat
Bengkulu
Oct 28, 2016
Nov 8, 2016
211,374,500,000
630CD
July 30,
2018
--
-17
PT. Jaya Konstruksi
Manggala Pratama Tbk
Sp. Gunung Kemala
Pugung Tampak
Lampung
Nov 17,
2014
Sept 4, 2015
199,551,000,000
720 CD
Aug 23,
2017
-
-
-19
PT. Roda Tekindo Purajaya
Bintunan - Lais
Bengkulu
Feb 27,
2015
Mar 11,
2015
33,689,452,000
300 CD
Jan 4, 2016
125CD
44,419,760.000
425CD
June 30,
2016
20
PT. Nindya Karya
Lubuk Alung
Sicincin
West
Sumatera
Jun 1, 2016
Sept 1, 2016
113,818,300,000
540CD
Feb 22,
2018
- 54 CD
-
486 CD
Dec 31,
2017
21
PT. Multi Structure
Lubuk Alung
Kuraitaji
West
Sumatera
Jun 1, 2016
Sept 1, 2016
126,301,900,000
540CD
Feb 22,
2018
- 54 CD
-
486 CD
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
13
Activities done during the 4
th
Quarter of 2016 were repair and restoration of deteriorated
existing pavements, roadway excavation, embankment formation, spreading of granular
pavement for roadway widening, asphalt paving, structural works, construction of stone
masonry side ditches, stockpiling of raw material, production of crushed aggregates, other
minor works, bridge construction, finalization of
Field Engineering
surveys and
mobilization of resources of the newly started contract packages.
The four (4) contract packages under implementation program AWP-1 were already
completed and now under defects liability period for two (2) years since the issuance of
TOCs.
Under the implementation program AWP-2 and AWP-3, there are currently thirteen (13)
contract packages that are on-going construction implementation and one (1) package on
AWP-3 is already completed. Physical progress of three (3) of the packages are lagging far
behind schedule with negative slippages of 23.92%, 14% and 12.78% respectively, while
progress for the other ten (10) packages are still slightly on or behind schedule.
Progress status of the on-going civil works contracts as of this reporting period are shown in
Table 6
.
Following are brief status of the on-going construction contract packages :
Package No. 1 : Biha
Krui
The contract package is completed on January 20, 2016 and provisionally handed over to the
Employeer and currently under Defects Notification Period until after two (2) years
reckoned from the issuance of the TOC.
A more detailed previous status during the whole duration of the contract implementation
of this Package is presented in
ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah
Sp. Empat (Including Air Gadang Bridge)
The contract package is completed on April 14, 2016 and provisionally handed over to the
Employeer and currently under Defects Notification Period until after two (2) years
reckoned from the issuance of the TOC.
ANNEX P-2 Executive Summary Report
present a more detailed status during the whole
duration of the contract implementation of the Contract Package.
Package No. 3 : Manggopoh
Padang Sawah
The contract package is completed on March 17, 2016 and provisionally handed over to the
Employeer on March 17, 2016 and currently under Defects Notification Period until after
two (2) years reckoned from the issuance of the TOC.
A more detailed status of the project progress during the whole duration of the contract
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
[image:19.842.54.815.87.518.2]Western I ndonesia National Roads I mprovement Project
14
Table 6
Program
Contract
Package
#
Contractor
Name of Road
Target Progress
Schedule Ending
December 2016
Actual Progress
Accomplished
Slippage
Time Elapsed
Remaining
Time
Remarks
AWP-1
1
PT. Jaya Konstruksi Manggala
Pratama Tbk
Biha - Krui
*
-
-
-
-Completed
PHO : Jan 20, 2016
2
PT. Jaya Konstruksi Manggala
Pratama Tbk
Padang Sawah
Sp.Empat incl.Air Gadang
*
-
--
-
-Completed
PHO : April 14, 2016
3
PT. Jaya Konstruksi Manggala
Pratama Tbk
Manggopoh
Padang
Sawah
*
-
-
-
-Completed
PHO : Mar 17, 2016
4
PT. Waskita Karya and PT.
Mulya Turangga (JO)
Ipuh - Bantal
*
-
-
-
-Completed
PHO : May 31, 2016
AWP-2
5
PT. Nusa Konstruksi Enjiniring
Sp. Rampa - Poriaha
41.99%
42.73%
0.74%
72.87%
207 CD
Based on revised contract time
and schedule
6
PT. Waskita Karya Tbk
Ps. Pedati
Kerkap
96.07%
91.23%
-4.84%
95.07%
34 CD
Based on 2nd revised contract
time and schedule
7
PT. Adhi Karya
Indrapura - Tapan
43.74%
39.21%
-4.53%
60.57%
248 CD
Based on original contract
time and schedule
8
PT. PP/PT. Statika Mitra J.O
Bts. Kota Pariaman
Manggopoh
30.85%
32.15%
1.30%
42.75%
371 CD
Based on original contract
time and schedule
11
PT. Hutama Karya/ PT. DMT
Mukomuko - Bantal
96.19%
86.28%
-9.91%
93.32%
48 CD
Based on original contract
time and revised schedule
12
PT. Lancarjaya/PT. Cahaya
T.A. JO
Kambang
Indrapura
9.39%
4.02%
-5.37%
36.80%
371 CD
Based on original contract
time and revised schedule
13
PT. Waskita Karya (Persero)
Tbk
Sp. Rukis
Tj. Kemuning
77.66%
32.63%
-45.03%
72.60%
197 CD
Based on original contract
time and schedule
AWP-3
14
PT. Yasa
PT. Conbloc (JO)
Painan
Kambang
5.87%
3.94%
-1.92%
27.96%
371 CD
Based on revised contract
time and schedule
15
PT. Pembangunan
Perumahan (Persero)
Sibolga
Bts. Tapsel
44.45%
20.52%
-23.93%
51.94%
371 CD
Based on revised contract
time and schedule
16
PT Yasa-Multi Structure, Jo
Seblat Ipuh
0.26%
0.26%
-
92.53%
582 CD
17
PT. Jaya Konstruksi Manggala
Pratama Tbk
Sp. Gn Kemala
Pg.
Tampak
54.12%
41.34%
-12.78%
66.48%
241 CD
Based on original contract
time and schedule
19
PT. Rodatekindo Purajaya
Lais - Bintunan
100%
100%
-
-
-
Completed
PHO : June 30, 2016
20
PT. Nindya Karya
Lubuk Alung
Sicincin
12.38%
13.60%
1.22%
23.66%
371 CD
Based on revised contract time
21
PT. Multi Structure
Lubuk Alung
Kuraitaji
9.86%
3.25%
-6.61%
23.66%
371 CD
Based on revised contract time
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
15
Package No. 4 : Ipuh
Bantal
The contract package is completed on May 31, 2016 and provisionally handed over to the
Employeer on May 31, 2016 and currently under Defects Notification Period until after
two (2) years reckoned from the issuance of the TOC.
Shown in
ANNEX P-4 Executive Summary Report
showing the details and status of the
project.
Package No. 5 : Sp. Rampa
Poriaha
Based on the revised schedule approved on 23, November 2016. As of the end of this
month, the actual work progress is 41.99% of the scheduled 42.72%. The balanced +0.74%
progress is achieved.
ANNEX P-5 Executive Summary Report
shows the Contractor s Progress Schedule.
Package No. 6 : Kerkap
Ps. Pedati
Based on the 2
nd
revised progress schedule, the actual work progress is 91.23% which is still
behind schedule by -4.84% balancing from the scheduled 96.07%.
Basically the only remaining major work item to be completed is the asphalt pavement
which is 60.39% component of the whole contract and the end of this period, 57.63% of the
works is already completed with still 2.76% to be done.
For the Contractor to accomplish with the revised completion date on January 28, 2017.
The remain 8.77% is to be done as of the completion date of which the rest of calendar
days are about one month.
ANNEX P-6 Executive Summary Report
shows the complete details of the contract
package.
Package No. 7: Indrapura
Tapan
During this month, the Contractor is trying to stabilize and balancing the progress, however
the actual overall progress is still less on schedule by -4.53%, mainly due to the inclement
weather conditions.
Barring any unforeseen circumstances that will interupt or disrupt the execution of the
works, the target date of completion on August 30, 2017 can be easily achieved, provided
the Contractor shall produce at least minimum 7.6% progress every month during the
remaining contract time of eight (8) months.
ANNEX P-7 Executive Summary Report
shows the complete details of the contract
package.
Package No. 8 : Bts. Kota Pariaman - Manggopoh
As the month ended, the overall actual work progress was achieved 32.15% which is ahead
of schedule by +1.30% relative to the progress schedule of 30.85%.
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
16
At this present, unsettled land acquisition appx. 6 km should be treated and handled as top
and urgent element maintaining the stable progress for this project.
ANNEX P-8 Executive Summary Report
shows the complete details of the contract
package.
Package No. 11 : Bantal - Mukomuko
Based on the revised schedule due to approval of the results of Field Engineering , the
actual overall progress attained by the Contractor up to end of this period is 86.28% against
96.19%.
During this month, the negative slippage rate is raised up to -9.81% comparing with -8.8%
of the previous month.
The reason for delayed progress was mainly due to the asphalt pavement works owing to
shortage of dust. (Abu Batu) and frequent broken-down of A/P finisher.
Base on the schedule, the remaining working month is only 2.6 months with 13.72% of the
remain work. Thus, the contractor have to accelerate their work forces on the asphalt
pavement works by means of increasing supply of agreegate materials, especialy Abu batu
and changing the main equipments in good conditions.
For more details of the Contract Package, refer to
ANNEX P-11 Executive Summary
Report
.
Package No. 12 : Kambang - Indrapura
From the commencement date to this month, the construction time has been elapsed of 8
months but the actual wrok progress to date is only 4.02% against 9.39%.
Delayed works are mosthly General, Earthwork, Granular Pavement and Structures.
Furthermore asphalt pavement works are not started so far.
The weight of work portion for asphalt pavement is to be more than 50% from the total of
works. Therefore, the contractor has been strongly adviced that the preparatory
arrangements for executing asphalt pavement works should be done as early as possible.
Details of the Contract Package are shown in
ANNEX P-12 Executive Summary Report
.
Package No. 13 : Sp. Rukis
Tj. Kemuning
During this month, the work progress is achieved of 9.86% per a month against 4.69%
scheduled.
Overall work progress to date is only 32.63% against 77.66% scheduled. Hence the slippage
rate of the progress is to become -45.03% which is considerably improved from the
previous month.
For this month progress has been leaded by the asphalt pavement affacted by more than
90% of this month overall progress.
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
17
catch-up the work progress of granular pavement to obtain the more working areas of the
next works, Asphalt Pavement.
Details of the work progress are shown in
ANNEX P-13 Executive Summary Reports.
Package No. 14: Painan - Kambang
The work progress up to this month is achieved of 3.94%, excepting asphalt pavement due
to the fault to apply the material on site of aggregate stones, etc as the work progress
which is not allowed by the contract, against 5.87% scheduled.
Aggregate stone materials are stockpiled in huge amount, accordingly it is expecting that
the next month progress is to be improved.
ANNEX P-14 Executive Summary Report
shows the complete details of the project.
Package No. 15: Sibolga
Bts. Tapsel
During this month, the work progress per a month is achieved of 7.28% against 6.95%
scheduled.
Overall work progress to date is only 20.52% against 44.45% scheduled. Hence the slippage
rate of the progress is to be -23.93% which is slightly less than the previous month -24.2%.
This month progress has been leaded by the asphalt pavement work mostly affacted by
more than 97% of this month overall progress.
In order to maintain the smooth progress in the future, the contractor has to improve and
catch-up the work progress for espicially Drainage, Earthworks, Granular pavement to
obtain the more working areas of the next work, Asphalt Pavement.
Detailed and work progress of the contract package are shown in
ANNEX P-15 Executive
Summary Report
.
Package No. 16 : Seblat
Ipuh
Notice to proceed (NTP) to commence the works has been issued on November 8,2016 and
pre construction meeting was held on November 14,2016 in Bengkulu City.
The mobilization of basecamp, construction equipment, manpower etc, is still on going.
Hence the contractor is not in the position to have financial progress up to this month.
Package No. 17 : Sp. Gunung Kemala
Pg. Tampak
Overall actual progress to date 41.43% against 54.12% scheduled. Progress slippage rate to
date has became bigger -12.78% against 7.87% of the last month.
Delayed work progress is mainly due to the Asphalt pavement, Pavement widening &
Shoulder, Granular pavement and Drainage.
However an einclement weather condition in the rainny season could be a reason for
delaying progress, the contractor s construction management is to be one of the main
element, for delay either.
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
18
of the project.
Package No. 19 : Lais
Bintunan
The contract package is completed on June 30, 2016 and provisionally handed over to the
employer and currently under Defects Notification Period until after two (2) years
reckoned from the issuance of the TOC
Complete details of the contract package are shown in
ANNEX P-19 Executive Summary
Report
Package No. 20 : Lubuk Alung - Sicincin
Since NTP issued on September 1, 2016, the mobilization of construction equipments and
manpowers of the Contractor are likely to accomplish and espicially development at their
own quarry site, located in adjacement area of the existing main road, 8 km far from the
Project end point, Instaling AMP & crushing plant in the quarry as wall could be a good
element to keep a constant progress during the construction.
At September that site construction management and traffic control of the contractor have
to be improved more, actively and maintained by means of establishing feasible working
methods, work sequeuces before starting of the works.
The progress of this month was achieved 13.60% againts 12.38% schedule, thus fairly ahead
of +1.22%.
ANNEX P-20 Executive Summary Report
shows the Contractor s schedule and work
progress.
Package No. 21 : Lubuk Alung - Kuraitaji
Since NTP issued on September, 1, 2016, the mobilization of construction equipments,
AMP, Crusher plant etc, have been done fairly, but in spite of a huge quantities of drainage
works, work forces, manpower, sub-contractors for the drainage works are much
insufficient.
The Contractor has to mobilize the working teams much more than the present for the
drainage work to obtain more working areas for the next works, like granular pavement,
Asphalt pavement in order to catch-up the very delayed progress, -6.61% slippage
comparing with actual 3.25% and scheduled 9.86%.
ANNEX P-21 Executive Summary Report
shows the Contractor s schedule and work
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
19
3.3
Variation Order Details
To date, amendements and/or variation orders for six (6) construction contract packages
were already processed and approved by Pejabat Pembuat Komitmen (PPK), the
authorize Office to approve financial disbursement.
The approved variations orders were due to the following reasons :
a) Change of Engineer s Team Leader from V. Thiagarajah to Johnson Villar.
b) Change of PPK Sub Project Manager.
c) Contract amount revision due to Technical Justification of Field Engineering
results.
d) Revision of time for completion (time extension).
e) Contract amount revision due to contract price adjustment (escalation of unit
rates).
f)
Change of Contractor s authorize representative.
g) Deletion of unspent provisional sum amounting to Rp. 7.1 Billion and balancing of
quantity overruns/underruns.
h) Final Quantity.
i)
Change Bank Account
In regards with additive/deductive cost variations, original cost of the six (6) construction
contract packages increases by Rp. 149,417,273,000 while the variation orders for the
other contract packages are still under evaluation by DSC and PPK which is expected that
the results will increase the respective original contract amounts.
In anticipation of future claims for varied works by the Contractors, a revised costs of
additional 11% of the Original Cost for each contract package covered by AWP-1 has been
considered and 6% cost increases for packages under AWP-2 and AWP-3 to cover any
Variation Orders that may arise during the implementation of the Works.
Presented in
Table 7
are details of Variation Orders for the four (4) sub-projects under
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
[image:25.595.51.572.94.663.2]Western I ndonesia National Roads I mprovement Project
20
Table 7
Details of Amendments (Variation Orders)
Reason For Change :
A
Change of Engineer s Team Leader from V. Thiagarajah to Johnson Villar.
B
Change of PPK Sub Project Manager.
C
Contract amount revision due to Technical Justification of Field Engineering results.
D
Revision of time for completion (time extension).
E
Contract amount revision due to contract price adjustments (escalation).
F
Change of Contractor s authorize representative.
G Deletion of unspent provisional sum amounting to Rp. 7.1 Billion and balancingof quantity overruns/underruns.
H Final quantity (overuns/underruns).
I
Change Bank Account.
Package
No.
Original Contract
Amount
(Rp)
Amend
No.
Variation
+/-(Rp)
Revised Contract
Amount
(Rp)
Variance
%
Time
Extension
Reason For
Change
1
134,909,211,000
1
0
134,909,211,000
0
-
A
2
+19,163,804,000
154,073,015,000
+14.20
-
C
3
0
154,073,015,000
+14.20
-
B
4
0
154,073,015,000
+14.20
93
D
5
-13,817,995,000
140,255,020,000
+3,96
-
G
2
197,936,699,000
1
0
197,936,699,000
0
-
A
2
0
197,936,699,000
0
-
F
3
0
197,936,699,000
0
-
B
4
+28,776,518,000
226,713,217,000
+14.54
-
C
5
0
226,713,217,000
+14.54
105
D
6
+22,635,714,000
249,348,931,000
+25.97
-
E
3
143,688,963,000
1
0
143,688,963,000
0
-
A
2
0
143,688,963,000
0
-
F
3
0
143,688,963,000
0
-
B
4
+21,468,809,000
165,157,772,000
+14.94
-
C
5
0
165,157,772,000
+14.94
75
D
6
+18,783,100,000
183,940,872,000
+28.01
-
E
4
186,936,750,000
1
0
186,936,750,000
0
-
A
2
+9,501,334,000
196,438,084,000
+5.08
-
C
3
0
196,438,084,000
+5.08
-
B
4
0
196,438,084,000
+5.08
90
D
5
-1,535,905,000
194,902,179,000
+4.26
-
H
5
107,321,260,000
1
0
107,321,260,000
0
-
A
2
0
107,321,260,000
0
+224
D
8
355,500,000,000
1
0
355,500,000,000
0
-81
D
2
0
355,500,000,000
0
-
C
11
228,899,717,000
1
0
228,899,717,000
0
-
B
2
+33,711,586,000
262,611,303,000
+14.73
-
C
12
358,650,400,000
1
0
358,650,400,000
0
-132
C&D
13
292,700,000,000
1
0
292,700,000,000
0
-
I
2
0
292,700,000,000
0
-
B
3
0
292,700,000,000
0
-
F
4
0
292,700,000,000
0
-
C
5
0
292,700,000,000
0
-
C
14
214,322,429,000
1
0
214,322,429,000
0
-114
C&D
15
260,100,000,000
1
0
260,100,000,000
0
-37
C&D
17
199,551,233,000
1
0
199,551,233,000
0
-
C
19
33,689,452,000
1
0
33,689,452,000
0
-
B
2016 Quarterly Progress Report
4
th
Quarter : October-November-December
Western I ndonesia National Roads I mprovement Project
21
3.4
Consultancy Services
Technical Assistance for Core Team Consultant (CTC) to Support the Project
Management Unit.
Lead Consultant: PT. Perentjana Djaja
CTC Contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 Nov 2012 between
the Ministry of Public Works , Directorate of Planning, DGH and PT. Perentjana Djaja,
Yongma Engineering Co. Ltd, PT. Epadascon Permata Engineering Consultant, JV and the
work commenced on 12 November 2012.
Amendment No.1 to original contract was signed on October 25, 2013.
Amendment No. 2